City of Richmond v. I. J. Smith & Co.

89 S.E. 123, 119 Va. 198, 1916 Va. LEXIS 95
CourtSupreme Court of Virginia
DecidedJune 8, 1916
StatusPublished
Cited by9 cases

This text of 89 S.E. 123 (City of Richmond v. I. J. Smith & Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Richmond v. I. J. Smith & Co., 89 S.E. 123, 119 Va. 198, 1916 Va. LEXIS 95 (Va. 1916).

Opinion

Keith, P.,

delivered the opinion of the court.

I. J. Smith & Company entered into a contract with the city of Richmond for the construction of a bridge over James river. Differences 'arose between the parties as to their respective rights, which resulted in an action of assumpsit being brought by the company against the city of Richmond and a judgment in favor of the plaintiff, which is now before us upon a writ of error.

The declaration embraces the common counts in assumpsit and a special count upon the contract between the parties for the construction of the bridge in question. There was a demurrer to the declaration, which involves bo question of interest or importance, and which we think wholly without merit.

The special count, as amended states that the city employed the plaintiff to construct a bridge across James river in accordance with the terms of a contract marked Exhibit “A” and made a part of the declaration; that the plaintiff, on its part, fully complied with the terms of the contract, and that while the work was being done the defendant, through its city engineer, ordered the plaintiff to do certain extra work, which is shown upon an account also filed with the declaration and marked Exhibit “B;” that the plaintiff did and performed the extra work at the instance and request of the defendant and as provided m Exhibit “A” with respect to extra work; that it [200]*200made claim therefor and called upon the defendant, through the city engineer, to fix the price of said work; but although the city, through its engineer, ordered the extra work to be done, it failed and refused to fix and determine the value and amount of the extra w;ork, which the defendant afterwards accepted, but refused to pay for, although often requested so to do, and still refuses to pay, to the damage of the plaintiff $55,000.

The object of the city was to construct a reinforced concrete bridge, at a cost not to exceed $225,000, and looking to this end it authorized an advertisement to be made on the-30th of November, 1910, by which it invited- proposals for plans, designs, drawings and specifications for the erection and construction of such a bridge. A letter of information, dated January 18, 1911, stating what would be required by the committee on streets, was delivered to prospective bidders. The condition's stated were that the plans, designs, detail drawings (drawn to scale), strain sheets and proposals were to be submitted to the committee on streets not later than February 1, 1911, and each proposal was to be accompanied by certified check for $5,000; that the bridge was to be built of reinforced concrete from shore to shore of the river, complete in every respect, and designed to have a forty-four foot roadway and two eight-foot walkways, including railing, and many other details which need not be mentioned; that all piers were to be equi-distant, and the spans of uniform length and height; that the bridge was to be designed so as to vent the river flow of the highest recorded freshet, and to be five feet above the present street surface grades on each side of the river. It was further required of the parties submitting the designs and proposals that the cost should not exceed $225,000, and this was to be for a complete structure in every [201]*201respect; and it was further required that if the committee on streets should accept any one of the designs and proposals offered, the party submitting such design and proposal would be required to enter into a contract with the committee for the construction of the bridge under a bond of fifty per cent, of the amount of the proposal. To this paper, stating what the committee on streets required of the bidders, there was appended a note as follows:

“All persons wishing to submit designs and proposals will be furnished with a blue print showing the location of the site, the present bridge and a profile of existing conditions, and parties not wishing to submit plans, specifications and proposals are requested to return all blue prints furnished them by this office.”

Among other things, this blue print showed a line from shore to shore extending across the bottom of the river and across Mayo’s Island, which was marked “rock,” and this line is of great importance in the consideration of this case. In order to secure a permanent structure, it was essential that the foundations of the piers should rest upon solid rock. This blue print with the profile was given the contractors to enable them to make an intelligent estimate of the work which they were about to undertake, and they were, of course, guided in their estimates by the depth of the excavation necessary to reach a safe foundation upon solid rock.

During the progress of the work the contractors, Smith & Company, found the solid rock bed of the river to be much below the rock line shown on the plans and profile, and on the 18th of October, 1911, they addressed to the city engineer the following letter:

[202]*202“Oct. 18, 1911.

“Mayo Bridge.

“Mr. Charles E. Bolling, City Engineer, “Richmond, Virginia.

“Dear Sir:

“On the above mentioned job we find the solid rock bed to the James river much below the rock line shown on the plans and profiles; we write to ask if you wish us to excavate down to solid rock or stop at the grade shown on the plan and profile.

“Awaiting your early reply, we beg to remain, “Yours very truly,

“I. J. Smith & Company, Inc.”

To this letter G. M. Bowers, who signs himself as “resident engineer,” replied by letter dated October 20, 1911, as follows:

“Your letter of last evening handed me, addressed to Mr. C. E. Bolling, city engineer, in regards to the depth to be excavated to for foundation of piers and abutments for the Mayo (free) bridge was delivered to me.

“Doubtless you will receive a reply from Mr. Bolling in answer to whether you should excavate only to the elevation as shown on preliminary plan submitted to bidders or to bed' rock, regardless of elevation shown on map.

“I wish to say that whatever reason you may have for stopping the excavation for foundation before solid bed rock is reached there is no reason you could give (considering the stability of the work) that would convince me that the proper foundation is other than solid bed rock, and I shall insist upon the excavation being carried to this character of foundation.”

[203]*203On October 23, 1911, the city engineer, Mr. Charles E. Bolling, wrote Smith & Company the following letter:

“Replying to your letter of 18th instant, in which you state you find a solid rock bed in the James river much below the rock lines shown in the plans and profile, and ask if I wish you to excavate down to solid rock or stop at grade shown in plans and profile. I beg to say I wish the excavation carried down to the solid rock bed. See end of clause nine in the specification, as follows: ‘The foundations will be on rock. They shall be prepared by removing all sand, mud or other soft material and by excavating to rock bed as shown on plans. Rock surface for foundations may be uneven, but large, inclined rock surfaces must be stepped before concreting is started.’ ”

This letter from Mr. Bolling was replied to on October 30, 1911, by Smith & Company as follows:

“Yours of the 23rd to hand and of course we shall follow your instructions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. City of Humansville, Missouri
348 S.W.2d 369 (Missouri Court of Appeals, 1961)
Furton v. City of Menasha
71 F. Supp. 568 (E.D. Wisconsin, 1947)
Phoenix State Bank & Trust Co. v. Burpee
14 Conn. Super. Ct. 252 (Connecticut Superior Court, 1946)
Fitzgerald v. Thompson
184 S.W.2d 198 (Missouri Court of Appeals, 1944)
Transbay Const. Co. v. City and County of San Francisco
35 F. Supp. 433 (N.D. California, 1940)
Dunbar & Sullivan Dredging Co. v. State
259 A.D. 440 (Appellate Division of the Supreme Court of New York, 1940)
Wussow v. State
267 N.W. 56 (Wisconsin Supreme Court, 1936)
Oklahoma City v. Derr
1928 OK 159 (Supreme Court of Oklahoma, 1925)
Palmberg v. City of Astoria
228 P. 107 (Oregon Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
89 S.E. 123, 119 Va. 198, 1916 Va. LEXIS 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-richmond-v-i-j-smith-co-va-1916.