Furton v. City of Menasha

71 F. Supp. 568, 1947 U.S. Dist. LEXIS 2561
CourtDistrict Court, E.D. Wisconsin
DecidedMay 7, 1947
DocketCiv. No. 1130
StatusPublished

This text of 71 F. Supp. 568 (Furton v. City of Menasha) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Furton v. City of Menasha, 71 F. Supp. 568, 1947 U.S. Dist. LEXIS 2561 (E.D. Wis. 1947).

Opinion

STONE, District Judge.

This action was commenced by the plaintiffs, copartners of Menominee, Michigan, against the defendant, a municipal corporation situated in Winnebago County, Wisconsin, to recover the sum of $100,994.71. that plaintiffs allege they suffered by reason of misrepresentations by the defendant contained in the plans and specifications of their contract with defendant, entered into on December 17, 1941.

Plaintiffs are contractors and they agreed by the terms of their contract to construct' according to the plans and specifications, a pre-settling basin for defendant to be used in connection with the operation of its water utility in the City of Menasha.

The work required of plaintiffs by the terms of the contract included the excavation, to a depth of approximately 7 feet of an area to be used for said basin, three-fourths of which was surrounded by water and the dimensions of which were as follows : 724%feet long on one side; 732 feet on another side next to an outlet creek leading into Lake Winnebago; ISO feet on the side next to the lake shore; and 1,000 feet on the remaining side next to a dredged channel.

Plaintiffs claim is for alleged extra and additional services rendered and expenses incurred by them under circumstances which they contend made defendant liable therefor.

Their claim is comprised in part of lien claims amounting to $23,886.22, and one for rental of machinery and equipment in the sum of $63,414.22.

The misrepresentation is alleged to appear in the plans and specifications as to the depth at which a solid layer or floor of rock underneath the area to be excavated would be found at a uniform level, which would permit plaintiffs to use their heavy machinery, trucks and equipment thereon in the excavation of the basin.

[570]*570Plaintiffs claim they made and submitted their bid to the defendant on the assumption that there was such a solid foundation or layer of rock at the elevation designated on the plans as “rock” ; that .after they had performed a substantial part of the contract they discovered that the rock base did not exist and that by reason of is non-existence they were compelled to use heavier and additional equipment, and to erect portable mats of blocks and timber to support their machinery and trucks. They also contend that defendant’s engineer ordered them to perform the additional work and to incur (he additional expense.

The defendant denies that the contract contained any such warranty or representation, or that its engineer was authorized to or did authorize plaintiffs to perform the alleged additional work or incur the alleged additional expense. It asserts that it paid plaintiffs all that was due them on the contract except the sum of $14,603.57 which they retained. That $10,103.37 of said sum represented the 15% retained by it pursuant to the contract which it now claims as an offset against the cost of completing the project and the payment of the lien claims.

The project was not completed prior to the commencement of this action and the defendant has had no use of the settling basin.

Most of plaintiffs’ machinery and equipment on this project was used and second hand when they purchased it. The rental charge entered on their books in the sum of $63,414.22, and made a part of their present claim against defendant, was not a cash outlay or expenditure. It was shown as a bookkeeping entry in which plaintiffs charged themselves for rental of machinery and equipment owned by them and used by them on this project, which rental charge in some instances exceeded many times the original cost of the tractors or other machinery.

Plaintiffs make no claim that the area to be excavated was enlarged or changed in any manner by supplemental plans or specifications, or that they were required to remove a larger quantity or different quality of material than originally contemplated by the contract. They do assert that there was some quicksand removed. The proof discloses that the amount of quicksand so removed was negligible and of no significance.

Plaintiffs contend that when they discovered the non-existence of the rock base, the defendant’s engineer, orally, but not in writing, directed them to continue the performance of the work. This is denied by the engineer, and the conduct of the plaintiffs gives support to the engineer’s testimony thar he at no time áuthorized them to perform the alleged extra work in writing or otherwise.

It appears from the evidence that plaintiffs discovered the absence of the “rock foundation” on March 6, 1942, but failed to notify the defendant of their alleged claim until 11 months thereafter, although from the very outset and throughout the period of, the operation on this project, they were in financial difficulties and badly in need of additional funds to carry on the work. They never included in their monthly estimates thereafter, any claim for additional or extra compensation for excavation of the basin. The contract provided that all claims for extra work must be submitted not later than the 5th day of the next month. Their claim was not filed until April 9, 1943, which was 13 months after they discovered the alleged misrepresentation.

Each monthly report showed the amount of work in each category during the preceding month and the amount approved for payment was based upon the work performed during the preceding month as shown by the estimates approved by the contractor. Plaintiffs submitted to defendant 13 monthly estimates without mention or reference in any of them to the claim now in suit. The estimates stated the full and complete claim of plaintiffs up to the date of each statement. Apparently at no time during that period did plaintiffs entertain any thought that it had any such claim against the defendant.

From October 1, 1942, to January 1, 1943, the estimates show $1,556, $1,300 of which was for excavation, $256 for other work under the contract, and nothing for extras. It then showed the cost of excavation to [571]*571that date as $27,898.19. It appears to this court that the claim in issue is frivolous and without merit. It was not presented to defendant until after the Commission had declared plaintiffs in default on their contract. Its filing was undoubtedly due to that “sober second afterthought”. There were seven extras approved and paid for by defendant. All were based upon written communications from defendant’s engineer authorizing the extra work, except as to two minor items.

The engineer’s authority was limited by the terms of the contract. He could authorize additional work only in writing. There is no evidence of any written order made by the defendant or its engineer authorizing plaintiffs to do this alleged additional work.

There is no evidence or proof of any waiver by defendant of the necessity for a written order from the engineer for extra work as a condition precedent to the payment for additional services.

The contract was signed December 7, 1941. Plaintiffs undoubtedly intended to promptly commence the excavation work so as to take advantage of the winter weather. Unfortunately they were unable to start until January 21, 1942, when they obtained the performance bond. They lost a month and a half of weather conditions valuable and precious to a contractor in excavating this type of soil.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hollerbach v. United States
233 U.S. 165 (Supreme Court, 1914)
Christie v. United States
237 U.S. 234 (Supreme Court, 1915)
United States v. Atlantic Dredging Co.
253 U.S. 1 (Supreme Court, 1920)
MacArthur Brothers Co. v. United States
258 U.S. 6 (Supreme Court, 1922)
Pitt Const. Co. v. City of Alliance, Ohio
12 F.2d 28 (Sixth Circuit, 1926)
Maney v. Oklahoma City
1931 OK 250 (Supreme Court of Oklahoma, 1931)
City of Richmond v. I. J. Smith & Co.
89 S.E. 123 (Supreme Court of Virginia, 1916)
City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)
McDonald v. State
235 N.W. 1 (Wisconsin Supreme Court, 1931)
Wussow v. State
267 N.W. 56 (Wisconsin Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
71 F. Supp. 568, 1947 U.S. Dist. LEXIS 2561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/furton-v-city-of-menasha-wied-1947.