McGovern v. . City of New York

138 N.E. 26, 234 N.Y. 377, 25 A.L.R. 1442, 1923 N.Y. LEXIS 797
CourtNew York Court of Appeals
DecidedJanuary 9, 1923
StatusPublished
Cited by57 cases

This text of 138 N.E. 26 (McGovern v. . City of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGovern v. . City of New York, 138 N.E. 26, 234 N.Y. 377, 25 A.L.R. 1442, 1923 N.Y. LEXIS 797 (N.Y. 1923).

Opinion

Cardozo, J.

The plaintiffs made a contract with the defendant, the city of New York, in August, 1916, for the construction of that part of the subway known as *382 route number 61 in consideration of the payment of $4,194,797. They assert the existence of a later contract by which the defendant, acting through the public service commission and the board of estimate and apportionment, undertook to pay to them the extra cost incurred through the advance in the price of labor and material as a consequence of the war. The validity of that contract is the chief question to be determined. The circumstances leading up to its making are set forth fully in the fourth cause of action, to which for the time being our attention will be confined. The fifth and sixth causes of action, which together with the fourth are challenged by the demurrer, involve narrower questions of pleading with but slight relation to the merits.

The plaintiffs say that at the commencement of the work, the General Contractors’ Association, of which they are members, fixed a wage scale with representatives of the labor unions engaged in subway work which was to continue unchanged until the completion of the contracts. In December, 1916, the men demanded an increase. The contractors yielded to the demand under protest, and fixed a new scale to continue for a stated time. In February, 1917, before the stated time had elapsed, there was a new demand. The workmen appealed to the commission and its chairman. The commission insisted that the work must not be interrupted. The contractors, however, were assured that a way would be found of reimbursing them for the increased expense. They were also assured that in the judgment of the commission a state of war was then imminent between the United States and Germany, that war would probably lead to still greater cost both of labor and of materials, and that if war were declared, the defendant would pay plaintiffs and said other contractors, respectively, all further increases in the cost of labor and materials that might be due to it, or to labor inefficiency resulting from or following it.” There was also a promise to co-operate *383 with the contractors in procuring the legislation necessary to that end. Shortly thereafter war was declared, and the contractors thereupon established a new scale to take effect from April 1, 1917, and to continue until the completion of the contracts. The war withdrew from peaceful industry great numbers of workmen whose services were required by the government. It also transferred large numbers to the munition plants and to other industries engaged in the manufacture of war materials and the furnishing of war supplies. The government at places outside of New York paid a scale of wages greatly in exqess of that prevailing in subway and similar work when war was declared. So also did the war industries. As a result of said increased demand for the services of workmen and of men for military duty by the United States and other employers, and the greatly increased wages established, offered and paid as aforesaid elsewhére than in New York city and its vicinity, as well as the increased and increasing cost of living,” the workmen, in May, 1918, despite their earlier agreements, demanded a large increase in the wages they were then being paid and in excess of the then prevailing rate,” and gave notice to the contractors and to the commission and the board of estimate that they would strike if said increase was not granted. The contractors refused to pay said increase unless defendant would agree to reimburse them for the added cost to them resulting from payment of said increased scale as compared with the scale prevailing at the date of their respective contracts, and also the increase in the cost of material due to the war, as compared with its cost at said dates, on the further performance and completion of their respective contracts,” besides the increased cost of both labor and material paid or incurred since April 6, 1917. They did not limit their demand to the prospective increase in the cost of labor, but they included prospective increase in the cost of material, and also past increases in the cost both of labor and of material. *384 The commission and the board of estimate and apportionment, thus pressed, promised .to enter into a binding agreement accordingly, and if necessary to exercise the powers conferred by the so-called Lockwood Act (L. 1918, ch. 586). The plaintiffs in reliance on these assurances accepted the new scale, and put it in force for one week beginning June 1, 1918. The defendant, however, failed and refused to enter into any binding agreement, and thereupon the plaintiffs canceled the new scale, and the men struck. They gave notice in striking that, unless they had a satisfactory agreement, they would scatter and prevent the further prosecution of subway work. Thereupon ^the board of estimate and the commission held joint and separate meetings. As a result, according to the allegations of the complaint, they expressly, jointly and severally promised and agreed ” that if the contractors would pay the increased wages, the defendant would pay the increased cost of labor and material due to the war ” from April 6, 1917, as well as any future increase due to the same cause.” The amount of the increase in the cost of labor was to be ascertained by comparing the scale of wages established in April, 1917, with the rates in force when the construction contracts were made, and the amount of the increase in the cost of material was to be computed in a like way. For breach of that agreement this action is brought. There are allegations that a critical situation was presented by the threatened strike; that there was danger of great injury to the public by the obstruction of the work; that about 6,000 workmen were employed; and that in the emergency thus arising it was necessary to reheve the contractors from burdens not foreseen when the undertaking was begun.

