John Arborio, Inc. v. State

41 Misc. 2d 145, 245 N.Y.S.2d 274, 1963 N.Y. Misc. LEXIS 2143
CourtNew York Court of Claims
DecidedApril 5, 1963
DocketClaim No. 37188
StatusPublished
Cited by3 cases

This text of 41 Misc. 2d 145 (John Arborio, Inc. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Arborio, Inc. v. State, 41 Misc. 2d 145, 245 N.Y.S.2d 274, 1963 N.Y. Misc. LEXIS 2143 (N.Y. Super. Ct. 1963).

Opinion

John P. Gualtieri, J.

This is a claim for damages for breach of contract arising out of a highway construction contract executed by the State of New York and the claimant on May 11, 1956.

The claim alleges that the State made false and misleading representations to the claimant upon which it relied and that as a result thereof the claimant has been damaged in the sum of $343,803.42.

At the trial the following were claimed to be the items of damage: (a) $84,948 as a result of the amount of “borrow” misrepresented in the contract plans; (b) $121,192.38 (erroneously computed by claimant as $121,182.38) for increased transportation costs resulting from the misrepresentation; (c) $55,250.34 in connection with the misrepresentation of the amount of .sod to be removed in the performance of the contract; and (d) $78,247.42, damages sustained by reason of the unavailability of railroad facilities of the New York, Ontario and Western Railroad contemplated as existing when the contract was made.

Under a separate judgment of the court dated December 14, 1959, the claimant was awarded the sum of $94,097.29, the amount admitted to be due under the State’s final estimate, the matter of interest on this amount having been reserved for determination in the trial of the present action.

The contract involved the construction of a highway in Sullivan County known as Contract No. PARC 56-87, Monticello-Liberty Part II. Invitation for bids was first published about March 10, 1956. The claimant received the proposal about March 26, 1956; the bids were opened on April 19, 1956.

[147]*147In the contract plans which were merged in and became part of the contract, the State represented that the contractor would require approximately 419,725 cubic yards of “borrow” material, to be obtained by the contractor from sources outside the construction site. In the execution of the contract the claimant discovered that this approximate figure of 419,725 cubic yards turned out to be only 65,775 cubic yards. In other words, the State’s approximation was wrong by over 600%.

Also, it is contended that the State represented that there would be sod removal required to the extent of 130,238 cubic yards; it actually turned out to be 21,904 cubic yards.

It is contended by the claimant that after receiving the proposal and in preparing its bid it relied upon these representations. If the State’s representations had been reasonably accurate it projected a profit on the “ borrow ” item of $84,948 and a profit on the sod removal item of $55,250.34. With this anticipated profit leeway on these two items under section 2B it put in a bid of 68^ per cubic yard for all work performed under this section 2B of the contract labeled “ Unclassified Excavation ” made up of several component items.

We shall consider the “ borrow ” item first because the court has concluded to reach a definite result in connection with this item in the claim and the claim for the sod removal item requires separate discussion and consideration.

Here it is important to bear in mind that this was not a lump-sum contract; we have a contract in which the bidder was obliged to put in prices for each of the items broken down in the proposal.

The distinction, of course, is that if this had been a lump-sum contract any erroneous approximation of quantities on the part of the State would not result in liability. It has been held consistently that in such a contract the bidder takes his own chances. (Dunbar & Sullivan Dredging Co. v. State of New York, 259 App. Div. 440; Lentilhon v. City of New York, 102 App. Div. 548.)

We are called upon to consider therefore whether the gross discrepancy between the State’s projected figures and the actual amount subsequently found to be the fact imposes an obligation upon the State to respond in damages.

Although there are allegations in the claim that the State was guilty of fraud, no proof of fraudulent intent was offered during the trial. The court concludes, however, that proof of a fraudulent scheme is not required under the facts presented here to establish the State’s liability. A party to a contract, be it a governmental unit or an individual, cannot make reckless inaccu[148]*148rate representations to induce another to sign a contract and thereafter escape the consequences of such statements to the financial detriment of the other party. (Lowman Constr. Co. v. State of New York, 10 N. Y. S. 2d 963.)

The representations were contained in the plans and became part of the contract between the parties. This is not a ease of a bidder relying upon preliminary estimates forming no part of the final agreement.

It is apparent from the evidence before the court that the State had for at least a year or two prior to releasing the proposal engaged in studies and investigations on the site for the purpose of discovering the physical facts upon which to inform prospective bidders as to the various quantities and items which the bidders were to consider in preparing their bids. The State allowed the bidders approximately three weeks within which to prepare and submit their bids, an obviously insufficient period of time for a bidder to personally check the quantities and items recited in the proposal. A bidder has a right to rely upon the fact that the State had made its own studies reasonably accurate and that when the plans said approximately 419,725 cubic yards of “borrow” it would not turn out to be 65,775 cubic yards.

Where a bidder is allowed insufficient time within which to make a personal study, the State cannot invoke the general exculpatory clauses to exonerate itself from liability. Particularly is this true in a case such as this where no specific warning is given in connection with the particular item the representation of which is in question; or in a situation like that in the case at bar where the bidder has not time to make a personal and detailed inspection. (Young Fehlhaber Pile Co. v. State of New York, 265 App. Div. 61.)

The State knew that no prospective bidder could in the space of time alloted discover the inaccuracy of its representations as to quantities when it itself had a long period of time in which to carefully and scientifically discover the true facts.

It is remarkable that the State offered no reasonable explanation for the great disparity between its represented quantities and the actual amounts later found to be required.

It is urged by the State that the items under section 2B - unclassified materials, is made up of several components and that by considering the total of the items in that category, the difference between the represented quantities of the total items in that classification would not be as great if considered altogether. The fallacy of the State’s position is that the radical disparity between the quantities projected and the quantities [149]*149actually found to be true are confined to the two items involved, namely, “borrow” material and sod removal. It would be understandable if a reasonable variation were spread throughout all the items in the section 2B classification. This serious discrepancy would throw the computations of any bidder off kilter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lancaster Development, Inc. v. State
148 A.D.2d 892 (Appellate Division of the Supreme Court of New York, 1989)
Yonkers Contracting Co. v. New York State Thruway Authority
45 Misc. 2d 763 (New York State Court of Claims, 1964)
Johnson v. State
46 Misc. 2d 303 (New York State Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
41 Misc. 2d 145, 245 N.Y.S.2d 274, 1963 N.Y. Misc. LEXIS 2143, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-arborio-inc-v-state-nyclaimsct-1963.