Molloy v. Village of Briarcliff Manor

145 A.D. 483, 129 N.Y.S. 929, 1911 N.Y. App. Div. LEXIS 4769
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 2, 1911
StatusPublished
Cited by16 cases

This text of 145 A.D. 483 (Molloy v. Village of Briarcliff Manor) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Molloy v. Village of Briarcliff Manor, 145 A.D. 483, 129 N.Y.S. 929, 1911 N.Y. App. Div. LEXIS 4769 (N.Y. Ct. App. 1911).

Opinion

ÜARR, J.:

The defendant appeals from a judgment against it for the sum of $10,680.48 damages and costs, recovered by the plaintiff as an alleged balance due under a written contract between the parties for the construction of a public highway of the defendant. The contract in question was based upon plans and written specifications which in express terms were made a part of the contract itself. 4 It provided for the doing of all the work and the furnishing of all the materials required by the plans and specifications for the lump sum of $31,900. The contract further provided as follows: “ For any increase or deduction which may be made for changes as provided for in the specifications aforesaid ” (here follows an enumeration of twenty-two different items of work with a price specified for each). The specifications contained a clause as follows: “The engineer shall have the right to make such changes in the plans and specifications either before or after the contract is awarded or as may from time to time appear desirable and such changes shall in no wise invalidate the contract. The contract price shall be increased or decreased in accordance with the schedule of prices bid by the contractor. Should any work be required that is not included in plans and specifications such work shall be done under the written order of the engineer after price has been agreed therefor, and approved by the Board of Trustees.” The written bid of the contractor provided as follows: “Ido hereby offer and agree to furnish all the materials to fully and faithfully perform all the work in accordance with plans and specifications and complete in a workmanlike manner the above work for the sum of $31,900.00. I hereby agree to accept the following named unit prices for any increase or deduction which may' be made for changes as provided for in specifications for said improvement ” (here follows an enumeration of twenty-two separate items with prices, the same as that set forth in the contract itself). The specifications contained a heading, “Instructions to Bidders,” under which appeared a provision as follows: “Bids will be made upon the blank form attached to specifications, said specifications with original bid will be attached to and form part of the contract. A lump sum proposal shall be made.” The [486]*486specifications contain a further provision headed •“ Engineer’s Estimate of Quantities,” with a list of quantities, together with a clause relating thereto as follows: “The Contractor must satisfy himself regarding the conditions governing the work, of the. nature and extent of the materials required in the work.” The contract provided, on this point, as follows: “The party of the second part [the contractor], admits and agrees that the amounts and quantities of materials to be furnished and work done, as stated in the' proposals for estimate for the said work, are approximate only; that the said party of the second part is satisfied that the engineer’s estimates of quantities is sufficiently accurate to determine the prices according to which he agrees to do' the work required by this contract in accordance therewith; and that he shall' not or will not at any time dispute or complain of such statement, nor assert that there was any misunderstanding in regard to the depth or character of the excavation to be made or the nature or amount of the materials to be furnished or work to he done,” etc.

