Dunbar & Sullivan Dredging Co. v. State

259 A.D. 440, 20 N.Y.S.2d 127, 1940 N.Y. App. Div. LEXIS 6168
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 8, 1940
DocketClaim No. 25371
StatusPublished
Cited by7 cases

This text of 259 A.D. 440 (Dunbar & Sullivan Dredging Co. v. State) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dunbar & Sullivan Dredging Co. v. State, 259 A.D. 440, 20 N.Y.S.2d 127, 1940 N.Y. App. Div. LEXIS 6168 (N.Y. Ct. App. 1940).

Opinion

Dowling, J.

On July 17, 1936, the State, by its chief engineer of the State Department of Public Works, entered into a contract with the Dunbar & Sullivan Dredging Company of Detroit, Mich., for excavating in the Barge Canal from Lock No. 2 at Fulton to Lock No. 5 at Minetto, Oswego county, N. Y., being Contract U. S. 14. The estimated amount of excavation under the contract was 541,000 cubic yards of which approximately 207,000 cubic yards was ledge rock. The contract was an area contract and the bids were unclassified. The State agreed to pay for the excavation the sum of $1,919,640. The Dunbar & Sullivan Dredging Company agreed to supply all material, labor and machinery required for a faithful and speedy performance of the work.

The contract provided: “ The work to be commenced promptly, progressed with diligence, in the order directed and under the supervision of the Chief Engineer, Department of Public Works, and in accordance with the drawings and specifications prepared by the Chief Engineer, Department of Public Works, and to be fully completed on or before December 1, 1938 * * *. It is understood and agreed that all the terms, provisions, conditions and obligations set forth in this Agreement, the Proposal, the General Requirements, the Drawings and Specifications, constitute a part of this contract, and are to have the same force and effect as if set forth specifically and at length herein.”

The specifications provided in part:

All proposals will be held to have been made with full knowledge of conditions and requirements. The Contractor will be held to have visited the premises prior to the time of submitting bids and to have appraised conditions under which the contract is to be executed.”
Contractor will be paid in monthly approximate estimates, a sum not to exceed ninety per cent of the value of the work performed as so certified by the Engineer except as provided in paragraph 2.100.”
“ The Department of Public Works, subject to the approval of the Division Engineer, North Atlantic Division, U. S. Army reserves the right until the final completion and acceptance of the work, to make such additions to or deductions from such work or changes in the drawings and specifications covering the work as may be necessary and the contract shall not be invalidated thereby; [442]*442and the contractor shall do and complete the work in accordance with such additions to or deductions from or changes in the drawings and specifications and no claim shall be made by the contractor for any loss of profits because of any such change or by reason of any variation between the quantities of the approximate estimate and the quantities of the work as done * * (§ 1.32.)
“No claim shall be made against the State because the estimate, tests or representations of any kind affecting the work made by any officer or agent of the State, may prove to be in any respect erroneous.” (§ 1.33.)

The State prepared the plans and specifications from soundings it had taken in 1935. The contract drawings consisted of sheets 1 to 29, inclusive. . I j

The contractor entered upon the performance of the contract and completed it within the required time, to the satisfaction of the State. The contractor received final payment on the 13th of September, 1938. The contractor executed a form receipt on that occasion containing the following reservation: “ We reserve the right to file a claim for quantities in Section 1 of Contract V. S. 14 Barge Canal Improvement.”

The contract consisted of nine separate sections or subdivisions. But the excavation for each section or subdivision comprised only an item in the contract. (Sheet 1 — Information for Proposers.) There is no dispute as to any of the items except item No. 1, section No. 1, Lock 2 to Lock 3. The contract involved the deepening of the canal from twelve to fourteen feet with a foot tolerance. Sheet No. 3 of the plans depicts the dispute before us. Section 1, on sheet 3, under the heading “ Earth Cubic Yards,” indicates that there were 24,294 cubic yards of earth to be excavated in that section. In the center of sheet No. 3, marked with an asterisk, is the following notation: “ This quantity will be reduced approximately 10,000 cu. yds. because of maintenance dredging by the State between locks 2 and 3, Fulton, before contract work is executed in this section.” Sheet 3 was prepared on or before March 23, 1936. It is well to keep this date in mind because the contract was not let until July, 1936. • 1

When the contractor began to do the dredging between Locks 2 and 3 in section 1, it discovered that the State had excavated 17,676.3 cubic yards instead of the 10,000 cubic yards noted on sheet No. 3. The contractor continued with the performance of the contract and, after the work had been completed, the contractor duly presented the claim in question asking damages for breach of contract for 7,738 cubic yards at five dollars and ninety cents per cubic yard, that being the contract price, By continuing the [443]*443performance of the contract the contractor did not waive the breach of the contract by the State, if breach there was. (Byron v. Low, 109 N. Y. 291, 295, 296.) The claim came to trial before Judge Barrett. The claimant introduced the contract, plans and specifications and proof of presentation of claim. The claimant then called its engineer who testified that it was possible for one performing dredging work to determine when a specified quantity has been removed. The determination in such case is made by taking cross sections daily and keeping a check on them. The court found that the State could have determined when it had removed 10,000 cubic yards. The court found, Finding 29: That the State unnecessarily performed 7,676.3 cubic yards of excavation within Section 1 that were part of the work included in claimant’s contract.” Claimant’s engineer also testified that claimant’s bid would have been higher had it known at the time that the State would remove more than 10,000 cubic yards. It was conceded on the trial that the fair value of removing silt or earth was seventy-five cents per cubic yard. The State rested at the close of claimant’s case and moved for dismissal of the claim. Decision of the motion was reserved. Judge Barrett wrote an opinion to the effect that the State unnecessarily had removed this additional 7,676.3 cubic yards of earth, thereby greatly increasing the relative proportions of rock and earth to the claimant’s damage. Judge Barrett also held that such action upon the part of the State was not authorized under the terms of the contract and that the claimant did not waive its right to loss of profits under the provisions of the contract. The Court of Claims awarded the claimant a judgment against the State for the sum of $39,532.95, with interest from September, 13, 1938. From the judgment entered, amounting to $41,751.18, the State has appealed. The State contends that the terms of the contract preclude a recovery. The State bases its claim principally upon sections 1.32 and 1.33 of the specifications as above set forth and upon the information furnished to bidders to the effect that each section or subdivision was only an item in the contract and that the removal by the State of 17,676.3 cubic yards was approximately 10,000 cubic yards considering the fact that the contract called for the excavation of 541,000 cubic yards. The State relies on Del Balso Construction Corp. v. City of New York (278 N. Y. 154) in support of its position.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First American Commercial Bancorp, Inc. v. Saatchi & Saatchi Rowland, Inc.
55 A.D.3d 1264 (Appellate Division of the Supreme Court of New York, 2008)
Amadeus, Inc. v. State
55 Misc. 2d 27 (New York State Court of Claims, 1967)
John Arborio, Inc. v. State
41 Misc. 2d 145 (New York State Court of Claims, 1963)
Clark v. City of Humansville, Missouri
348 S.W.2d 369 (Missouri Court of Appeals, 1961)
A. S. Wikstrom, Inc. v. State
16 Misc. 2d 587 (New York State Court of Claims, 1958)
A. E. Ottaviano, Inc. v. State
202 Misc. 532 (New York State Court of Claims, 1952)
Dunbar & Sullivan Dredging Co. v. State
174 Misc. 743 (New York State Court of Claims, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
259 A.D. 440, 20 N.Y.S.2d 127, 1940 N.Y. App. Div. LEXIS 6168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dunbar-sullivan-dredging-co-v-state-nyappdiv-1940.