New York Building & Improvement Co v. Springfield Elevator & Pump Co.

56 A.D. 294
Appellate Division of the Supreme Court of the State of New York·Decided July 1, 1900·Published·Cited by 7 cases

Opinion

Rumsey, J.:

The plaintiff brings this action to recover damages for the violation of a contract made between the defendant and itself on the 5th day of March, 1898. On the 22d of October, 1896, the plaintiff, being engaged in the construction of a building, made a contract with the defendant to-put elevators therein. The terms of that contract are not necessary to be considered except so far as to say that the defendant guarantees to do the work to the satisfaction of the architect, and to make good any faults or defects in the work for which it was responsible, and in consideration the plaintiff agreed to pay a certain sum for the work, one-half of which was to be paid in thirty days, and the other half in sixty days after the completion of the elevators.

It was claimed by the plaintiff that this contract was not completed by the defendant, and ■ the contract which lies at the basis of this action was the result of that claim. In that contract the making of the original agreement to put in the elevators was recited, as were also the facts that the plaintiff claimed that the contract was not performed; that there was still unpaid the sum of $2,620.26, which the defendant was desirous of having paid before the complete performance of the contract; and in consideration of the payment of that sum it was agreed, among other things, that the defendant would perform completely every provision and requirement in said contracts contained on or before the 16th day of May, 1898, to the satisfaction of R. M. Watson, who is hereby made sole judge and arbitrator as to. what shall be deemed compliance with the provisions and requirements of said contracts, and .whose determination, given in writing, shall. be binding and conclusive upon the parties hereto.” It was further agreed that time was of the essence of [296] the contract, and that if before the sixteenth of May the defendant-had not completed the work as required by the contracts to the-satisfaction of said Watson the plaintiff might, under the direction of Watson and at the expense of the defendant, complete the work,, and in so doing the plaintiff was authorized to replace any part or parts óf said elevators and their appurtenances with articles of the-make or manufacture of parties other than the defendant.

It was alleged in the complaint that the defendant failed to perform the work by the sixteenth of May ; .that on the seventeenth of May Watson so certified, and that a copy of Watson’s certificate was-on that day sent to the defendant with notice that the plaintiff would proceed to complete the contract at the expense of the. defendant. It was further alleged that the plaintiff had completed the contract at an expense of $5,200, and this suit was brought to-recover that sum. ■ ,

Upon the .trial the foregoing facts were made .to appear and it was further shown by the certificate of Watson and by common-law proof that the reasonable expense incurred .by the plaintiff in -completing the contract after May seventeenth was $5,200.

The defendant sought to prove in the first place that it had substantially completed the original contracts to put in the elevators,-, and it excepted to a ruling excluding evidence of that fact. That-, ruling was not error. The contract upon which this action was brought recited that it was claimed by the plaintiff that the elevators, had not been completed, and the new agreement expressly was that the defendant should perform completely every portion and requirement of the original contracts. That provision in the contract necessarily implied that there was still something to be done torn alee the elevators comply with the requirements of the original contracts, and how that necessity arose is óf no importance. The» agreement was that the requirements of the contracts should be completely performed, and that Watson’s certificate to that effect-should be final and conclusive upon the parties.; -and when his certificate had been given that the contract of March fifth had not been performed it was conclusive upon the parties. The rule in such cases is that. where one agrees to be bound- as to the fact, of the performance of a contract by the certificate of any person who is named therein as arbitrator, that certificate is conclusive in. [297] the absence of proof of bad faith, corruption or palpable error in the making of it. (Smith v. Mayor, 12 App. Div. 392; Sewer Commissioners v. Sullivan, 11 id: 472; affd., 162 N. Y. 594.)

If the certificate had been given corruptly, or in bad faith, or there liad been a mistake palpable on. its faee, that would constitute an affirmative defense which must be pleaded, and unless it was. pleaded the defendant would be in no situation to prove it. (Everard v. Mayor, 89 Hun, 425.)

The only question remaining, therefore, was whether the plaintiff' had completed the contract in pursuance with its terms and what was the reasonable expense of that work. The defendant insists-that it appears that the plaintiff did not complete the work in compliance with the terms of the contract. It complains that the plaintiff threw out a very large amount of the material which it might have used and. that, the contract when completed was not the contract which the defendant had agreed to perform. So far as the last objection is concerned, it appears that.the contract made by the defendant was to put in an elevator which would run at the speed of 300 feet a minute, whereas the plaintiff only installed machinery capable of running the elevator at the rate of 200 feet a minute. The defendant insists that this it had no right to do. The objection is-clearly not well taken. If the plaintiff chose to do so it was at liberty to put in an elevator running at the speed of 300 feet a minute,, and it is in evidence that machinery to run an elevator at that speed would cost more than to run one at the rate of 200 feet. The-defendant has no reason to complain if the plaintiff in completing the work saw fit to put in an elevator running at a slower speed and costing less than that which it might have put in under the terms of the contract.'

Free access — add to your briefcase to read the full text and ask questions with AI

New York Building & Improvement Co v. Springfield Elevator & Pump Co., 56 A.D. 294 (N.Y. Ct. App. 1900).

56 A.D. 294 (New York Building & Improvement Co v. Springfield Elevator & Pump Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Spencer, White & Prentis, Inc. v. City of New York
189 Misc. 616 (New York Supreme Court, 1945)
Duffy Bros. v. Bing & Bing, Inc.
217 A.D. 10 (Appellate Division of the Supreme Court of New York, 1926)
E. E. Smith Contracting Co. v. City of New York
209 A.D. 271 (Appellate Division of the Supreme Court of New York, 1924)
Cosden v. E. E. Paul Co.
196 A.D. 68 (Appellate Division of the Supreme Court of New York, 1921)
Molloy v. Village of Briarcliff Manor
145 A.D. 483 (Appellate Division of the Supreme Court of New York, 1911)
Horan v. Mason
141 A.D. 89 (Appellate Division of the Supreme Court of New York, 1910)
Farrell v. Levy
139 A.D. 790 (Appellate Division of the Supreme Court of New York, 1910)