Clark Co. v. Miller

122 So. 475, 154 Miss. 233, 1929 Miss. LEXIS 133
CourtMississippi Supreme Court
DecidedMay 20, 1929
DocketNo. 27590.
StatusPublished
Cited by8 cases

This text of 122 So. 475 (Clark Co. v. Miller) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark Co. v. Miller, 122 So. 475, 154 Miss. 233, 1929 Miss. LEXIS 133 (Mich. 1929).

Opinion

Appellee filed his bill in the chancery court of Leflore county on behalf of the Yazoo-Mississippi Delta levee board against appellants, R.T. Clark Co., a partnership composed of R.T. Clark, R.L. Cheshire, R.P. Harris, and C.H. Dulaney, levee construction contractors of the said levee district, and the United States Fidelity Guaranty Company, surety on their contractors' bond, to recover from the contractors the sum of three hundred seventy-eight thousand three hundred thirty dollars, with interest, and from the Guaranty Company one hundred sixty thousand dollars of that amount, the penalty of the contractors' bond with interest, as damages suffered by the levee district, because of an alleged breach by the contractors of a levy construction contract theretofore entered into between the said R.T. Clark Co. and the Yazoo-Mississippi Delta levee board. Copies of the contract and of the bond were made exhibits to the bill. A trial was had on bill, answers, and proofs, resulting in a final decree in favor of the appellee for the amounts sued for with interest. From that decree, appellants prosecute this appeal. *Page 236

This is the second appearance of this case in the supreme court (Clark v. Miller, 142 Miss. 123, 105 So. 502). The former appeal was for the purpose of settling the principles of the cause; and the case as then presented, with the opinion of the court, should be considered in connection with this case in order to get the full meaning of the present decision. The bill first filed made R.T. Clark Co., the Guaranty Company, and the members of the levee board who voted for the raise in the contract price of the levee work, defendants, and sought the same recovery against R.T. Clark Co. and the Guaranty Company as in the present case, and, in addition, sought to hold the levee commissioners who voted for the increase in price and the sureties on their bonds liable for such increase in price. On the former appeal, the court held, among other things, that the bill was multifarious; that separate suits should have been brought against R.T. Clark Co. and the Guaranty Company on the one hand, and the levee commissioners who voted for the increase, and the sureties on their bonds on the other hand; and on the remand of the case that was accordingly done. Substantially the same bill, as was originally filed against all the parties, was filed against the appellants in this case. The allegations of the bill are set out in the opinion of the court on the former appeal, and we deem it unnecessary to repeat them here.

The Guaranty Company, R.T. Clark, and R.P. Harris separately answered the bill denying that the contract had been breached by R.T. Clark Co., and averred, in substance, that the participation of the United States in the World War had increased the cost of labor and materials going into the levee work to such an enormous extent as to render it impossible for the contractors to complete the work at the contract price without great loss, and for that reason the levee board, recognizing the emergency for the completion of the work, raised the contract *Page 237 price fifty per cent. Dulaney, one of the partners in the firm of R.T. Clark Co., adopted the answer of the Guaranty Company; Cheshire, the other partner, did not answer.

There was no conflict in the material evidence; and we think a fair statement of the evidence in the case is contained in the brief of the Guaranty Company and that of the revenue agent, which follow in the order referred to:

"Clark, Harris, Cheshire and Dulaney were not partners generally. Each had his outfit and was doing construction work with it. They got together to bid on this particular work with a view to dividing it up among themselves and each doing a part. They contracted with the Levee Board as R.T. Clark Company. They were referred to in the bond as R.T. Clark, R.P. Harris, R.L. Cheshire and C.H. Dulaney, trading as R.T. Clark Company, and they signed the bond R.T. Clark Company, by R.T. Clark, by R.P. Harris, by R.L. Cheshire, by C.H. Dulaney, by L.C. Dulaney, Agent and Attorney-in-fact. At the time they bid on this work and got the contract Dulaney's outfit was at work on a contract in Louisiana and it was understood between them that he was to finish that work before coming on this. Clark, Harris and Cheshire moved their outfits on the job and started work the last of 1916 or early in 1917. The date could not be definitely fixed and the exact time is uncertain. The Engineer, Mr. Head, thought it was in February, 1917 which was probably correct in view of the fact that the first estimate allowed was on the 1st of March, 1917, but the actual date of beginning the work is not material. It was begun, at all events, before April 1, 1917 when the contract provided they were to begin if river conditions permitted. They were first hindered in their work by rains and high water. The United States having entered the war with Germany begun to draft their labor and left them without sufficient men to man *Page 238 their teams at times. War conditions were greatly increasing the cost of labor and material and the cost of doing the work. In the months of July, August, September, October, November and December, 1917, the board appears not to have had any money to pay them for their work and gave them estimates not payable until January 10, 1918, which the contractors had to raise money on their bank. In the winter of 1917-18 they had unusually cold weather and heavy snows and the flu epidemic hit their camps and they had further difficulty in carrying on their work. Dulaney, it seems, had on account of the increase of the cost of everything, met his Waterloo in Louisiana and his creditors had taken his outfit away from him and he had never been able to join his partners in this work. The others, Clark, Harris and Cheshire, had carried on in spite of everything. Cheshire's creditors, however, sometime during 1917 took his outfit away from him and his partners were deprived of his assistance. Clark and Harris thereafter carried on alone. Clark and Harris were evidently considered to be making the best progress possible under the conditions, for it does not appear that the engineer attempted to put any force account on them under Section 9 of the contract hereinbefore referred to; Mr. Head testified, in effect, that he had no criticism to make of their efficiency. In the early part of 1918, inferably February, 1918, as we find the first mention of it in the Minutes of the board's meeting of February 5, 1918, Mr. Clark on behalf of his firm appeared before the Levee Board and told them that the war had greatly increased the cost of labor and material and that the work in consequence was costing much more than the contract price, and that two of his partners, Dulaney and Cheshire, had gone completely broke and their creditors had taken their outfits away from them and they were not helping, and that he and Harris who were doing the work were nearly broke and *Page 239 that while they would go on until their creditors stopped them, they could not go but a few months longer unless the board helped them by increasing their contract price; and he told them that the Mississippi Levee Board at Greenville and the Levee Board in Arkansas had increased prices under similar contracts and submitted data on the prices of materials used by them. Mr. Head, the Engineer, testified to Mr. Clark's having made practically the same statement to Major Dabney and himself, inferably, before he appeared before the board since Major Dabney was ready with a report and recommendation on the increase at the meeting of February 5th.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knight v. State
161 So. 2d 521 (Mississippi Supreme Court, 1964)
Old Ladies Home Assn. v. Hall
52 So. 2d 650 (Mississippi Supreme Court, 1951)
Freeto v. State Highway Commission
166 P.2d 728 (Supreme Court of Kansas, 1946)
Bushey v. Dale
1937 OK 716 (Supreme Court of Oklahoma, 1937)
Lowenstein v. Federal Rubber Co.
85 F.2d 129 (Eighth Circuit, 1936)
Kimel v. Missouri State Life Ins. Co.
71 F.2d 921 (Tenth Circuit, 1934)
Leggett v. Vinson
124 So. 472 (Mississippi Supreme Court, 1929)
National Surety Co. v. Miller
124 So. 251 (Mississippi Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
122 So. 475, 154 Miss. 233, 1929 Miss. LEXIS 133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-co-v-miller-miss-1929.