Collins v. State of New York

181 N.E. 357, 259 N.Y. 200, 1932 N.Y. LEXIS 926
CourtNew York Court of Appeals
DecidedJune 1, 1932
DocketClaim 18655
StatusPublished
Cited by15 cases

This text of 181 N.E. 357 (Collins v. State of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Collins v. State of New York, 181 N.E. 357, 259 N.Y. 200, 1932 N.Y. LEXIS 926 (N.Y. 1932).

Opinion

Crane, J.

On June 19, 1927, William L. Collins entered into a contract with the State of New York, through the State Department of Public Works, Bureau of Highways, for the repair of Livonia-Ontario county line highway in Livingston county, known as Reconstruction Contract No. 1582: The road was a little *202 over five miles in length and was to be reconstructed with a concrete pavement.

The contract provided that claimant was to perform certain work on a large bridge designated as No. 3, in the village of Hemlock, which work consisted in removing the old truss, refacing the old abutments, the construction of new wings, the recapping of the old center pier, with a small extension on the west end, and the construction of a new floor slab with parapets.

Old bridge No. 3, which spanned the outlet of Hemlock lake, was a two-span iron truss bridge, about seventy feet in length, resting upon masonry 'abutments, and a center pier -which stood in the outlet of the lake.

The center pier at ground level was about thirty-five feet in length, twelve feet in height and about nine feet in width at the base. It was. an old masonry pier consisting of stones mortared up. Some sections of the pier where it had previously been repaired consisted of concrete.

The plans and drawings made a part of the contract, and set forth in detail the work required to be performed to construct a reinforced concrete T beam bridge, with floor pavement, slab and parapet, in place of the existing iron truss bridge.

These plans set forth that the old center pier, when altered as provided thereby, was to remain in place, as a center support for the new bridge. The plans provided that claimant should cut down the elevation of the pier slightly by cutting off the top and recapping it, and extend the length of the pier upstream about five feet by adding a concrete extension on the end, and also provided for refacing the downstream end.

When the contractor reached the work on the bridge and pier, it was discovered that the interior of the old pier, instead of being solid and suitable to be used in the construction of the bridge, was composed of a fill of loose stone and unstable materials. Wilson Harger, bridge *203 engineer of District No. 4, New York State Department of Highways, testified that at the time of his investigation to ascertain the work to be done, the pier seemed to be solid and firm, and, in fact, seemed to be in better condition than either the north or south abutment. “ We knocked off some of the outside plaster with hammers, and examined it with a short drill. We also got the history of the pier from the local people, and we came to the conclusion that the probabilities were that the pier could be utilized essentially as shown on the plan, although we admitted the possibility of some further modification.”

Later, when the contractor had reached this part of the work, Harger made another inspection, and testified: “And the object of my inspection on that day was to examine this pier to determine whether it could be utilized as called for on the plans, or whether some modification would be necessary to ensure stability of the structure. The result of that inspection, after finding the masonry as described, was that I ordered the engineer — Mr. James Douglass — to have the pier entirely removed and an entire new pier constructed of exactly the same general dimensions in regard to batter, top, width and grade as shown for the pier extension on the original plan.”

The Mr. Douglass referred to, testified, regarding the pier, as follows: “ I found a fairly good outer crust on the top of the pier that was exposed. But the inner portion was composed of stone and very loose broken up mortar, and some dirt. * * * I found the same rotten condition of the inner core — the pier core.”

Collins, the contractor, was, therefore, ordered through the bridge engineer, and his assistant civil engineer, to destroy the pier, a stone structure about thirty-five feet in length, twelve feet high and nine feet in width, built in the bed of a stream. This meant blasting with dynamite, the construction of an earth dyke, or cofferdam, *204 and the rebuilding, from a depth a little lower than the original, of a new pier.

Collins protested that this was no part of his contract; that the State was preventing the execution of the contract as made. That called for the use of the old pier by cutting off the top and recapping it and extending its length. The very structure which the plans and specifications required him to use in constructing the new bridge, to wit, the pier, was to be destroyed and taken away by the State, so that he, Collins, could not do the work unless he rebuilt that which the State was to supply. This in his opinion was a breach of the contract, and he protested. On the other hand, Harger, the bridge engineer of the district, acting in perfect good faith, considered this work merely a modification of the plans, coming within the provisions of.section 4 of the contract which reads as follows: "4. * * * The State, however, reserves the right to make such additions, deductions or changes as it deems necessary, making an allowance or deduction therefor at the prices named in the proposal for this work, and this contract shall in no way be invalidated thereby; and no claim shall be made by the Contractor for any loss of anticipated profits because of any such change, or by reason of any variation between the approximate quantities and the quantities of the work as done. It is further agreed that any extra work performed or extra material furnished shall be covered by a supplemental contract as provided in Chapter 30 of the Laws of 1909 and the amendments thereto, and that no claim will be made by the Contractor for any such items performed or furnished before such supplemental contract shall have been approved by the Comptroller of the State of New York and executed by the Commissioner of Highways as provided by Chapter 342 of the Laws of 1913 and amendments thereto.”

The contractor did the work, finished it by December, 1927, and under protest, in March of 1928, received from *205 the State pay for this rebuilding of the pier at the prices named in the proposal for the work. The State engineers contended that the removal of the old pier was work which came under the excavation item of the contract, for which claimant was to be paid fifty cents per cubic yard, and that the construction of the new pier came under the item for second class concrete, for which claimant had a contract item price of $10.50 per cubic yard. In preparing the final estimate and making payment, the Highway Department and the Comptroller assumed that the work came within the contract provisions and under the items and prices for unclassified excavation and second class concrete, and allowed and paid claimant for the quantities of excavation and concrete under these two items.

The claim which the contractor has presented to the Court of Claims is for his damages sustained when the State of New York, in breach and violation of the provisions of said contract, directed and compelled claimant over his protest to blast out, excavate and entirely remove said old center pier, and construct an entire new center pier in place thereof.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kalisch-Jarcho, Inc. v. City of New York
533 N.E.2d 258 (New York Court of Appeals, 1988)
County Asphalt, Inc. v. State
40 A.D.2d 26 (Appellate Division of the Supreme Court of New York, 1972)
County Asphalt, Inc. v. State
63 Misc. 2d 329 (New York State Court of Claims, 1969)
Garofano Construction Co. v. State
206 Misc. 760 (New York State Court of Claims, 1954)
Michael v. State
276 A.D.2d 806 (Appellate Division of the Supreme Court of New York, 1949)
Michael v. State
192 Misc. 464 (New York State Court of Claims, 1948)
Spencer, White & Prentis, Inc. v. City of New York
189 Misc. 616 (New York Supreme Court, 1945)
Arc Engineering Corp. v. State
267 A.D. 797 (Appellate Division of the Supreme Court of New York, 1943)
Griffis v. State
11 N.W.2d 138 (South Dakota Supreme Court, 1943)
Shapiro v. George F. Driscoll Co.
266 A.D. 260 (Appellate Division of the Supreme Court of New York, 1943)
Nugent v. State
265 A.D. 549 (Appellate Division of the Supreme Court of New York, 1943)
Mirabelli v. City of New York
262 A.D. 60 (Appellate Division of the Supreme Court of New York, 1941)
Schroeder v. State
162 Misc. 105 (New York State Court of Claims, 1937)
Fowler & Banko, Inc. v. State
243 A.D. 653 (Appellate Division of the Supreme Court of New York, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
181 N.E. 357, 259 N.Y. 200, 1932 N.Y. LEXIS 926, Counsel Stack Legal Research, https://law.counselstack.com/opinion/collins-v-state-of-new-york-ny-1932.