National Contracting Co. v. Hudson River Water Power Co.

84 N.E. 865, 192 N.Y. 209, 1908 N.Y. LEXIS 873
CourtNew York Court of Appeals
DecidedMay 19, 1908
StatusPublished
Cited by65 cases

This text of 84 N.E. 865 (National Contracting Co. v. Hudson River Water Power Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Contracting Co. v. Hudson River Water Power Co., 84 N.E. 865, 192 N.Y. 209, 1908 N.Y. LEXIS 873 (N.Y. 1908).

Opinion

Cullen, Ch. J.

On May 18th, 1900, the plaintiff and defendant entered into a written contract whereby the plaintiff, in consideration of payments to be made by the defendant, agreed to construct a dam across the Hudson river at a point near Palmer’s Falls, in the county of Saratoga. Prior to the execution of the contract the defendant had solicited proposals for the work from various contractors, submitting to such parties the specifications of the proposed structure and *214 a letter explanatory of its general design. The letter stated that the dam would consist “ of an earth-dam with a central masonry core, of a masonry over-fall dam and of a masonry intake dam.” The specifications contained this provision: “2. General description. The dam is to be built partly of masonry and partly of earth approximately on the lines shown ; but if the character of the materials or circumstances arise which render it advisable to change the location of the dam or to change the plans of the dam, the Hudson Biver Water Power Company expressly reserves the right to do so without payment of damages to the contractor, but all work actually completed will be paid for as per prices bid for the whole work.” The plaintiff bid on the work and thereupon negotiations proceeded between the parties, which finally culminated in the execution of the contract, the subject of this action. That contract and the specifications which were incorporated in it differed materially from those which had been originally prepared and furnished to the various contractors. In the general description already quoted there were erased the words “partly” preceding the word “masonry,” and the subsequent words “and'partly of earth,” by drawing lines in red ink through the printed form of contract, so that this clause read “ the dam is to be built of masonry.” At many other points in the specifications, by similar means, erasure was made of all matters or provisions referring or applicable to a masonry core dam. The contract provided for the payment by the defendant not of a gross sum, but of unit prices for the different kinds of work that might be performed in building the structure. Payments were to be made monthly for eighty-five per cent of the value of the work done as estimated by the .engineer, full payment to be made on the completion of the work. In the executed contract the provision for payment to the contractor was modified by a further clause which authorized the defendant to make such payment, instead of in money, in the defendant’s first mortgage five per cent bonds at ninety per cent and accrued interest. Shortly after the execution of the contract the plaintiff commenced the prosecution of the work and *215 continued the same until August, 1900. About that time excavations in the river had disclosed that the bed rock on which the river section of the dam was to rest lay at a much greater depth than had been anticipated, which would result in great increase in the cost of the structure. In view of this increased expense the defendant commenced the consideration of a modification of the character of the dam so as to substitute for a dam of masonry a'dam of earth with a masonry core, and, at least for a time, it determined to make the substitution. The defendant’s engineer furnished to the plaintiff such plans and detailed drawings as were necessary at the time on the new or altered character of the structure, and required the plaintiff to prosecute the work in accordance therewith. Against this alteration the plaintiff protested. The defendant replied, asserting its right under the terms of the contract to so modify the plans of the structure. The plaintiff retorted that the action of the defendant was a breach of the contract, and refused to accede to the defendant’s demand. Each party insisted on the correctness of the position it had assumed. The details of the controversy it is unnecessary to relate. It is sufficient to say that on the 23rd of November, 1900, the plaintiff, after having given previous notice to that effect, withdrew its workmen and plants and ceased the prosecution of the work. Thereafter it brought this action to recover the balance claimed to be due to it for work done under the contract, and for loss of profit as damages for the breach of the contract. The answer of the defendant denied any breach on its part and counterclaimed for damages for the failure and refusal of the plaintiff to carry out the contract. The referee before whom the case was tried rendered judgment dismissing the complaint and awarded the defendant a recovery on its counterclaim. This judgment Avas affirmed by the Appellate Division unanimously, so far as it dismissed the plaintiff’s complaint, and by a divided court as to the defendant’s counterclaim.

