Nugent v. State

265 A.D. 549, 40 N.Y.S.2d 361, 1943 N.Y. App. Div. LEXIS 6353
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 3, 1943
DocketClaim No. 23969
StatusPublished

This text of 265 A.D. 549 (Nugent v. State) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nugent v. State, 265 A.D. 549, 40 N.Y.S.2d 361, 1943 N.Y. App. Div. LEXIS 6353 (N.Y. Ct. App. 1943).

Opinion

Hill, P. J.

Plaintiff-appellant has recovered a judgment against the State for one of several items for which his claim [550]*550was filed. The State has paid the judgment and has stipulated that the acceptance thereof will not prejudice his right to seek a recovery for unallowed items. The claim arose in connection with a contract to build three and a half miles of the Eastern State Parkway. It is alleged that there was a breach of contract 11 by virtue of unreasonable, unnecessary and material changes along in excess of eighty-six per cent of the length of the road; ” there were vigorous protests, but by reason of imperative written and parol orders given by the State acting through the chief engineer of the Taconic State Park Commission, claimant was required to act to his damage and injury. The allegation as to damages reads: ‘ ‘ The excess cost to the undersigned claimant of completing the said contract by reason of the acts of omission and commission, malfeasance and misféasanee of the State of New York acting through the Taconic State Park Commission as aforesaid, is the sum of $110,000, and interest thereon from March 15, 1933.” Claimant argues that upon the trial before the Court of Claims he established that the reasonable value of the work performed on the excavation, trenching and grading items was $239,930.91, that he received at the unit prices in the contract $171,281.11, leaving a balance his due on a quantum meruit basis $68,649.80. The amount now claimed is the latter figure after deducting his recovery of $8,565.71. Proof as to damages was made by an expert accountant from claimant’s records and bank accounts under a theory that as to excavation, trenching and grading, the unit prices in the contract were entirely voided, and a recovery should be had on a cost plus basis.

The decision states that the award is for 1227.18 cubic yards of rock excavation at $8 per cubic yard, less $1.02, the amount bid per yard, which had been paid as a part of the final estimate. The basis for the recovery is stated in the findings: “ That the State, through its agency, the Taconic State Park Commission interfered with the progress of the work by failing and omitting to provide the contractor with channel grades in due time to conform with the normal progress of the work, and by compelling the contractor to perform such requirement as a secondary operation subsequent to the usual and normal time for performing it which was contrary to good engineering practice. ’ ’ Claimant appeals from the judgment for inadequacy and from the portion thereof which dismisses other items of his claim, notice of which was filed September 6,1933. The first hearing was held on May 2, 1938. The judge who heard the claim died before the decision.

[551]*551The road was to be built in a new location, over rough virgin land, with variable contours, covered in part with trees and brush, with some outcroppings of ledge rock and many surface boulders. The southerly station was 279, the northerly 465. In the original contract it crossed Roaring Brook at six locations where bridges were to be built. These were not included in claimant’s contract, but he was required to make certain channel changes in the brook at the proposed bridge sites. Later the State let the contract to Fox-Reynolds, Inc., to build four bridges. The location had been so changed as to eliminate two originally planned. Claimant was notified by the engineer that the roadway had been changed between stations 349-50 and 402, to an entirely new route on the westerly side of the brook, whereas previously it had been on the easterly side.

The proposal form furnished by the State contained an estimate, “ earth excavation 42,000 cubic yards, rock excavation 94,000 cubic yards, embankment 146,000 cubic yards.” It is admitted that the State finds no data sustaining the rock estimate. Claimant testified that as a result of bar tests it was his opinion that ledge rock did not exist on the original location at many points indicated on the State’s cross sections, and would not exceed 30,000 cubic yards, with earth excavation proportionately increased above the State’s estimate, and he believed that the contract was reasonably balanced between earth and rock excavation, with fills of sufficient depth to dispose of the rock, and sufficient earth for filling and covering the rock, so that borrow would not be required. In reliance thereon he bid $1.02 per cubic yard as a fair composite price for the entire excavation work, both earth and rock, together with fifteen cents per cubic yard for embankments which it was expected would be made from the earth excavated on the line of the road.

The claimant began work at the south end of the contract, working northerly, clearing the lines of the road, stripping and storing top soil and expecting to carry on the excavation and grading in a continuous manner to the northerly end. In about a month he was prepared to drill and excavate the first rock cut. He requested the engineers in charge to establish the grade for the tile underdrain so that he could drill and excavate the channel while the rock excavation within the roadway lines was being done. His request was refused. The engineers informed him that the “ grades for the roadway might be changed, that final grades had not been determined and trench[552]*552ing for underdrains could not be performed at that time.” Claimant protested and informed the engineers that the cost would be greatly increased in performing the work as a secondary operation. In January, 1932, while claimant was clearing the ground northerly of station 402, he was ordered to stop for the reason that a change in the location of the roadway was going to be made, and in April following a change was made from station 393 to 465, and new plans and cross sections were furnished. (This was the second change between station 393 and 402.) Upon examination it was claimant’s opinion that the second change would again increase the rock excavation and would further unbalance the entire project as between excavation, cuts, fills and embankment work.

Claimant complains that in September, 1931, the chief engineer, Bradner, required that he abandon the orderly progress of the work which he had started at the southerly end of the road and do such grading as might be found necessary to construct a work road to the places where the four bridges were to be built by the Fox Company. The work road was to be built on the line of the new highway. Claimant testifies to an oral protest: “ I said, ‘ If we got to go and make a road, that will eat up a lot of the earth and we won’t be able to do any rock work, because we will have to keep on going to get this road. * * * It will do me a lot of harm.’ He [Bradner] said 1 It don’t make any difference, you go ahead,’ I said ‘ If I go ahead I am going ahead under protest. Somebody has to pay me for doing this work. * * * If I go ahead and make roads for trucks, I will have to use all of the earth up and I won’t have time to blast any rock. ’ ”

The Court of Claims found against the claimant on this item. He was sustained by Fox, the bridge-builder, who gives testimony: “ Q. Did you have a conversation with anyone there relative to this contract before you filed your bid? A. I did. Q. With whom? A. Mr. Bradner. Q. And in the conversation with Mr. Bradner was there any reference made by him, or by you, to the matter of your getting access to the site of these bridges, if you received the contract? * * * A. Yes, there was. Q. Give us the conversation. * * * A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. State of New York
181 N.E. 357 (New York Court of Appeals, 1932)
Gearty v. . Mayor, Etc., of New York
63 N.E. 804 (New York Court of Appeals, 1902)
Lentilhon v. . City of New York
77 N.E. 1184 (New York Court of Appeals, 1906)
Borough Construction Co. v. City of New York
93 N.E. 480 (New York Court of Appeals, 1910)
Lentilhon v. City of New York
102 A.D. 548 (Appellate Division of the Supreme Court of New York, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
265 A.D. 549, 40 N.Y.S.2d 361, 1943 N.Y. App. Div. LEXIS 6353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nugent-v-state-nyappdiv-1943.