McGovern v. City of New York

202 A.D. 361, 196 N.Y.S. 162, 1922 N.Y. App. Div. LEXIS 4903

This text of 202 A.D. 361 (McGovern v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGovern v. City of New York, 202 A.D. 361, 196 N.Y.S. 162, 1922 N.Y. App. Div. LEXIS 4903 (N.Y. Ct. App. 1922).

Opinions

Greenbaum, J.:

The action arises out of a contract dated August 3, 1916, made by the plaintiffs with the city of New York acting by the Public Service Commission for the construction of part of what is known as route 61, a part of the Broadway-Fourth Avenue Rapid Transit railroad.

The contract provided that the work to be done thereunder was to be completed on or before the 3d day of February, 1919, for the agreed sum of $4,194,797. The complaint is most voluminous. To a large extent it consists of evidentiary matter [363]*363reciting labor troubles, conditions and negotiations leading up to the alleged agreements upon which the claims of plaintiffs are based.

The alleged facts set forth in the three causes of action, which are attacked by the demurrer, are identical in substance and differ merely in respect of the measure of damages.

The action was commenced on February 3, 1920. The complaint was served on February 26, 1921. The complaint so far as it relates to the three causes of action under review alleges that at the time of the execution of the plaintiffs’ contract “ and continuously until June, 1918, and for a long period thereafter, there were twenty-eight (28) subway contracts ” outstanding and in the process of performance held by different contractors, and that the total amount agreed to be paid by the city under all of these contracts amounted to approximately $65,000,000, and. that in June, 1918, there remained undone and unperformed under these contracts work and materials aggregating at contract prices the sum of approximately $19,000,000.

It is alleged that at the times mentioned in the complaint the various subway contractors were associated together under a corporation known as the General Contractors Association, which acted for the plaintiff and the other contractors and in their behalf entered into collective agreements presumably with labor unions interested in subway construction for the purpose of safeguarding the contractors with respect to the wages to be paid for labor until the completion of the contracts.

It is further alleged that, despite these precautions taken by the contractors, “ certain classes of the workmen ” of the plaintiffs as well as of the other contractors demanded an increase in the wages over the then prevailing rate; that conferences were thereafter had not only with the workmen and the contractors, but with the chairman of the Public Service Commission, who advised the contractors to yield to the labor demands, as a result of which the workmen agreed to accept certain formulated increases in wages to be operative as to some of them during the year 1917 and as to others during 1917 and 1918; that these agreements were violated by the workmen in February, 1917; that conferences were again called; that the Public Service Commission insisted that the subway work must not be interrupted and that to .prevent its interruption the said last increase in the scale of wages demanded by said workmen should and must be granted and paid by plaintiffs and said other contractors, respectively, for the future in order to avert a strike, * * * and that there was a way and a way would be found on the part of the defendant and said Commission [364]*364for the defendant to assume and pay, and that the defendant would assume and pay or repay to plaintiffs and said other contractors, respectively, the amount of the increases in cost occasioned, as above stated, or which in the future would be occasioned or caused plaintiffs and said other contractors respectively by the last-mentioned increase in wages demanded, in case the same was put into effect and paid,” and that said “ Commission further stated and assured plaintiffs and said other contractors, respectively, then and theretofore that in its judgment a declaration of a state of war was then imminent between the United States and the Imperial German Government, and that the declaration and existence of such a war would probably further add to the increase in cost both of labor and materials in the prosecution of said subway work; that the “ Commission would endeavor to procure or co-operate with said contractors in procuring legislation giving the defendant, if necessary, added and adequate power and authority to pay, repay or reimburse said plaintiffs and said other contractors, respectively, for the increased cost occasioned by compliance, on their part, with said last • demand for an increase and said prior increases paid by them, as well as any future increase in cost that might thereafter arise in the event of said declaration or existence of a state of war and due to it or to any increased labor inefficiency following the same; ” that finally the plaintiff and the other contractors yielded to the wishes of the Public Service Commission and modified their former agreement with their workmen respecting wages; that notwithstanding that the plaintiff and the other contractors had yielded again to the demands of their workmen a further demand for a large increase in wages was made after the United States was drawn into the World War; that the workmen insisted that said increase must be paid to them from and after May 15, 1918, and served notice on plaintiffs and said other contractors, respectively, and also on the Board of Estimate of defendant and on said Commission that if said demand was not complied with and said increase not granted and put into effect and paid from and after said date, they, said workmen, would strike and stop all further construction work'; but plaintiffs and said other contractors, respectively, refused to meet said demand or pay said increase, because said demand was in violation and disregard of the provisions of said agreements with said workmen above mentioned, and also because said demand exceeded the then prevailing rate of wages in New York and its vicinity in subway and similar work, and at the same time labor had become and was much less efficient, either in consequence of its scarcity or of conditions following the war, and further that plaintiffs and said [365]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leahy v. . Fairlie
126 N.E. 913 (New York Court of Appeals, 1920)
Matter of Mahon v. . Bd. of Education
63 N.E. 1107 (New York Court of Appeals, 1902)
Gordon v. . State of New York
134 N.E. 698 (New York Court of Appeals, 1922)
De Cicco v. . Schweizer
117 N.E. 807 (New York Court of Appeals, 1917)
Leahy v. Lucius Engineering Co.
186 A.D. 354 (Appellate Division of the Supreme Court of New York, 1919)
Boret v. L. Vogelstein & Co.
188 A.D. 605 (Appellate Division of the Supreme Court of New York, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
202 A.D. 361, 196 N.Y.S. 162, 1922 N.Y. App. Div. LEXIS 4903, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgovern-v-city-of-new-york-nyappdiv-1922.