The learned referee, Avhile he felt that the disposition of the case was controlled by the decisions of the Appellate Division *216 and of this court (170 N. Y. 439), made on previous appeals in the cause, passed on all the facts in controversy, so that the rights of each party could be fully protected, and in our discussion we shall not go outside of those findings, passing till a a later time the claim that we are concluded by our former decision on a demurrer to one of the defendant’s defenses. It is clear that the important question in this case is the right of the defendant under the terms of the contract to change the structure from a masonry dam to an earth dam with masonry core. We think it had no such right. Under the contract the plaintiff did not become obligated to furnish labor and materials for the prosecution of any work or the construction of any structure the defendant might designate. 'It agreed to furnish such labor and materials as might be necessary for the construction of a particular thing, to wit, a dam. It could not, under the contract, have been required to build an aqueduct, a bridge, a courthouse or a railroad. Its obligation was not only confined to the construction of a dam, but to the construction of a particular kind of dam, to wit, a masonry dam. The provision that the dam was to be of masonry was as essential an element of the identity of the structure as was the provision that it was to be a dam. The circumstances attendant the preparation and execution of the contract clearly establish this. The original specifications, before erasure, contained elaborate provisions applicable, appropriate and necessary for an earth dam with masonry core. Every one of these provisions was erased in the contract executed by the parties. The contract, however, contained this provision: “ E. Alterations. It is further agreed that the Engineer may make alterations in the line, grade, plans, form, position, dimensions, or material of the work herein contemplated, or of any part thereof, either before or after the commencement of construction. If such alterations diminish the quantity of work to be done, they shall not constitute a claim for damages, or for anticipated profits on the work that may be dispensed with; if they increase the amount of work, such increase shall be paid for according to the quantity actually done, and at the *217

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicagoland Chamber of Commerce v. Pappas
880 N.E.2d 1105 (Appellate Court of Illinois, 2007)
N & N Catering Co., Inc. v. City of Chicago
37 F. Supp. 2d 1056 (N.D. Illinois, 1999)
N&N Catering Co. v. City of Chicago
26 F. Supp. 2d 1067 (N.D. Illinois, 1998)
Phoenix Electrical Contracting, Inc. v. Lehr Construction Corp.
219 A.D.2d 467 (Appellate Division of the Supreme Court of New York, 1995)
Ole, Ole, Inc. v. Kozubowski
543 N.E.2d 178 (Appellate Court of Illinois, 1989)
Ross v. Kozubowski
538 N.E.2d 623 (Appellate Court of Illinois, 1989)
Black Knight Restaurant, Inc. v. City of Oak Forest
513 N.E.2d 109 (Appellate Court of Illinois, 1987)
Illinois Municipal League v. Illinois State Labor Relations Board
488 N.E.2d 1040 (Appellate Court of Illinois, 1986)
Scioto Trails Co. v. Ohio Department of Liquor Control
462 N.E.2d 1386 (Ohio Court of Appeals, 1983)
Seals v. City of Chicago
417 N.E.2d 843 (Appellate Court of Illinois, 1981)
Duncan v. Marcin
403 N.E.2d 653 (Appellate Court of Illinois, 1980)
Huguley v. Marcin
349 N.E.2d 564 (Appellate Court of Illinois, 1976)
People v. Downes
212 N.W.2d 314 (Michigan Court of Appeals, 1973)
Alfred Vail Mutual Ass'n v. Borough of New Shrewsbury
274 A.2d 801 (Supreme Court of New Jersey, 1971)
Griggs v. State
73 So. 2d 382 (Alabama Court of Appeals, 1954)
State Ex Rel. Minot v. Gronna
59 N.W.2d 514 (North Dakota Supreme Court, 1953)
Holloway v. Schott
64 So. 2d 680 (Supreme Court of Florida, 1953)
People of Illinois v. Sullivan
175 F.2d 282 (Seventh Circuit, 1949)
College Inn Food Products Co. v. State
18 Ill. Ct. Cl. 14 (Court of Claims of Illinois, 1948)
Doyle v. King
44 S.E.2d 608 (Supreme Court of South Carolina, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
84 N.E. 865, 192 N.Y. 209, 1908 N.Y. LEXIS 873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-contracting-co-v-hudson-river-water-power-co-ny-1908.