Tomlinson Construction Co. v. State

26 Misc. 2d 488, 211 N.Y.S.2d 564, 1961 N.Y. Misc. LEXIS 3364
CourtNew York Court of Claims
DecidedFebruary 17, 1961
DocketClaim No. 34472
StatusPublished
Cited by7 cases

This text of 26 Misc. 2d 488 (Tomlinson Construction Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tomlinson Construction Co. v. State, 26 Misc. 2d 488, 211 N.Y.S.2d 564, 1961 N.Y. Misc. LEXIS 3364 (N.Y. Super. Ct. 1961).

Opinion

Charles T. Major, J.

This motion is based upon an order issued on application of the claimant, which directs the State of New York and the New York State Thruway Authority to show cause ‘ ‘ why the Court should not grant a re-hearing * * * of the motion made in open court on April 27,1959, by the Attorney General to dismiss the claim and of the cross motion by claimant to substitute or join the Thruway Authority as defendant, and why the Court should not reconsider its decision of May 8, 1959 and thereupon deny the Attorney General’s said motion and grant claimant’s cross motion, and why claimant should not have such other and further relief as may be just and proper Notices of this motion were duly served upon the State and the New York State Thruway Authority. Upon the argument of the motion, claimant was represented by his attorney, the State of New York by the appearance of the Attorney-General, and the Attorney-General appeared specially for the New York State Thruway Authority. The entry of judgment of dismissal heretofore made was stayed, pending the outcome of this motion.

This claim is based upon a contract dated July 28, 1953, entered into between claimant and the New York State Thruway Authority. Claimant demands the sum of $734,619.84, with interest, and sets forth seven separate causes of action, which include balance due on completed contract, damages for delay, extra work and material, all in connection with the contract of the Thruway Authority. All of the work was completed under the contract on March 8, 1956, when the final estimate was sent to claimant with a check for $131,460.43, being the amount the State or the Thruway Authority admitted as being due and owing to the claimant.

The claimant returned the check, and on August 7, 1956 served a notice of intention to file a claim on the Clerk of the Court of Claims, the Attorney-General and the New York State Thruway Authority. On February 26, 1957, claimant duly and timely served its claim upon the Clerk of the Court of Claims, the Attorney-General and the New York State Thruway Authority. An examination of the notice of intention and claim herein shows that, although the name of the New York State Thruway Authority was not included in the title, it is very clear that the claim arose out of a contract with the New York State Thruway [490]*490Authority for work performed and materials furnished for the improvement of the Thruway under the jurisdiction of the Authority. Service of copies of the notice of intention and claim upon it were acknowledged by the New York State Thruway Authority by letter dated May 9, 1957.

After the claim was filed, the claimant’s representatives corresponded and conferred with the Thruway Authority’s Chief Engineer, in an effort to explore the possibility of arriving at a settlement. The claim was placed on the calendar of the Court of Claims, and in October, 1958 claimant moved for a change of place of trial to the Syracuse District and obtained such an order. About February 9, 1959 the claimant moved for an order granting a preference for the trial. The trial of the claim was commenced on Monday, February 16, and continued for five successive days until Friday, February 20, 1959. At the trial the claimant was represented by its counsel, and the Assistant Attorney-General, who had years of experience in defending claims against the State, appeared in opposition. A Deputy Assistant Attorny-General was associated with him. The trial proceeded in a manner indicating that the claim was the result of a contract with the New York State Thruway Authority. Before any testimony was taken, each party introduced exhibits in evidence. The Assistant Attorney-General introduced the contract between the claimant and the New York State Thruway Authority, specifications, drawings, monthly statements, estimates, extension agreements, progress reports, etc. After a week’s trial and presentation of evidence, the claimant did not complete the case and an adjournment was taken with the understanding that the court would fix a time and notify counsel when the trial would continue. Up to this adjournment no motions were made by the Assistant Attorney-General against the claim or pertaining to its dismissal.

Upon the resumption of the trial the Assistant Attorney-General had retired from such position, and his associate at the previous session, a Deputy Attorney-General, took over the trial of the matter and before any witnesses were sworn, the Deputy Attorney-General moved to dismiss the claim for the reason that it was filed against the State of New York instead of the New York State Thruway Authority. Claimant’s attorneys immediately made a countermotion which in substance would include the name of the New York State Thruway Authority in the caption or title and whenever necessary in the pleadings. After hearing oral arguments from both sides, the matter was held to give counsel an opportunity to present briefs and take such other steps as might be deemed necessary. The court reserved [491]*491decision on both motions. Other motions were thereafter made to direct an examination of certain officials of the Thruway Authority and denied.

The court later granted the State’s motion to dismiss the claim against the State and denied the claimant’s countermotion to add or substitute the Thruway Authority as defendant, having in mind the following reasons:

(1) The contract is between claimant and the New York State Thruway Authority, and the State has no liability directly connected with it.

(2) The New York State Thruway Authority is an agency of the State, classified as a public authority, but exercising its powers and carrying on its functions in its own entity, with power to sue and be sued like any public corporation, subject to legislative enactment and control. (Easley v. New York State Thruway Auth., 1 N Y 2d 374; Strang v. State of New York, 206 Misc. 734; Glassman v. Glassman, 309 N. Y. 436; Tompkins v. State of New York, 6 A D 2d 977; Matter of Plumbing, Heating, Piping & Air Conditioning Contrs. Assn. v. New York State Thruway Auth., 4 AD 2d 541, motion for leave to appeal denied 5 A D 2d 797.)

(3) Assistance to be rendered by State officers, departments, etc., to the New York State Thruway Authority (Public Authorities Law, § 362, as amd. by L. 1951, ch. 776, eft. April 12, 1951). “ § 362. * * * At the request of the authority, * * * legal services for such authority shall be performed by forces or officers of the department of public works and the department of law ”.

(4) No written advance notice was given to the Thruway Authority. (Public Authorities Law, § 361-b, as added by L. 1954, ch 517, § 9, eft. April 7, 1954.)

The Court of Claims has exclusive jurisdiction in suits against the New York State Thruway Authority (a) for its tortious acts and those of its agents, and (b) for breach of a contract relating to construction, reconstruction, improvement, maintenance or operation, in the same manner and to the extent provided by and subject to the provisions of the Court of Claims Act with respect to claims against the State, and to make awards and render judgments therefor. All awards and judgments arising from such claims shall be paid out of moneys of the Authority. (Public Authorities Law, § 361-b, added by L. 1954, ch. 517, § 9, eft. April 7, 1954.)

The requirements of the Court of Claims Act cannot be waived or excused in a claim against the State. (Undritz v. State of New York, 179 Misc. 467; Buckles v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shimmerlik v. City University of New York
142 Misc. 2d 118 (New York State Court of Claims, 1988)
Bell v. Tri-City Hospital District
196 Cal. App. 3d 438 (California Court of Appeal, 1987)
Doe v. State
86 Misc. 639 (New York State Court of Claims, 1976)
Murphy v. Schuler
74 Misc. 2d 732 (New York Supreme Court, 1973)
Montgomery v. State
69 Misc. 2d 127 (New York Supreme Court, 1972)
Norton v. State
53 Misc. 2d 495 (New York State Court of Claims, 1967)
Tomlinson Construction Co. v. State
30 Misc. 2d 1010 (New York State Court of Claims, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
26 Misc. 2d 488, 211 N.Y.S.2d 564, 1961 N.Y. Misc. LEXIS 3364, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tomlinson-construction-co-v-state-nyclaimsct-1961.