Oscar Daniels Co. v. City of New York

196 A.D. 856, 188 N.Y.S. 716, 1921 N.Y. App. Div. LEXIS 5622
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 27, 1921
StatusPublished
Cited by7 cases

This text of 196 A.D. 856 (Oscar Daniels Co. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oscar Daniels Co. v. City of New York, 196 A.D. 856, 188 N.Y.S. 716, 1921 N.Y. App. Div. LEXIS 5622 (N.Y. Ct. App. 1921).

Opinion

Laughlin, J.:

The action is for an alleged balance due and owing to the plaintiff for work, labor and services performed and materials furnished under a contract made between the plaintiff and defendant on the 13th of September, 1911, for the construction of section No. 12 of route No. 5 of the Lexington avenue subway from a point 70 feet south of One Hundred and Sixth street to a point 115 feet south of One Hundred and Fifteenth street. It is not disputed that the contractor fully performed the contract. The points in controversy do not, as is often the case, relate to work required to be done or materials required to be furnished which the contractor claimed it was not obligated by the contract to perform or furnish (See People ex rel. Cranford Co. v. Willcox, 153 App. Div. 759; affd., 207 N. Y. 743), but solely to the amount to which the plaintiff was entitled according to the provisions of the contract which prescribed that payment should be made according to specified unit bases. The points upon which we are asked to review the trial and reverse the judgment relate to the construction of the contract with respect to the measurements of underpinning and of gratings furriished and installed under the curbing by the contractor, and to the classification of steel. The plaintiff recovered a verdict for $8,937.49 and $639.42 interest thereon for certain items, and since the city did not appeal, no point is presented with respect to them.

[858]*858On the completion of the work the engineer made a final certificate in accordance with the provisions of the contract showing a balance of $72,760.16 due and owing to the contractor. The comptroller, however, instead of issuing to the contractor a warrant for that amount issued a warrant for $71,000 for and on account of final payment on contract,” leaving a balance of $1,760.16 which was not paid but was included in the plaintiff’s recovery; and the contractor thereupon executed a general release to the city of its liability under the contract containing a reservation of its claim for the balance certified by the engineer and of a claim which he had filed "in the department of finance on August 8, 1916, for $197,641.43. The release provides that said claims are neither released by the contractor nor conceded by the city.

Article XXXV of the contract provided that the acceptance of final payment by the contractor should be and operate as a release of the city from all claims and liability to the contractor, with the exception of any claim it might have for moneys withheld under the provisions of the contract. Counsel for the city contends that this acceptance by the contractor of part of the final payment released the city from all claims involved in this appeal. He contends (citing Hearst v. McClellan, 102 App. Div. 336) that the comptroller was merely an auditing officer and that it was his duty to pay the full amount specified •in the final certificate of the engineer, and that notwithstanding .his failure so to do the payment of $71,000 made to and accepted by the contractor constitutes a final payment under the certificate, and he cites as authority therefor MacArthur Bros. Co. v. City of New York (177 App. Div. 725; affd., 224 N. Y. 629). In that case, however, there was payment in full to the contractor according to the final certificate, and it was merely held that where the contractor accepts the final payment as in full, he cannot by a release, the execution of which is neither required by law nor by the contract, reserve a claim. We are of opinion, therefore, that thp acceptance of part of the final payment did not release the city.

Article X of the contract provided as follows:

Article X. In order to construct the Railroad it' will be necessary to take up and relay the sidewalk pavement [859]*859or other surface material, and to lay and maintain a temporary pavement in the roadway, to protect, support and maintain during construction all buildings and other structures, including their foundations, and all elevated and surface and sub-surface railroads, watermains, gas pipes, electric subways, poles and wires, pneumatic tubes, steam pipes, vaults, including vaults of abutting property, and other surface, sub-surface and overhead structures, together with their necessary connections, as the same may be met with along the route; to build sewers both along the route and other streets; to make or remake the necessary manholes, catch basins and other sewer connections therewith; to move, alter, readjust or rebuild water mains, gas pipes, electric subways, pneumatic tubes, steam pipes, vaults, including vaults of abutting property, and other sub-surface structures, together with their necessary connections; and to do all such additional and incidental work as may be necessary for the completion of the Railroad and the reconstruction and restoration of the street pavements or other surfaces (except as herein provided in respect of temporary pavements for roadways), adjacent to the route of the Railroad and which may have been directly or indirectly disturbed or injured by the Contractor in the progress of the work of construction, to as useful and good a condition as existed before construction shall have been begun. All such work of every description including underpinning wherever necessary, of all buildings or structures of whatsoever nature, monuments, elevated railroads and surface and sub-surface railroads affected by or interfered with during the construction of the Railroad, is part of the work which is included in this contract and which the Contractor agrees to perform for the prices herein agreed upon.”

Section 84 of the specifications provided that in order to secure adjacent ground or the buildings thereon, or to prevent bringing an unusual pressure on the structure when completed, the Contractor shall secure the sides of the excavation by suitable timbering, and shall safely and permanently underpin adjacent buildings.” The unit prices to be received by the contractor were specified in a schedule contained in article XI of the contract. Its compensation for underpinning work [860]*860was prescribed in item 4 of the schedule, which provides as follows:

Item 4. For underpinning buildings, including all incidental work and material, as follows:

“ (a) For buildings less than seven (7) stories in height the sum of Eighty-two and 50 /100 dollars ($82 50 /100) per lineal front foot of building underpinned.”

That schedule also prescribed compensation for the restoration of street surface; ” and with reference to surface and sub-surface structures ” it prescribed compensation for the support, reconstruction and rebuilding of electric and horse railways. It also provided for compensation for changing, the location of and relaying or reconstructing “ in other than the original position ” water, gas, steam and other pipes.

Article XVIII recites that the contractor has examined the work and has read and understands the specifications. By article XXXVIII the contractor stipulated that it could do the work without damage to the foundations, walls or other parts of adjacent buildings and structures, and that it would be responsible for any damage thereto. Section 70 of the specifications obligated the contractor to maintain, to the reasonable satisfaction- of the owners, all surface and subsurface structures and to protect them from injury, and if injured, to restore them without other compensation than that expressly provided for in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BOARD OF WATER & SEWER COM'RS v. Bill Harbert Const. Co.
870 So. 2d 699 (Supreme Court of Alabama, 2003)
Thomas Crimmins Contracting Co. v. City of New York
138 A.D.2d 138 (Appellate Division of the Supreme Court of New York, 1988)
Savin Brothers, Inc. v. State
62 A.D.2d 511 (Appellate Division of the Supreme Court of New York, 1978)
Joseph Davis, Inc. v. Merritt-Chapman & Scott Corp.
27 A.D.2d 114 (Appellate Division of the Supreme Court of New York, 1967)
Terminal Const. Corp. v. Bergen, Etc., Authority
112 A.2d 762 (New Jersey Superior Court App Division, 1954)
E. E. Smith Contracting Co. v. City of New York
209 A.D. 271 (Appellate Division of the Supreme Court of New York, 1924)
McGovern v. City of New York
202 A.D. 317 (Appellate Division of the Supreme Court of New York, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
196 A.D. 856, 188 N.Y.S. 716, 1921 N.Y. App. Div. LEXIS 5622, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oscar-daniels-co-v-city-of-new-york-nyappdiv-1921.