County Asphalt, Inc. v. State

63 Misc. 2d 329, 311 N.Y.S.2d 650, 1969 N.Y. Misc. LEXIS 1010
CourtNew York Court of Claims
DecidedDecember 9, 1969
DocketClaim No. 42891
StatusPublished
Cited by1 cases

This text of 63 Misc. 2d 329 (County Asphalt, Inc. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County Asphalt, Inc. v. State, 63 Misc. 2d 329, 311 N.Y.S.2d 650, 1969 N.Y. Misc. LEXIS 1010 (N.Y. Super. Ct. 1969).

Opinion

Johit P. GrUALTiEEi, J.

This is a claim for damages arising out of a highway construction contract between the claimant and the State, dated October 21, 1960, which provided for the construction of 5.42 miles of roadway on Interstate Route 502 in Clinton County for the sum of $2,165,588.50.

The proposal was given out to prospective bidders on August 31,1960. The bids were to be submitted by September 21, 1960, giving the bidders a period of approximately three weeks within which to study the details contained in the proposal and make such physical investigations and studies as were possible to make within the allotted time.

It cost the claimant $536,320.19 in excess of the contract price to complete the job. It is the contention of the claimant that this substantial additional cost was brought about because of the misrepresentation of quantities of Item 2-S of the contract, that the State withheld from bidders material physical facts known to it and its representatives, that it improperly altered quantity estimates under the 2-S category and that it compelled the claimant to use a substantial amount of material nowhere mentioned in the proposal. It is claimed that by reason of the State’s conduct the claimant was mislead and deceived and that when it entered into the performance of the contract it was confronted with conditions which resulted in its having been obliged to perform an entirely different contract than that upon which it was invited to bid.

While the State gave out the proposal in 1960, its engineers and surveyors had been engaged in making detailed physical studies of the area embraced in the contract since 1957. These preliminary studies indicated that there would be required 1,550,000 cubic yards of unclassified excavation in Item 2-S. This estimate was given in May of 1957. The State, in order to reduce the estimated cost of the job, asked the engineers to revise their estimates. In October of the same year they so altered their figures that they came up with an estimated figure of 823,037 cubic yards of unclassified excavation. In the original quantities given in May of 1957, a quantity of Item 2-EC, select borrow, was provided for. In the revised figures given in October not only was the estimated quantity of unclassified excavation reduced by almost one half but the 2-EC material was not mentioned at all.

It may be well at the outset, in order to understand and evaluate the claimant’s contentions, to set forth the quantities contained in the proposal and the actual quantities found to be required when the job was completed. They are as follows:

[331]*331Contract Actual

Estimates Quantities

Unsuitable material including

stripping and topsoil.......... 89,819 c.y. 224,722 c.y.

Bock Excavation .............. . 15,656 c.y. 22,163 c.y.

Common Borrow.............. . 686,869 c.y. 482,986 c.y.

Common Excavation........... 29,004 c.y. 48,208 c.y.

821,348 c.y. 778,129 c.y.

However, in addition to the 778,129 cubic yards actually found to be required, the claimant was directed to furnish an item, 2-EC, select borrow, a more expensive and superior material not mentioned in the proposal at all. By the time the job was completed the claimant had to provide 501,518 cubic yards of this material, almost one half of the total quantities furnished under 2-S, which gives weight to the claimant’s position that after it signed the contract it was called upon to perform an entirely different contract than that envisioned in the proposal.

The ultimate actual quantities found to be required under Item 2-S, including the 501,518 cubic yards of 2-EC material not mentioned in the contract, totaled 1,279,647 cubic yards which, as estimates go, was closer to the original May, 1957 estimates of 1,500,000 cubic yards.

It is obvious that the necessity for the claimant’s furnishing 501,518 cubic yards of 2-EC, not mentioned in the contract, caused the wide variation in the other quantities contained in the other portions of Item 2-S.

This brings us to a consideration of whether or not this case falls within that line of established decisions that hold that a bidder must not rely upon preliminary estimates, that he must submit his bid based upon the estimates contained in the proposal and that the State is not liable in damages if there should later be found to be a radical variance in the estimates and the actual quantities found to be needed. A unit price is fixed in the contract and the contractor is bound by the unit price to which he agreed when he signed the contract whatever the quantities involved. (Yonkers Contr. Co. v. New York State Thruway Auth., 25 A D 2d 811, affd. 23 N Y 2d 856; Johnson Corp. v. City of New York, 162 Misc. 665, affd. 251 App. Div. 811, mot. for lv. to app. den. 276 N. Y. 688; Depot Constr. Corp. v. State of New York, 23 A D 2d 707, affd. 19 N Y 2d 109.)

Here, however, we have a different situation. When it signed the contract claimant had no opportunity to set a price for which [332]*332it was willing to furnish Item 2-EC because this select material was nowhere referred to in the proposal. The rule that a contractor is bound by the unit price established in the contract, whatever the quantities, has no application here.

By omitting from the proposal any mention of Item 2-EC the State misrepresented a very substantial, almost one half, of the type of material required under Item 2-S of the contract and misrepresented to a prospective bidder the nature of the contract to be performed at a time when the bidder was planning his material sources, equipment and work schedules.

The State knew all along that Item 2-EC would be required. It was indicated in the initial investigations as early as May of 1957. It admits that the omission of this material from the proposal was due to careless procedures on the part of the officials responsible for the preparation of the proposal. In a memorandum dated January 21, 1961 which seeks to explain the reason for the omission of Item 2-EC from the proposal, appears the following language: “It would seem a very advantageous practice if the plans and work-ups of the various consultants could be reviewed by the members of the interested district, at least two weeks before the final * * * bid offerings to bidders. In this way other persons who have had experience in this line of work could have a chance to see what had been worked up and possibly offer a few constructive suggestions ”. Also, in Exhibit 10, which was Supplemental Agreement No. 3, sheet 2 of 9, a State official in explaining the reason for the omission of 2-EC material used the following language: 1 ‘ Under similar conditions in Interstate contracts both north and south of this project, Item 2EC was specified for replacing removed muck and humus. The item was inadvertently omitted from this contract.”

The State does not claim that this omission was due to unknown physical conditions resulting in an honest mistake on its part for which it could not be held legally responsible. (Johnson Corp. v. City of New York, 162 Misc. 665, affd. 251 App. Div. 811, mot. for lv. to app. den. 276 N. Y. 688.)

It appears that it was omitted, the State says, ‘1 inadvertently ’ ’, with full knowledge that this material would be required.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County Asphalt, Inc. v. State
40 A.D.2d 26 (Appellate Division of the Supreme Court of New York, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
63 Misc. 2d 329, 311 N.Y.S.2d 650, 1969 N.Y. Misc. LEXIS 1010, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-asphalt-inc-v-state-nyclaimsct-1969.