Gordon v. . State of New York

134 N.E. 698, 233 N.Y. 1, 21 A.L.R. 562, 1922 N.Y. LEXIS 831
CourtNew York Court of Appeals
DecidedFebruary 28, 1922
StatusPublished
Cited by21 cases

This text of 134 N.E. 698 (Gordon v. . State of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gordon v. . State of New York, 134 N.E. 698, 233 N.Y. 1, 21 A.L.R. 562, 1922 N.Y. LEXIS 831 (N.Y. 1922).

Opinion

Hogan, J.

November 10, 1915, the claimant, respondent, entered into a, contract with the state oí New York, through the commissioner of highways, for improving the Fleming-Scipio, part 2, county highway, number 1307, 6.06 miles, in the county of Cayuga. The contract provided that the material and work therein specified was to be furnished and performed by the claimant for which claimant was to be paid unit prices stated therein. The work contracted for was to be completed on the 15th day of November, 1916.

Chapter 459 of the Laws of 1919, entitled “ An act authorizing the termination of certain highway contracts, conferring jurisdiction upon the court of claims to hear *4 and determine claims and make awards for increased costs incurred in war contracts, and making an appropriation for the completion of unfinished work,” became a law May 7, 1919.

By section 1 of the act “ war contracts ” were designated as those which were made and executed prior to the 6th day of April, 1917, the date of the declaration of war between the United States Of America and the Imperial German Government.

Section 2 authorized and directed the state "commissioner of highways to enter an official order terminating any war contract and releasing the contractor and the surety on the bond accompanying such contract from any further obligation or responsibility thereunder, provided that such contractor shall not have violated the contract prior to April 6th, 1917, by unreasonable delay in its performance or other substantial breach of the provisions thereof, other than the failure to complete the same.

By section 3 the commissioner of highways was required to prepare a final account of all labor performed and materials furnished by the contractor at the contract unit prices therefor, and after deducting all previous payments made, pay the balance remaining to the contractor.

Section 5 provided a contract thus terminated was required to be completed under the direction and supervision of the state commissioner of highways by a contract awarded after competitive bidding.

Section 6 of the act conferred upon the Court of Claims jurisdiction to hear all claims for alleged increase in the costs of labor, materials, or the transportation of material, incurred after April 6, 1917, in the doing and performance of war contracts which had been completed, accepted,' and for which final payment had been made, and also any war contract terminated under the provisions of the act, and authorized the court to determine the increased cost, whether the whole or a part, which is properly chargeable against the state, and render judgment against *5 the state for the amount so determined as chargeable against the state, which judgment shall be paid as other judgments against the state are paid, no judgment, however, to be rendered _ for an amount greater than thirty-five per cent of the contract price of labor, materials and the transportation of materials furnished or supplied during the year 1917, nor greater than fifty per cent of the same supplied, etc., during the year 1918.

Pursuant to the provisions of this chapter, the claimant filed a claim against the state wherein he asserted that the time for the completion of the contract was extended by law either expressly or by implication until about June 12, 1919, at which time the commissioner of highways entered an official order terminating said contract and released the claimant and the surety on his bond accompanying said contract from further obligation or responsibility thereunder and further alleged that the actual increased cost to him under said contract brought about by reason of the increased prices of labor, materials and transportation of materials in the work of constructing the highway subsequent to April 6, 1917, and during said year was the sum of $10,139.99, for which amount he prayed judgment against the state.

Upon the hearing before the Court of Claims, the attorney-general moved that the claim be dismissed on the ground that the statute of 1919 was in contravention of enumerated provisions of the Constitution. The counsel for the claimant practically conceded that the claim filed was predicated upon and presented under the provisions of the act of 1919 and based upon that statute. The motion of the attorney-general was granted and the claim dismissed. The Appellate Division reversed the determination and granted a new trial.

