Freeto v. State Highway Commission

166 P.2d 728, 161 Kan. 7, 1946 Kan. LEXIS 224
CourtSupreme Court of Kansas
DecidedMarch 9, 1946
Docket36,315
StatusPublished
Cited by19 cases

This text of 166 P.2d 728 (Freeto v. State Highway Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Freeto v. State Highway Commission, 166 P.2d 728, 161 Kan. 7, 1946 Kan. LEXIS 224 (kan 1946).

Opinion

The opinion of the court was delivered by

Harvey, C. J.:

F. H. Freeto,'a highway construction contractor, and twelve other persons, firms, or corporations engaged in the same business, each having previously entered into one or more contracts with the state highway commission (hereinafter called the commission) for the construction of one or more highway projects, brought separate actions in equity against the commission in the district court of Shawnee county to have the contracts can-celled on the ground of impossibility of performance. In the thirteen actions the plaintiffs sought cancellation of twenty-seven contracts involving highway projects, the contract cost for which aggregated about $1,600,000. Some of the actions were filed January 19, 1944, and others on various dates to March 10, 1944. As filed, some of the cases were assigned to each of the three divisions of the court. After issues were joined by pleadings filed the actions were consolidated for the purpose of trial and were tried before the three judges of the three divisions of the court sitting en banc, and counsel stipulated “that all evidence offered may be considered where competent, in each of the cases.” The trial was had and plaintiffs’ evidence introduced October 12 to 19, 1944. At the close of the evidence on behalf of plaintiffs defendant demurred “to the evidence in every case, for the reason that the evidence adduced fails to establish or prove a cause of action in favor of the plaintiffs or any of them and against this defendant under the issues joined in each and every case herein.” After con *10 sidering the evidence and the argument of counsel on the demurrer the court sustained the demurrer and each judge made the proper order in the case pending in his division. Plaintiffs promptly appealed to this court from the order sustaining defendant’s demurrer to the evidence. In this court the entire proceedings were filed as one case and abstracted and briefed together.

Appellants point to our well-established rule that in considering defendant’s demurrer to plaintiffs evidence the court cannot weigh the evidence, but must consider it in the light most favorable to plaintiffs. (See Zumbrun v. City of Osawatomie, 130 Kan. 719, 721, 288 Pac. 584; In re Estate of Bond, 158 Kan. 776, 150 P. 2d 343, and cases cited therein.) This requires us to summarize the pleadings and the evidence.

The petition in the case of Freeto v. The Commission, after identifying the parties and their functions, alleged that on May 14, 1941, plaintiff entered into two contracts (tied together) with defendant for the construction of two bridges in Neosho county, known as Project No. 39-67 PA 567, section A (1), which contract incorporated by reference and made a part thereof the standard specifications for state road and bridge construction (printed in book form and too bulky to attach), plaintiff’s proposals, schedule of prices, and the bonds. These were attached as exhibits. That the work order was issued January 19, 1942; that plaintiff started work on the project, completed the piers and abutments, and had received the reinforcing steel when he was forced to cease work on the project and has been unable to continue due to the participation of the United States in the present World War. The causes arising from war conditions which made the continuance of the contracts impossible were alleged to be: (1) The refusal of the federal government to permit steel companies to ship structural steel needed for the completion of the project because its use was necessary for war purposes, and that it is impossible to foresee when structural steel will be available. (2) The War Production Board placed a stop order on the project December 24, 1942, requiring cessation of further work. (3) Plaintiff was informed by army officials, through his agent, J. W. Ballard, secretary of the Kansas Contractors Association, that unless equipment was made available for war projects, such equipment would be taken under authority of U. S. C. A., Title 50, section 721, and made available for government use. (4) The priorities for highway construction *11 were not sufficient to enable plaintiff to obtain repairs for equipment even though it were available. (5)- Labor has been withdrawn from highway construction to work on war projects and is not and cannot be made available. That because of such conditions plaintiff is unable to continue the work on the project and that it cannot be foreseen when, if ever, he will be able to do so; that if at some future date he might be able to complete the work, conditions have so changed that the work could not be completed under the terms and conditions the contracting parties had in mind when the contracts were made; that the contracts provided for a limited time for completion, which time has long since expired, but defendant has failed and refused to cancel the contracts and plaintiff is being hampered and damaged in the conduct of his business by reason thereof. The prayer was for a decree that the contracts are no longer in force and an order that the defendant cancel the same, that an accounting be had for the work done, and for such other relief as the court finds just and equitable.

Attached to the petition as exhibit “B” is a copy of plaintiff’s proposal for a contract for the construction of one of the bridges, which reads:

“Pin Check Here
State Highway Commission op Kansas proposal'
“1. Proposal of F. H. Freeto for the construction and improving of Project No. 39-67 FA 567 A (1) in Neosho county, state of Kansas, by the construction of the work as shown by the plans, drawings and specifications for the above-mentioned project'as set forth in the schedule of prices.
“2. All work to comply with the Standard Specifications for State Road and Bridge Construction, Edition 1937, and printed pamphlet of Supplemental Specifications dated April 1, 1939, of the State Highway Commission of Kansas.
“To the State Highway Commission:
“3. The undersigned agrees to execute a contract for the proposed work within ten (10) days after the date of the award of the contract and to begin work within ten (10) calendar days of the date stated in the work order and to complete the work, if this proposal is accepted” on the several portions of the project within a stated number of working days. There is the further statement that the proposal is tied with the proposal of the same submitted upon the construction of the other bridge, and that plaintiff would not accept one unless awarded the other. It further recites:
“5. In submitting this bid the undersigned declares that he is the only person interested in the said bid; that it is made without any connection with *12 any person or persons making another bid for the same contract; that the bid is in all respects fair and without collusion, fraud or misrepresentation.
“6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T.S.I. Holdings, Inc. v. Jenkins
924 P.2d 1239 (Supreme Court of Kansas, 1996)
Butler Manufacturing Co. v. Americold Corp.
850 F. Supp. 952 (D. Kansas, 1994)
State Ex Rel. Stephan v. Kansas Racing Commission
792 P.2d 971 (Supreme Court of Kansas, 1990)
Sunflower Electric Cooperative, Inc. v. Tomlinson Oil Co.
638 P.2d 963 (Court of Appeals of Kansas, 1981)
Wichita Properties v. Lanterman
633 P.2d 1154 (Court of Appeals of Kansas, 1981)
Simpson v. KFB Insurance Co., Inc.
498 P.2d 71 (Supreme Court of Kansas, 1972)
Shunga Plaza, Inc. v. American Employers' Insurance
465 P.2d 987 (Supreme Court of Kansas, 1970)
Stauffer v. City of Topeka
436 P.2d 980 (Supreme Court of Kansas, 1968)
Kendall Plumbing, Inc. v. St. Paul Mercury Insurance
370 P.2d 396 (Supreme Court of Kansas, 1962)
Nelson v. Robinson
336 P.2d 415 (Supreme Court of Kansas, 1959)
Bailey v. Talbert
294 P.2d 220 (Supreme Court of Kansas, 1956)
Knouse v. Equitable Life Insurance
181 P.2d 310 (Supreme Court of Kansas, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
166 P.2d 728, 161 Kan. 7, 1946 Kan. LEXIS 224, Counsel Stack Legal Research, https://law.counselstack.com/opinion/freeto-v-state-highway-commission-kan-1946.