E. E. Smith Contracting Co. v. City of New York

209 A.D. 271, 204 N.Y.S. 289, 1924 N.Y. App. Div. LEXIS 8605
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 2, 1924
StatusPublished
Cited by2 cases

This text of 209 A.D. 271 (E. E. Smith Contracting Co. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. E. Smith Contracting Co. v. City of New York, 209 A.D. 271, 204 N.Y.S. 289, 1924 N.Y. App. Div. LEXIS 8605 (N.Y. Ct. App. 1924).

Opinion

Martin, J.:

On the 7th day of March, 1913, the plaintiff entered into a contract with the Public Service Commission for the construction of an elevated railroad including stations, about three and one-quarter miles long, commencing two hundred and seventy feet east of Van Dam street and running along Queens boulevard, Greenpoint, Silkman and Roosevelt avenues to a po'nt on Roosevelt avenue about seventy feet east of Sycamore avenue.

About 4,000 feet of the railroad situated on the Queens boulevard was to be constructed of reinforced concrete, the remaining part being ordinary elevated railroad construction.

Plaintiff commenced work in April, 1913. The date for completion was extended from time to time. The work was not finished until the fall of 1916.

The final estimate of the value of work performed was made on March 29, 1918, by the engineer of the Public Service Commission. It shows $2,429,799.64 previously estimated; $6,206.65, the amount of the final estimate remaining unpaid; $50,000' of retained percentages in corporate stock deposited by the plaintiff with the comptroller, and $692.66 of retained percentages in cash.

Plaintiff refused to accept the amount shown to be due by the final certificate or to accept a return of its stock, having previously filed a claim for a large amount based upon allegations of damage and failure to properly classify work performed. This action was then brought to recover the amount which the p’aintiff asserted to be still due.

Judgment was given for the following: Balance due as shown by final certificate, $6,206.65; retained percentage in corporate [273]*273stock, $50,000; retained percentage in cash, $692.66. These items were not contested by the city.

The court submitted to the jury a number of additional claims and the jury found a verdict for the plaintiff upon the following: Dressing exterior of reinforced concrete structure, $34,734.28; increased cost of fabricating, erecting and transporting by fighter extra or unclassified steel, $18,988.12; increased cost of unloading steel due to traction feed wire, $468.50; extra cost of placing concrete in mezzanines, $74,745.22. All of these items had been classified by the engineer and paid for at the unit price with the exception of the one for increased cost of unloading steel due to traction feed wire. The amounts here allowed are cost plus ten per cent after deducting the amount already paid by the city therefor. The claim for increased cost of unloading steel was for damage alleged to have been caused by the city in permitting a feed wire to be placed along the line of the work in such a manner as to obstruct or interfere with the plaintiff’s operations.

The court directed a verdict for the following amounts: Waterproofing, $7,574.41; ducts rejected, $14.44; cutting panel in abutment, $7.16; cost of making sample column, $61.29; moving plant, $195.24; cost of rubbing jack arches, $1,193.27; increased cost of fabricating steel for Fiske avenue station, $4,747.03; Fiske avenue station wire, $207.64; extra cost of plans made by American Bridge Company, $423.50; cost of Tarvia pavement, $106.76. Of these items, several were classified by the engineer and paid for by the city at unit prices. The amount allowed in each instance by the court was cost plus ten per cent, after deducting the amount already paid for same.

A number of these claims for which the court directed a verdict were solely for damages for alleged breach of contract, and were not the subject of classification. Of these items, included in the directed verdict, the following were classified by the engineer and paid for by the city at unit prices and the recovery is for the amount the jury found to be the cost plus ten per cent, after deducting the amount already paid by the city: Waterproofing, $7,574.41; cutting panel in abutment, $7.16; cost of making sample column, $61.29; cost of rubbing jack arches, $1,193.27; increased cost of fabricating material for Fiske avenue station, $4,747.03; cost of Tarvia pavement, $106.76.

The following were not ordered by the engineer, but were allowed as damages for breach of contract: Ducts rejected, $14.44; moving plant, $195.24; removing Fiske avenue station wire, $207.64; extra cost of plans made by American Bridge Company, $423.50.

[274]*274Plaintiff has appealed from the judgment and order only in so far as the dismissal relates to what are known as insurance claims, consisting of two items, one for $310.36, and the other for $7,675.27.

The complaint herein sets forth one cause of action only. Both plaintiff and defendant appear to have properly adopted the theory that under the terms of this contract the engineer had the right to make changes in the plans, and, if found necessary, to order extra or additional work.

The construction of the contract made by the engineer having been adopted by the parties, the plaintiff very properly brought its action to recover upon the contract and not for a breach thereof.

In many instances the plaintiff seeks to recover the cost of the work plus ten per cent. The city paid for this work at the unit prices set forth in the contract, but refused to pay cost plus ten per cent.

The plaintiff asserts that it is not bound to accept the classification of the engineer or payment for the work at unit prices. The contract provides for such a contingency in section XII thereof:

“ In case any work or materials shall be required to be done or furnished in or about the works — whether specified herein or indicated on the plans or not — which are not susceptib e of classification under the Schedule of Unit Prices, the contractor shall and will if ordered by the engineer do and perform such work and furnish such materials at and for the actual and necessary net cost in money to the contractor for labor and for material, where new material is used, and in addition thereto ten per centum (10%) of such net cost for the use of tools and plant, superintendence and all other expenses incidental to the performance of such work and the furnishing of such material, and the contractor shall have no further claim in excess of the above; but this method of payment shall not apply to the performance of any work or the furnishing of any material which in part or in whole is susceptible of classification under such schedule, which work or material shall be paid for in part or in whole, as the case may be, at the unit price given in such schedule, except as herein otherwise expressly provided.

In case any work or material shall be required to be done or furnished under the provisions of this Article for cost plus ten (10%) per centum the contractor shall at the end of each day during the progress thereof furnish to the engineer daily time slips showing the name and number of each workman employed thereon, the number of hours employed thereon, the character of work he is doing and the wages paid or to be paid to him and also a daily memorandum of the material delivered on the work showing the amount and character of such material, from whom purchased and [275]*275the amount paid or to be paid therefor. If required, the contractor shall produce any books, vouchers, records or memoranda showing the work and materials actually paid for and the actual prices therefor.”

By sections XIV and XV it was provided that changes or alterations might be made and additional work ordered provided payment was made therefor under the terms of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas Crimmins Contracting Co. v. City of New York
138 A.D.2d 138 (Appellate Division of the Supreme Court of New York, 1988)
Pamozzo v. Carborundum Co.
7 F. Supp. 317 (W.D. New York, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
209 A.D. 271, 204 N.Y.S. 289, 1924 N.Y. App. Div. LEXIS 8605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-e-smith-contracting-co-v-city-of-new-york-nyappdiv-1924.