Foundation Company v. . State of New York

135 N.E. 236, 233 N.Y. 177, 1922 N.Y. LEXIS 854
CourtNew York Court of Appeals
DecidedApril 18, 1922
StatusPublished
Cited by44 cases

This text of 135 N.E. 236 (Foundation Company v. . State of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foundation Company v. . State of New York, 135 N.E. 236, 233 N.Y. 177, 1922 N.Y. LEXIS 854 (N.Y. 1922).

Opinion

Andrews, J.

The state designed a dam across the Mohawk river at Scotia with a canal lock at its south end. At this point a layer of gravel underlay the bed of the stream. Upon it the dam could not safely rest. Nor might cofferdams be used in its construction. It was determined, therefore, to sink caissons under compressed air to bedrock for the whole distance. The final result would be a solid concrete cut-off wall, on top of which would be placed the other structures necessary to complete the dam. The .caissons were to be twenty-four in number. Three of them were to extend beyond the others a considerable distance up and down the current, to support the piers of a bridge from which the dam gates were to be operated. For various reasons the expense of building caissons very rapidly increases with the increased, depth to which they are to be lowered. It would become important, therefore, to any one undertalcing this work to ascertain the situation of the bedrock. Investigation of this question had previously been made by the state, apparently for its own information. Its borings showed that everywhere bedrock would be reached above elevation 148, with one exception, where above that level it found rock or boulders.” The lock was also to be built of concrete. To accomplish this work it would be necessary to screen the site by sheathing or in some other way so as to make it water tight and to pump *181 the water therefrom. The cost of this pumping item depended largely upon the method to be adopted.

The appellant entered into a unit price contract with the state to build this dam and lock. The claims it now makes are based on two propositions. It says that when it made its bid, it and the state both understood that bedrock would be found not lower than level 148. The state so represented and warranted. As a fact under three caissons it was obliged to excavate 556 cubic feet below this levél. Against its protest the state compelled it to do this work — a work never contemplated by either party when the contract was made. It says also that while for the lock no more water was lifted than was always supposed to be necessary, the state so changed its plans that the method necessarily adopted was far more costly than that at first designed. Consequently, the bid for pumping did not fairly measure the actual cost. For the first of these items the Court of Claims awarded the appellant $11,417; for the second $62,272.21. The Appellate Division, however, reversed as to both on the law and the facts and dismissed the claim. But there is little or no dispute as to the circumstances surrounding the transaction.

Originally an attempt was made by another corporation to build this dam. It tried to use cofferdams for that Thfe aAvaívxA \m a IaxXyys mi Aw, wayAwA was canceled. It seemed that the caisson method was necessary. The state had, as we have seen, bored a number of holes near the site of the proposed work with a wash drill. This is not always satisfactory. A diamond drill is more accurate but more expensive. The state officials believed that they had found bedrock everywhere above level 148. In this, however, they were mistaken. In 1912 plans were- prepared and bids were invited by four advertisements published between June 6th and June 26th, 1912. Proposals would be received until July second. When this advertisement came to the *182 notice of the appellant does not appear. In his opening before the Court of Claims, however, its counsel seems to assume that it saw it at the time of its first insertion. Prospective bidders were told that various papers and plans and other information might be had at the office of the superintendent of public works. The claimant applied for this information. It was given, among other things, a sheet of drawings showing the plan and elevation of the caissons which represented them as resting on bedrock, but which contained no figures showing the depth at which bedrock would be found. It was told that the excavation lines and base of the structure as shown were but approximate. No statement was made as to the borings made by the state, nor did the boring sheet on which its results were recorded accompany the plans. In the course of its investigations, however, before presenting its bid, the claimant learned that such borings had been made and at its request this boring sheet was furnished to it. On its face it did not purport to be one of the plans on which bids were asked, but stated that it was made “ to accompany supplemental report of board of consulting engineers.” The claimant made no borings of its own, although there is some evidence that would justify the conclusion that it would have been enabled to check up the results obtained by the state in ■ two weeks. It seems to have known how the borings had been made by the state, and it was aware that borings obtained by a wash drill were not always accurate. At the same time there was also handed to the claimant a paper called “ information for bidders,” a preliminary estimate of quantities and costs made by the .state, a form of itemized proposals to be executed by the bidder, a proposed form of contract and the specifications which were made a part of it. The preliminary estimate of quantities and costs contained an item called a “ contingent item ” for 200 cubic yards of concrete pneumatic caisson work below elevation 148, and an estimate by *183 the state engineer that this would cost forty dollars per cubic yard. The information for bidders stated that the estimate of quantities is to be accepted as approximate only, and the bidders are required to form their own judgment as to quantities and character of the work by personal examination upon the ground and on the specifications and drawings relating thereto, or by such other means as they shall choose, and their attention was specifically called to paragraph 10 of the contract (an error for paragraph 11). This paragraph is to the effect that the contractor agrees that he has satisfied himself by his own investigation and research regarding all the conditions affecting the work to be done and labor and material needed, and that his conclusion to execute the contract is based on such information and research and not on the estimate of quantities or other information prepared by the state engineer, and “ that he shall make no claim against the State because any of the estimates, tests or representations of any kind affecting the work made by any officer or agent of the State may prove to be in any respect erroneous.” Under these circumstances the claimant bid, among many other items, for 200 cubic yards of caisson work below elevation 148 at twenty-five dollars a cubic yard. It received the contract to build the dam, and to do all the work necessary therefor. The work to be done is described as building three concrete pneumatic caissons, each sixty-four by fourteen feet, with tops at elevation 209, and bottom of foundation on bedrock at about elevation 166 for the southerly pier; at about elevation 156 for the middle pier; and at about elevation 149 for the northerly pier; and as building concrete pneumatic caisson cut-off walls between the piers and to shore, extending up to elevation 209 and down to bedrock. Payment was to be made at one price for work between levels 209 and 148 and at another for that below 148. If any item in the contract exceeds the quantity of the engineer’s estimate by more than fifteen *184

