Yonkers Contracting Co. v. New York State Thruway Authority

45 Misc. 2d 763, 257 N.Y.S.2d 781, 1964 N.Y. Misc. LEXIS 1844
CourtNew York Court of Claims
DecidedApril 23, 1964
DocketClaim No. 36841
StatusPublished

This text of 45 Misc. 2d 763 (Yonkers Contracting Co. v. New York State Thruway Authority) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yonkers Contracting Co. v. New York State Thruway Authority, 45 Misc. 2d 763, 257 N.Y.S.2d 781, 1964 N.Y. Misc. LEXIS 1844 (N.Y. Super. Ct. 1964).

Opinion

John P. Gualtieri, P. J.

This is a claim for damages for breach of contract arising out of a contract for the construction of a portion of the New York State Thruway, Erie Section, Subdivision E-6A, imown as Contract E. T. 56-7, S. T. 56-6, ft. 'C. 56-5. The contract was executed by the Thruway Authority and the claimant on or about March 21, "1956.

The claimant contends that the Thruway Authority made misrepresentations in the contract plans upon which the claimant [765]*765relied and, as a result thereof, it has been damaged in the sum of $231,518.06. The claimant asks for judgment in this amount plus various items of interest.

The following were claimed to be the items of damage: (a) $228,614.92 as a result of the amount of “borrow ” and “ waste ” misrepresented in the contract plans; (b) $774.87 as a result of the use of darex in the cement; (c) $2,128.27 for engineering and inspection charges improperly assessed against the claimant.

Under a separate judgment of the court entered in the office of the Clerk of the Court of Claims on September 16, 1959, the claimant was awarded the sum of $150,808.11, the amount concededly due under the Thruway’s final estimate. The matter of interest on this amount was reserved for determination in the trial of the present action.

The claimant now seeks interest at 4% ($6,484.74) on the severance judgment from September 23, 1958, the date the contract was accepted as complete, to October 20, 1959, date of payment of the severance judgment. The claimant also asks for interest on that $6,484.74 from October 20, 1959 to the date of judgment herein; and interest on items (a), (b) and (c) above from September 23, 1958 to the date of judgment herein.

The invitation for bids was first advertised on February 1, 1956 and came to the attention of the claimant during the first week of February at which time the claimant was performing another Thruway contract adjacent on the east to this contract. The claimant submitted its bid within the time allowed on February 23, 1956.

The main claim involves the amount of “borrow” and “ waste ” it was necessary for the contractor to handle in performing the contract and the expense of such handling. The plans prepared by the Thruway called for 92,795 cubic yards of “ borrow ”. The evidence submitted at trial by the claimant, which was not contested by the Thruway, showed that 237,394 cubic yards of “borrow” were actually used, 155% of the Thruway’s figure. Under the heading ‘ waste ” the plans called for the contractor to waste 30,974 cubic yards. In order to complete the contract 157,732 cubic yards of material wore wasted, an increase of 409%.

The claimant bid 62 cents a cubic yard on the “ borrow ” and 50 cents a cubic yard on the “ waste ” and all other items making up Item 2B.S, “ Unclassified Excavation ”. The claimant’s evidence, uncontested by the Thruway, showed the cost plus overhead and profit of the “ .borrow ” operations as $241,653.32. The Thruway paid the claimant at a rate of 62 cents per cubic yard for 92,795 cubic yards, the planned amount, and at 50 cents [766]*766per cubic yard for the excess 144,599 cubic yards; a total of $129,832.40. 'The claimed damage for “ borrow ” is therefore $111,820.9:2.

In the wasting operations the claimant’s evidence showed that cost plus profit and overhead amounted to $195,660. The claimant was paid at the rate of 50 cents a cuibic yard for all of the 157,732 cubic yards of “waste”, a total of $78,866. The claimed damage for “ waste ” is therefore $116,794. The Thruway therefore paid something for each cubic yard of material moved. The claimant alleges that this is insufficient because the soil conditions, the amounts and ratio of materials encountered was substantially different than what was represented in the plans and upon which the contractor computed his bid.

The court must determine if the discrepancies in soil conditions and amounts of material along with the Thruway’s action in preparing the plans and the contractor’s interpretation of the plans give rise to a situation wherein the Thruway must respond in damages for the increased soil handling.

The Thruway took over one and one-half years to prepare the plans for this portion of the Thruway. After the advertisement for bids the contractors who wished to bid had only three weeks to prepare their bids. The claimant in this case prepared its bid by studying the plans compiled by the Thruway and other data in the Thruway’s Buffalo office and by having its resident engineer make an on the spot investigation of the site. There was insufficient time for any subsurface exploration by the claimant and therefore its interpretation of subsurface conditions had to be based primarily on the figures and plans furnished by the Thruway.

The Thruway in effect planned the job for the contractor. Its figures were not estimates but definite representations of the amounts of various materials to be found within the area of the contract. The elaborate and definite plans broke the area down into balances and set forth exact amounts of “waste” and “ borrow ” to be found within each balance.

The main trouble developed in Balances 3, 5, 7 and 11. The plans had indicated “waste” of 12,326 cubic yards could be expected within these four balances; actually the contractor was forced to waste 139,083 cubic yards. The soil turned out to be very moist and because of that condition much of it was unsuitable for the subsurface of the Thruway.

The independent consulting engineering firm hired by the Thruway described the situation as follows: “soil on this contract has presented exceptional problems.”

[767]*767Although the evidence at the trial did not produce a completely satisfactory definition of “ waste ”, the court finds that the claimant’s figures on 1 ‘ waste ” are correct and this material was not suitable for the purposes represented by the plans. The contractor had to bring in from outside the contract area increased amounts of “borrow ” in order to supply enough suitable material for the Thruway. In order to obtain this “ borrow ” the claimant had to open three borrow pits on the land of private individuals near the Thruway and pay for the material removed to the Thruway.

The result was that the contractor encountered a situation it could not reasonably have expected from the Thruway plans. Due to the short time allowed to develop its bid, the completeness and definiteness of the Thruway’s figures and the superior knowledge of this area by the Thruway, the court finds that the contractor was justified in relying on the affirmative representations as to the quantities of “ borrow ” and “waste” of the State and when those representations turned out to be as inaccurate as the evidence at the trial showed, the Thruway must bear the damage that resulted from its gross misrepresentations on these two items.

This court finds the factual situation similar to that involved in the case of Dolomite Prods. Co. v. State of New York (258 App. Div. 294, 295) where the court said “ In doing the work Page was required to carry away and waste certain excavated earth, and to ‘ borrow ’ and bring in extra filling, because the excavated earth was not fit for filling, though the contract provided that it might be so used ”.

Claimant had a right to rely on the Thruway’s contract that the excavated earth could be used as fill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weston v. State of New York
186 N.E. 197 (New York Court of Appeals, 1933)
Dolomite Products Co. v. State
258 A.D. 294 (Appellate Division of the Supreme Court of New York, 1939)
Good Roads Engineering & Contracting Co. v. State
176 Misc. 1012 (New York State Court of Claims, 1941)
Garofano Construction Co. v. State
183 Misc. 1080 (New York State Court of Claims, 1944)
John H. Reetz, Inc. v. Stackler
24 Misc. 2d 291 (New York Supreme Court, 1960)
John Arborio, Inc. v. State
41 Misc. 2d 145 (New York State Court of Claims, 1963)
Bond v. Stewart
68 N.Y.S. 586 (Appellate Division of the Supreme Court of New York, 1901)