Palmberg v. City of Astoria

228 P. 107, 112 Or. 353, 1924 Ore. LEXIS 65
CourtOregon Supreme Court
DecidedJuly 22, 1924
StatusPublished
Cited by11 cases

This text of 228 P. 107 (Palmberg v. City of Astoria) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmberg v. City of Astoria, 228 P. 107, 112 Or. 353, 1924 Ore. LEXIS 65 (Or. 1924).

Opinions

BURNETT, J.

As stated in Palmberg v. Astoria, 101 Or. 224 (199 Pac. 630, 16 A. L. R. 1125):

‘‘This is an action to recover damages which the plaintiff claims to have sustained by reason of error committed by the defendant through mistake in materially understating in its specifications the amount of embankment required to complete an improvement upon a street of defendant city, by reason of which misrepresentation the plaintiff was induced to bid a lower sum for completing the improvement and to expend a greater sum of money therefor than would have been necessary had the conditions been as specified in defendant’s advertisement for bids.”

There, a demurrer was sustained to the complaint in the Circuit Court and the plaintiff appealed. The judgment of the Circuit Court was affirmed on the ground that the complaint did not allege that the specifications and profile described therein were all the data to which prospective bidders were referred and further, that the complaint was defective in that is merely stated that there was a mistake made by the surveyor and did not charge that the error was due to carelessness, negligence or incompetency of the agent of the city, who made it. On the authority of Williams v. Pacific Surety Co., 66 Or. 151 (127 Pac. 145, 131 Pac. 1021, 132 Pac. 959, 133 Pac. 1186), the cause was remanded to the Circuit Court with per[356]*356mission to the plaintiff to apply there for leave to amend his complaint. In pursuance of this commission, the plaintiff applied to and obtained from the Circuit Court permission to amend his initial pleading. In its changed form that document recites the municipal character of the defendant, the existence of Olney Avenue, and narrates the passage of a resolution for the improvement of that thoroughfare. It is then averred in substance that after the publication of its notice of intention to make the improvement, the city surveyor submitted plans including one profile, a copy of which was attached to and made part of a complaint, and specifications for the proposed street improvement which were filed with the auditor and police judge. Then follows this allegation:

“That said specifications, among other things, so far as relevant or material to the matters and things as hereinafter alleged, provided as follows:

“Items of Work and Material.

Item No. Total Quantities Units Prices Totals

Excavation 9,650 cu. yds. cu. yd.

Embankment 17,087 cu. yds. cu. yd.

16 ft. planked roadway 390 ft. per ft.

5 ft. wooden sidewalk 820 ft. per ft.

Repair of Macadam between 7 th and 5th

Macadam, 6 in. thick by 20 ft. by 355=160 cu. yds. consolidated

“Note: Embankment can be obtained from 10th Street and from 5th and 6th Streets. That the fore[357]*357going figures and items constitute and are the only items or data contained in said specifications indicating the nature or amount of work to be performed.”

As imputing tort to the defendant, the allegation of the amended complaint reads thus:

“That said Alfred S. Tee, while so acting for and on behalf of defendant City, in his said capacity of its duly elected, qualified and acting City Engineer and City Surveyor, in preparing said plans and. specifications for said proposed street improvement as aforesaid, carelessly, negligently, falsely, with utter and reckless disregard as to the truth, substantial accuracy or correctness thereof, and for the express purpose and design of having this plaintiff and all other prospective bidders for the work contemplated by said proposed street improvement rely thereon, drew and made said specifications to read and expressly represented therein that the amount of yards of dirt to be filled (or embankment, which means the same thing) amounted only to 17087 cubic yards. That said representation was utterly false, that said Alfred S. Tee well knew, or by the exercise of ordinary care and diligence could and should have known said representation to be false and substantially inaccurate and incorrect, and well knew, or by the exercise of ordinary care and diligence could and should have known, that in order to do the work as required by said contemplated street improvement and as called for in said plans, specifications and ordinance No. 5275 as heretofore alleged, and in the Notice of Receiving Bids as hereinafter alleged, it would take almost twice as many cubic yards of embankment as represented in said specifications and Notice of Receiving Bids, to wit: 28567 cubic yards.”

It is charged that the defendant, in representing that the amount of yards of dirt to be filled was only 17,087 cubic yards,

“did so carelessly, negligently, falsely, with utter and reckless disregard as to the truth, substantial ac[358]*358curacy or correctness thereof, and for the express purpose and design of having’ this plaintiff, and all other prospective bidders for the work contemplated by said proposed street improvement, rely thereon; that said representation was utterly false; that defendant City well knew, or by the exercise of ordinary care and diligence could and should have known said representation to be false and substantially inaccurate and incorrect', and well knew, or by the exercise of ordinary care and diligence could and should have known that, in order to do the work as required by said contemplated street improvement, and as called for in said plans, specifications, ordinance No. 5275, and Notice of Receiving Bids, it would take almost twice as many cubic yards of embankment as represented in said specifications and Notice of Receiving Bids, to wit: 28567 cubic yards.”

It is further said in substance, that relying upon the quoted tabulated items and without any knowledge of its falsity, inaccuracy and incorrectness the plaintiff submitted his bid, the items of which are in words and figures as set out in the table above quoted, with this added clause:

“All complete for the sum of $19,849.00. "Will have the work completed the 1st day of July, 1919.”

Then followed the history of other steps culminating in a contract between the plaintiff as party of the first part and the defendant as party of the second part which, after the formal recitation of parties, proceeds thus in respect to the work to be performed:

“That the party of the first part, for and in consideration therefor to be paid by the party of the second part, as hereinafter stated, does hereby covenant and agree to furnish all material and to perform all labor for the construction of the improvement of Olney Avenue from the west line of Fifth Street, to the east line of Tenth Street, except the crossing or intersection of Olney Avenue with Seventh Street, in the City of Astoria, Oregon, in accordance with a [359]*359resolution of the Common Council, adopted on the 17th day of June, 1918, and the plans and specifications made and filed by the City Surveyor therefor, the said resolution and said plans and specifications and said ordinance being hereby referred to and made a part hereof to the same effect and purpose as though set out in haec verba in this contract, said ordinance being approved on the 19th day of July, 1918, and said ordinance and said resolution and said plans and specifications are hereby referred to and made a part of this contract to the same effect and purpose as though the same were set out in full herein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Philip Morris Inc.
48 P.3d 824 (Court of Appeals of Oregon, 2002)
State v. McCormick
571 P.2d 499 (Oregon Supreme Court, 1977)
P & Z Pacific, Inc. v. Panorama Apartments, Inc.
372 F.2d 759 (Ninth Circuit, 1967)
Clark v. City of Humansville, Missouri
348 S.W.2d 369 (Missouri Court of Appeals, 1961)
Nisson v. TILLMAN ET UX
323 P.2d 329 (Oregon Supreme Court, 1958)
Caribbean Engineering Co. v. Municipio de Ponce
60 P.R. Dec. 26 (Supreme Court of Puerto Rico, 1942)
Scherrer v. State Highway Commission
80 P.2d 1105 (Supreme Court of Kansas, 1938)
City of Dallas v. Shortall
114 S.W.2d 536 (Texas Supreme Court, 1938)
L. C. James Motor Co. v. Wetmore
286 P. 180 (Arizona Supreme Court, 1930)
Inland Construction Co. v. City of Pendleton
242 P. 842 (Oregon Supreme Court, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
228 P. 107, 112 Or. 353, 1924 Ore. LEXIS 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmberg-v-city-of-astoria-or-1924.