The plaintiff has performed the work required to be done under his contract, except possibly as to an insignificant detail as to which he makes allowance, and the present controversy between the parties is as to the balance due after, credit^ ing payments made. The plaintiff claimed a balance of $9,133.18 and recovered therefor,, while the defendant admitted a balance due of $5,061.47, subject to a deduction of $102.31. The contract contained the usual clause for the' certificate of the engineer as' a condition precedent to payments, together with the usual provision that such certificate should be final and conclusive. A certificate was given by the engineer, but it is challenged by the plaintiff as false and fraudulent, and also as based upon an erroneous interpretation of the contract provisions. There is nothing in the record to show any fraud or intentional misconduct on the part of the engineer in the making of the certificate, but there is quite a controversy whether, he did hot make a palpable mistake in construing the contract provisions according to which he attempted to compute and adjust the amount payable to the plaintiff on the final payment. The principal dispute between [487]*487the parties arose as follows: The specifications contained a clause as follows: £‘ Surplus excavation estimated at 8,000 cubic yards shall be hauled by contractor to Scarborough Dock to be used in filling in- the same. ” After the work was begun it was found that Scarborough dock could not he used by the parties to the contract, and the engineer directed that the surplus excavation should he hauled elsewhere. This surplus excavation amounted actually to 9,456 cubic yards instead of 8,000 yards as estimated. Scarborough dock was about one mile from the highway under construction, and at the end of a downhill grade. The material to he supplied by the contractor was to be delivered to him at this dock, and his plan of operation contemplated sending to-the dock his trucks loaded with surplus earth, the trucks to return with materials to he used in the performance of his contract. As before indicated, the contract contained an enumeration of items and prices for “ any increase or deduction which may he made for changes as provided for in the specifications,” and among such items was one as follows: “ Overhaul, per cubic yard, per mile the sum of .528.” A similar enumeration of items in the specifications contained the same item and price. The word overhaul ” seems to have been used as synonymous with £ surplus excavation. ” The plaintiff claims an allowance for every cubic yard of surplus excavation at the rate of fifty-two and eight-tenths cents a cubic yard, while the defendant’s engineer has allowed him hut for 4,405 cubic yards at the rate of thirty-five cents a cubic yard, making a difference between plaintiff’s claim and the defendant’s allowance of $3,451.02. It appears that this surplus excavated material was hauled to and disposed of at various places, none of them requiring a haul of more than 3,500 feet, and some of them along the line of the improvement itself. As stated, the engineer allowed for 4,405 cubic yards at the rate of thirty-five cents a cubic yard. This allowance Was computed by taking as a standard the actual maximum haul of 3,500 feet and fixing the charge at the rate of fifty-two and eight-tenths cents a mile, making a cent a mile. ■ For the remaining 5,051 cubic yards he made no allowance at all, on the theory that this material was not hauled away from the place of the improvement and did not constitute ££ overhaul ” [488]*488in the sense in which the word was used between the parties. The trial court adopted-the plaintiff’s claim and made allowance for 9,4-56 cubic yards of “ overhaul ” at the rate of fifty-two and eight-tenths cents a yard, irrespective of the distance of the haul. In so doing the learned court fell into error. The contract between the parties was for a lump sum, unless changes should be made thereafter in the plans and specifications entailing more or less work. ' If such changes were made, and the work to be done, because thereof, was increased or decreased, then either increase of payments or allowance of credits were to be made as to various items of work at scheduled prices.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson, Drake & Piper, Inc. v. State
41 Misc. 2d 804 (New York State Court of Claims, 1964)
Bradshaw v. Wolfe City
3 S.W.2d 527 (Court of Appeals of Texas, 1927)
Ajax Drainage Contracting Corp. v. City of New York
125 Misc. 794 (New York Supreme Court, 1925)
Wade v. City of Tacoma
230 P. 99 (Washington Supreme Court, 1924)
Palmberg v. City of Astoria
228 P. 107 (Oregon Supreme Court, 1924)
Williams v. Hamilton Fire Insurance
118 Misc. 799 (Appellate Terms of the Supreme Court of New York, 1922)
Freeman v. Ralph Realty Corp.
198 A.D. 788 (Appellate Division of the Supreme Court of New York, 1921)
Snare & Triest Co. v. City of New York
191 A.D. 184 (Appellate Division of the Supreme Court of New York, 1920)
Richman v. City of New York
89 Misc. 213 (New York Supreme Court, 1915)
Callan v. Peck
91 A. 34 (Supreme Court of Rhode Island, 1914)
Uvalde Contracting Co. v. City of New York
160 A.D. 284 (Appellate Division of the Supreme Court of New York, 1914)
Molloy v. Village of Briarcliff Manor
158 A.D. 456 (Appellate Division of the Supreme Court of New York, 1913)
Atlantic, Gulf & Pacific Co. v. Woodmere Realty Co.
156 A.D. 351 (Appellate Division of the Supreme Court of New York, 1913)
Mechanics' Bank v. City of New York
151 A.D. 87 (Appellate Division of the Supreme Court of New York, 1912)
F. W. Carlin Construction Co. v. New York & Brooklyn Brewing Co.
149 A.D. 919 (Appellate Division of the Supreme Court of New York, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
145 A.D. 483, 129 N.Y.S. 929, 1911 N.Y. App. Div. LEXIS 4769, Counsel Stack Legal Research, https://law.counselstack.com/opinion/molloy-v-village-of-briarcliff-manor-nyappdiv-1911.