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greenfield v. Heckenbach
797 A.2d 63 (Court of Special Appeals of Maryland, 2002)
Costanza Construction Corp. v. City of Rochester
147 A.D.2d 929 (Appellate Division of the Supreme Court of New York, 1989)
Meaott Construction Corp. v. State
92 A.D.2d 730 (Appellate Division of the Supreme Court of New York, 1983)
Conduit & Foundation Corp. v. State
420 N.E.2d 397 (New York Court of Appeals, 1981)
Sasso Contracting Co. v. State
414 A.2d 603 (New Jersey Superior Court App Division, 1980)
Andrew Catapano Co. v. City of New York
116 Misc. 2d 163 (New York Supreme Court, 1980)
Twin Village Construction Corp. v. State
64 A.D.2d 866 (Appellate Division of the Supreme Court of New York, 1978)
Grow Construction Co. v. State
56 A.D.2d 95 (Appellate Division of the Supreme Court of New York, 1977)
Public Constructors, Inc. v. State
55 A.D.2d 368 (Appellate Division of the Supreme Court of New York, 1977)
A. S. Wikstrom, Inc. v. State
52 A.D.2d 658 (Appellate Division of the Supreme Court of New York, 1976)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
County Asphalt, Inc. v. State
40 A.D.2d 26 (Appellate Division of the Supreme Court of New York, 1972)
Rusciano Construction Corp. v. State
37 A.D.2d 745 (Appellate Division of the Supreme Court of New York, 1971)
Warren Bros. v. New York State Thruway Authority
34 A.D.2d 97 (Appellate Division of the Supreme Court of New York, 1970)
Depot Constr. Corp. v. State of New York
224 N.E.2d 866 (New York Court of Appeals, 1967)
Tufano Contracting Corp. v. State
25 A.D.2d 329 (Appellate Division of the Supreme Court of New York, 1966)
Johnson, Drake & Piper, Inc. v. New York State Thruway Authority
22 A.D.2d 321 (Appellate Division of the Supreme Court of New York, 1965)
Joseph F. Egan, Inc. v. City of New York
18 A.D.2d 357 (Appellate Division of the Supreme Court of New York, 1963)
John Arborio, Inc. v. State
41 Misc. 2d 145 (New York State Court of Claims, 1963)
Tomlinson Construction Co. v. State
30 Misc. 2d 1010 (New York State Court of Claims, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
135 N.E. 236, 233 N.Y. 177, 1922 N.Y. LEXIS 854, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foundation-company-v-state-of-new-york-ny-1922.