We think the contract is condemned by article III, section 28, of the Constitution of the state.

“ The legislature shall not, nor shall the common council of any city, nor any board of supervisors, grant any extra compensation to any public officer, servant, *385 agent or contractor” (Constitution, art. III, § 28). We have held that there is no power to repair out of the public purse the losses that war prices have brought to contractors with state or municipality in the performance of their contracts (Gordon v. State of N. Y., 233 N. Y. 1). Nothing inconsistent with our ruling was held in U. S. v. Cook (257 U. S. 523) which sustained an act of Congress awarding extra compensation to contractors with the United States who had suffered from the San Francisco earthquake. Extra compensation in circumstances of hardship may be consistent, where the supporting equity is strong enough, with the due process clause of the federal Constitution (People v. Westchester County Nat. Bank, 231 N. Y. 465, 470). It is not consistent with a provision in the Constitution of the state whereby the power to give extra compensation .is explicitly withheld.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Space Imaging Europe, Ltd. v. Space Imaging L.P.
38 F. Supp. 2d 326 (S.D. New York, 1999)
Rose v. Elias
177 A.D.2d 415 (Appellate Division of the Supreme Court of New York, 1991)
Vrooman v. Village of Middleville
91 A.D.2d 833 (Appellate Division of the Supreme Court of New York, 1982)
Los Angeles County Transportation Commission v. Richmond
643 P.2d 941 (California Supreme Court, 1982)
Vrooman v. Village of Middleville
106 Misc. 2d 945 (New York Supreme Court, 1981)
H. W. Wilson Co. v. United States Postal Service
438 F. Supp. 326 (S.D. New York, 1977)
Angel v. Murray
322 A.2d 630 (Supreme Court of Rhode Island, 1974)
OVERSEAS AFRICAN CONSTRUCTION CORP. v. McMullen
367 F. Supp. 202 (S.D. New York, 1973)
Gordon H. Ball, Inc. v. State ex rel. Department of Public Works
26 Cal. App. 3d 162 (California Court of Appeal, 1972)
United States v. Brooks
349 F. Supp. 168 (S.D. New York, 1972)
Kephart v. Wilson
219 F. Supp. 801 (W.D. Texas, 1963)
East Orange v. BD. OF WATER COM'RS., ETC.
191 A.2d 749 (New Jersey Superior Court App Division, 1963)
Joseph F. Egan, Inc. v. City of New York
18 A.D.2d 357 (Appellate Division of the Supreme Court of New York, 1963)
CUDD v. Aschenbrenner
377 P.2d 150 (Oregon Supreme Court, 1962)
Wardwell v. Commissioner
35 T.C. 443 (U.S. Tax Court, 1960)
Mullaly v. Carlisle Chemical Works, Inc.
184 F. Supp. 701 (D. New Jersey, 1960)
National Dairy Products Corp. v. Gleeson
16 Pa. D. & C.2d 390 (Dauphin County Court of Common Pleas, 1958)
Nybladh v. Peoples State Bank of Warren
76 N.W.2d 492 (Supreme Court of Minnesota, 1956)
State v. Duranleau
104 A.2d 519 (Supreme Court of New Hampshire, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
138 N.E. 26, 234 N.Y. 377, 25 A.L.R. 1442, 1923 N.Y. LEXIS 797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgovern-v-city-of-new-york-ny-1923.