The conclusion of the Appellate Division is tersely stated in the opinion as follows: “ We do not pass upon the constitutionality of the act, (1919) so far as it relates to claims arising under completed contracts. The deter- *6 ruination of that question is not necessary. We hold that the act, so far as it related to claims terminated under the provisions of the act, is constitutional, and that the act authorizes the Court of Claims to audit and allow the same.” In the course of the opinion the court holds that, while the legislature may not recognize claims founded upon gratitude or charity, it may recognize claims founded in equity and justice, and in the enactment of the statute in question the legislature recognized the claim in this case as one founded in equity and justice and the claim is not only a moral obligation against the state but a legal claim as well, founded as it is upon the cancellation of the contract and the release and waiver of the contractor and his surety.

The contract of November 10, 1915, between claimant and the state was executed after claimant in competition with other contractors had submitted a proposal for a performance of the work therein specified to be performed and the labor and material necessary to complete the same. Claimant was a contractor and familiar with the nature of the work to be performed, the cost of labor and materials necessary to complete the specified work and the time within which the same could be completed. Engaged in a hazardous business, claimant was chargeable with knowledge of the legal obligation imposed upon a party to a contract to perform his covenants and liability to respond in damages in the event of non-performance, and that a like obligation rested upon the state. We may also attribute to claimant as a business man and contractor knowledge of the increasing abnormal conditions existing at the time of the execution of the contract. The powers of Europe had for some time prior to November 10, 1915, been and were then engaged in war. Some five months previous - the aggressor had ruthlessly caused the death of American citizens and helpless- children upon the high sea and the fact was apparent that the United States could not in the interest *7 of humanity and as a measure of self protection long delay participation in the war in aid of the forces opposed to the aggressor. A continuance of the war and particularly the entry of this country into the conflict would necessarily result in scarcity of labor, increased cost of the same and increased cost of material with continued business depression. Confronted with that condition and outlook, claimant proposed to undertake the work under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MLF3 Jagger LLC v. Kempton
56 Misc. 3d 227 (New York Supreme Court, 2017)
P. T. & L. Construction Co. v. State
179 A.D.2d 850 (Appellate Division of the Supreme Court of New York, 1992)
D. Lambert Railing Co. v. County of Suffolk
80 A.D.2d 42 (Appellate Division of the Supreme Court of New York, 1981)
Ogdensburg Urban Renewal Agency v. Moroney
42 A.D.2d 639 (Appellate Division of the Supreme Court of New York, 1973)
Bayview General Hospital v. Associated Hospital Service
45 Misc. 2d 218 (New York Supreme Court, 1964)
Lowe v. Feldman
11 Misc. 2d 8 (New York Supreme Court, 1957)
Bates Chevrolet Corp. v. State
192 Misc. 151 (New York State Court of Claims, 1948)
Freeto v. State Highway Commission
166 P.2d 728 (Supreme Court of Kansas, 1946)
Whale Oil Co. v. State
180 Misc. 1067 (New York State Court of Claims, 1943)
Queensboro Farm Products, Inc. v. State
175 Misc. 574 (New York State Court of Claims, 1940)
Weston v. State of New York
186 N.E. 197 (New York Court of Appeals, 1933)
Cascade Automatic Sprinkler Corp. v. State
147 Misc. 420 (New York State Court of Claims, 1933)
In re Keep
138 Misc. 194 (New York Supreme Court, 1930)
Gordon v. Commissioner
16 B.T.A. 1012 (Board of Tax Appeals, 1929)
A. B. Barr & Co. v. State
127 Misc. 75 (New York State Court of Claims, 1926)
Carpenter Construction Co. v. City of Detroit
200 N.W. 955 (Michigan Supreme Court, 1924)
Busch v. Joint Drainage District No. 49-79
198 Iowa 398 (Supreme Court of Iowa, 1924)
McGovern v. . City of New York
138 N.E. 26 (New York Court of Appeals, 1923)
McGovern v. City of New York
202 A.D. 361 (Appellate Division of the Supreme Court of New York, 1922)
J. B. Lyon Co. v. State
118 Misc. 301 (New York State Court of Claims, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
134 N.E. 698, 233 N.Y. 1, 21 A.L.R. 562, 1922 N.Y. LEXIS 831, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gordon-v-state-of-new-york-ny-1922.