Spencer, White & Prentis, Inc. v. City of New York

189 Misc. 616, 75 N.Y.S.2d 629, 1945 N.Y. Misc. LEXIS 2870
CourtNew York Supreme Court
DecidedMay 23, 1945
StatusPublished

This text of 189 Misc. 616 (Spencer, White & Prentis, Inc. v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spencer, White & Prentis, Inc. v. City of New York, 189 Misc. 616, 75 N.Y.S.2d 629, 1945 N.Y. Misc. LEXIS 2870 (N.Y. Super. Ct. 1945).

Opinion

Schreiber, J.

Plaintiff, the successful bidder for a unit price contract with defendant City in construction of a section of the Sixth Avenue subway, seeks recovery herein, after completion of the work, under various causes and theories of action.

The first cause is for items claimed to be due and unpaid under the contract. It has been stipulated that plaintiff is entitled in this cause to recover $81,195.64. The amount of other items is conceded but the right to recovery is disputed. These items will be considered seriatim.

(1) I disallow the extra charge for cast iron rather than vitrified pipe ($196.30); such order was not made by the city and no necessity was shown requiring departure from the contract in this instance.

(2) I disallow the extra claim for extension of drain for toilets on the Sixth Avenue “ EL” at 14th Street ($180.64) on the ground that this is covered by the lump sum for underpinning and other work on the elevated column and is so specifically stated in the contract (item 153 b) and specifications (89.1 B).

(3) I disallow the claim dealing with gas by-passes ($1,291.16), as I interpret specification 72 (B) of the contract to mean that allowance may be made only for six feet of such pipe and not for any additional pipe used.

(4) I disallow the claim for plastering • ($862.01), wherein plaintiff substituted “ cement ” finish in areas designated by the plans as calling for “ plaster ”, on the ground that the city [619]*619did not order the change and plaintiff has- been fully paid for the “ plaster ” finish.

(5) I disallow the claim for extra compensation for work in support of the sewer at the Waverly Place shaft ($892.65); plaintiff was paid $2,500 to support this sewer, all inclusive (item 109, specification 501), and although, on excavation for this shaft, wooden piles were found to be decayed, it cannot fairly be said that this was an unforeseeable circumstance.

(6) I allow the claim for bracing hollow tile walls ($351.57) in the part of this section of the subway in which walls collapsed under blasting due to inadequate thickness and design. The burden here clearly should not be cast on plaintiff and is not fairly to be included in excavation amounts under subparagraph C, paragraph 169, of the specifications.

(7) I allow the claim for the emergency safeguarding work ($6,803.89) after the run or slide of July 12, 1938, which endangered subway and surface and was hazardous to property and persons; these were extraordinary and unforeseeable conditions the risk of which was not assumed by plaintiff and, indeed, for which the city, at the time, specifically promised to pay.

(8) Likewise the additional borings thereafter taken by plaintiff to ascertain the actual subsoil condition were proper and necessary under the circumstances, were ordered by the city and the cost thereof is allowed ($3,454.60).

(9) Altering track ($1,056.12), additional structural steel ($4,838.78), underpinning side walls of west tunnel ($766.28), are stipulated to be due to the plaintiff, and stopping leaks ($2,394.46), cutting chases ($150.87) and repainting steel ($278.22) are all items which are allowed on the ground that the work was made necessary because the structure was not designed as a waterproof structure and these additional expenses arise solely through insufficient design and are no fault of plaintiff.

(10) The claim for extra compensation' for moving waterproofing lines ($1,920.69) is-disallowed; although these lines, at some extra expense to plaintiff, had to be moved in order to create room to work on structural steel; and although the original contract drawings showed a clear space of twelve inches, the revised drawings showed plainly that this space would be greatly reduced because of the necessary use of steel stiffeners and, in fact, the defendant voluntarily paid to remove these lines six inches by reason thereof. The're is thus no basis for the claim that plaintiff reasonably could not have taken this item into allowance when making its bid.

