Arthur A. Johnson Corp. v. City of New York

162 Misc. 665, 295 N.Y.S. 547, 1936 N.Y. Misc. LEXIS 1674
CourtNew York Supreme Court
DecidedJune 13, 1936
StatusPublished
Cited by2 cases

This text of 162 Misc. 665 (Arthur A. Johnson Corp. v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arthur A. Johnson Corp. v. City of New York, 162 Misc. 665, 295 N.Y.S. 547, 1936 N.Y. Misc. LEXIS 1674 (N.Y. Super. Ct. 1936).

Opinion

Shientag, J.

The plaintiff, a subway contractor, is suing the city of New York to recover damages arising out of the construction of a subway under Manhattan avenue in Brooklyn. The complaint sets forth several causes of action based on various claims against the city, all of which were disposed of at the trial except the claim referred to as No. 5, covered by the second cause of action. This claim arose as the result of the increased cost of [667]*667excavation due to the presence in the soil of what is known as “ hardpan.” It is alleged that the presence of hardpan was not shown on supplementary drawing D-15, which sets forth the results of test borings made by a contractor employed by the city. It is further alleged that the plaintiff relied upon the drawings, that they furnished the basis of the bid it made, and that the board of transportation knew that the material to be excavated was different from that shown on the drawings.

Candor obliges me to say that when, at the conclusion of the trial, I summarized the evidence and reserved decision on questions of law involved, I labored under a misapprehension concerning certain portions of the testimony. The views that I then expressed concerning the facts must, therefore, yield to those set forth in this opinion after a careful examination of the record.

The contract was advertised for letting on December 16, 1927, and bids were received December 30, 1927. It is what is commonly known as a unit price contract; it provided different fixed unit prices for earth excavation and for rock excavation. Earth excavation included all materials of whatever nature encountered, including boulders and filled ground, except boulders whose volume within the ordered net lines of excavation was one cubic yard or more each. Such boulders were classified as rock excavation and payment provided as such. The contract specifically provided that the city did not guarantee the correctness or completeness of the borings.

Section 203 of the standard specifications reads:

(a) In addition to the contract drawings mentioned in Section 2 of the Special Specifications, the Board has had prepared a set of maps and drawings, bearing the same seal and general title as the contract drawings, but designated as Supplementary Drawings. These supplementary drawings exhibit certain information which the Board has received from the Engineer and its boring contractor as to borings taken along portions of the route, the nature and position of surface railroads, monuments, water mains, gas and other pipes, sewers, electric subways, manholes, hydrants, catch basins and other surface, subsurface and overhead structures.

“ (b) In addition to the information which is indicated by the supplementary drawings referred to, the Board has in its possession copies of certain old maps of the Borough of Manhattan which show topographical conditions in said Borough at the time of the preparation of said maps.

(c) These supplementary drawings, maps, samples of materials taken in connection with test borings and certain information relative thereto may be seen at the office of the Engineer. They [668]*668are exhibited to the Contractor so that he may form his own judgment thereon and without any guarantee on the part of the Board as to their completeness or correctness. The Contractor may have copies (blueprints) of these supplementary drawings for such aid, if any, as may be derived from them on the payment of the cost of blueprinting.”

Section 204 of the standard specifications and article VIII of the contract provide that the unit prices include all unforeseen difficulties in connection with the prosecution of the work.

Section 200 of the standard specifications provides as follows:

“ Quality of Construction, (a) The Special and Standard Specifications and the contract drawings mentioned in the Special Specifications, taken in connection with the other provisions of this contract, are intended to be full and comprehensive, and to show all the work required to be done. But in a work of this character the soil and other conditions cannot be fully explored or determined in advance and it is therefore impossible either in advance to show all details or precisely to forecast all exigencies. The Special and Standard Specifications and the contract drawings are to be taken, therefore, as indicating the amount of work, its nature and the method of construction so far as the same are now distinctly apprehended.

“ (b) The Contractor shall construct and complete the Bail-road strictly in accordance with the requirements of these Special and Standard Specifications. If in these specifications or this contract or on the contract drawings any matter or thing requisite be not contemplated, mentioned, specified or indicated or otherwise provided for, nevertheless the same is deemed to be included and the Contractor shall do the same as part of the work hereunder at the unit prices for each class of work where, in the opinion of the Engineer, applicable or as provided in Item 150.”

The city resists payment of the claim on the ground that it furnished to the plaintiff and made available to it all information in the city’s possession, including contract drawings, supplementary drawings, inspectors' reports and the physical material (samples) referred to in the drawings; that the inspectors’ reports reflected what they found at the scene of operation, and that the drawings, in turn, accurately and completely reflected the contents of the inspectors’ reports. In other words, the city takes the position that it did not conceal any facts in its possession from the plaintiff and that it was not guilty of bad faith.

On the other hand, plaintiff argues that the reports of the inspectors were not accurate, that although they show that certain “ wash borings ” were made, no such borings were in fact made, [669]*669and that both the reports and the drawings failed to disclose the presence of hardpan, of the existence of which the inspectors knew or should have known, and that the knowledge of the inspectors is to be deemed the knowledge of the city.

It may fairly be found from the evidence that hardpan was not embraced within the contract definition of earth. Hardpan has been defined as a substance cementitious in character, a combination of impacted sand, gravel and clay. The substance has a significance well known to the city; it is distinguished from ordinary sand, gravel and clay, which is readily breakable although in combination. The distinction between hardpan and the ordinary combination of sand, gravel and clay was recognized by the city in connection with other borings not involved in this suit and in connection with other contracts.

On the basis of the record it is fair to assume likewise that the hardpan encountered was present when the borings were made in 1906 and in 1925. The thickness of the layers and their extent warrant this inference. The situation differs, therefore, from a case where water is encountered below the surface at a level other than that indicated on the borings, which discrepancy may be explained by artificial diversion caused by other excavating operations in the vicinity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County Asphalt, Inc. v. State
63 Misc. 2d 329 (New York State Court of Claims, 1969)
Rocell Construction Co. v. State
208 Misc. 364 (New York State Court of Claims, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
162 Misc. 665, 295 N.Y.S. 547, 1936 N.Y. Misc. LEXIS 1674, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arthur-a-johnson-corp-v-city-of-new-york-nysupct-1936.