[620]*620(11) The claim for extra compensation for reconstruction of the intersecting.Hudson & Manhattan Railroad protection walls, the amount of which claim has been stipulated, is denied. The Sixth Avenue subway at this point was to be built on either side of or below the existing Hudson & Manhattan tubes. The protective masonry for the walls of the Hudson & Manhattan tube was different from that shown in the contract drawings, was loose and defective, and brick and hollow tile parts thereof were required to be removed and afterwards replaced. The city correctly contends that plaintiff has been paid in full under the contract for this work. Specification 89.4 (a) provides that payment for the support of the Hudson & Manhattan Railroad tube will be made at a lump sum price stipulated in item 154, for support, maintenance, underpinning, restoration, etc., of the said tube. Plaintiff’s attention was called to the supplementary drawings (§ 45, p. 149, contract) showing the nature and position of underground structures, and under section 45 (D) plaintiff was to form its own judgment thereon. Under these circumstances the risk of the conditions actually encountered was clearly on plaintiff under the contract and drawings and may fairly be assumed to-be reflected in the bid. In this connection, indeed, it appears that the city erroneously overpaid plaintiff the sum of $6,774.75 and is thus entitled to the amount sought on its counterclaim herein in that sum.

(12) It has been stipulated that plaintiff, if entitled to recovery, is to receive $1,333.75 for relocating-air vents. The buildings abutting Sixth Avenue had sewer lines running into the main sewer in the street. In construction of the subway the sewer lines had to be temporarily removed. Plaintiff claims that some of the- lines removed and later replaced, and in which air vents had to be relocated, originally had no air vents as required by the Sanitary Code. However, the defendant’s engineer properly took the position, as borne out by the testimony, that the required installation of most of the air vents within the building lines was caused by the method adopted by the plaintiff in underpinning operations which disturbed the existing plumbing. Inasmuch as the city was required to and has paid under the contract for the work done outside the building lines and in physical interference with the subway and is not responsible for the work within the building lines, the claim is disallowed.

(13) The contract obligated plaintiff to pump and keep dry the operation as long as it was doing any of the work required under the contract (specification 169 (d), p. 243, contract). Plaintiff asks for $3,211.82 as an additional charge, by reason of delays [621]*621in completing the work, with regard to such pumping, in which city-owned pumps were used, and the city counterclaims for $4,573.38 actually paid to plaintiff on this score oh the ground that under the contract there was no basis for any such payment. Inasmuch as under the cited contract provision payment for such pumping was included in the excavation prices, and, as hereinafter shown, there is no basis for ascribing any delay to the city, it is clear that the city’s contention in this .regard must here be upheld and plaintiff’s claim overruled and counterclaim allowed.

(14) A claim by.plaintiff for $767.17 for twenty-three extra work items is disallowed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Del Balso Construction Corp. v. City of New York
15 N.E.2d 559 (New York Court of Appeals, 1938)
Weston v. State of New York
186 N.E. 197 (New York Court of Appeals, 1933)
Kinser Construction Co. v. . State of N.Y.
97 N.E. 871 (New York Court of Appeals, 1912)
Manstin Engineering Corporation v. State
42 N.E.2d 747 (New York Court of Appeals, 1942)
Collins v. State of New York
181 N.E. 357 (New York Court of Appeals, 1932)
McGovern v. . City of New York
139 N.E. 266 (New York Court of Appeals, 1923)
New York Building & Improvement Co v. Springfield Elevator & Pump Co.
56 A.D. 294 (Appellate Division of the Supreme Court of New York, 1900)
McGovern v. City of New York
202 A.D. 317 (Appellate Division of the Supreme Court of New York, 1922)
Callaghan v. City of New York
233 A.D. 263 (Appellate Division of the Supreme Court of New York, 1931)
Farub Foundation Corp. v. City of New York
183 Misc. 636 (New York Supreme Court, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
189 Misc. 616, 75 N.Y.S.2d 629, 1945 N.Y. Misc. LEXIS 2870, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spencer-white-prentis-inc-v-city-of-new-york-nysupct-1945.