Maney v. Oklahoma City

1931 OK 250, 300 P. 642, 150 Okla. 77, 76 A.L.R. 258, 1931 Okla. LEXIS 287
CourtSupreme Court of Oklahoma
DecidedMay 12, 1931
Docket19224
StatusPublished
Cited by19 cases

This text of 1931 OK 250 (Maney v. Oklahoma City) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maney v. Oklahoma City, 1931 OK 250, 300 P. 642, 150 Okla. 77, 76 A.L.R. 258, 1931 Okla. LEXIS 287 (Okla. 1931).

Opinion

CLARK, V. C. J.

This action was commenced in the district court of Oklahoma county by plaintiffs in error against defendants in error to recover a mon.ey judgment. The controversy grew out of a contract entered into between plaintiffs and defendant wherein plaintiffs were to excavate a bypass for the defendant city. For convenience the parties will be referred to as they appeared in the trial court.

Plaintiffs in their petition alleged;

That the bid was based upon maps, drawings, plans, and specifications and sounding sheet and profile, showing the nature and character of the work to be done, and particularly the character of the material to be excavated, which had been prepared and made by the defendant city. That the maps, drawings, plans, specifications, and the sounding sheet (which was made from bor-ings made by defendant city) disclosed the material to be excavated consisted entirely of earth and dirt except a small and negligible quantity of rock at one particular point; thát the said maps, drawings,' plans, specifications, and sounding sheet, together with the representations made by the city engineer, were relied upon by the plaintiffs in the preparation of their bids and in entering into said 'contract. That plaintiffs did not have sufficient length of time between the advertisement for bids and the letting of the. contract to make their own soundings, but relied upon the representations of the defendant city as to the character of material to be encountered. That in the progress of the. work it developed that instead of the material to be excavated being earth and dirt excepting a negligible quantity of rock, a very large portion thereof was rock, to wit, about 74,000 cubic yards. That the defendant city, its engineers, and coriimissioners were immediately notified, who viewed the rock, and directed plaintiffs to proceed with said work under their contract, and all formal claims and notices prescribed in the specifications were waived by said city engineer and city commissioner's. That plaintiffs completed- their work . td' the satisfac *78 tion and written acceptance of the defendant city. That the contract price for earth and dirt excavation was wholly inadequate for excavation and removal of said solid rock; and that the fair and reasonable cost and expense of excavating and removing said rock was $1.40 per cubic yard. And plaintiff prayed for judgment against the city for $1.40 per cubic yard for the excavation and removal of said rock, and for such other and further relief as under the law and facts the plaintiff was entitled.

Defendant city filed its answer, which consisted of a general denial of all material allegations of plaintiffs’ petition except what were specifically admitted, as follows;

“-1. Admitted the status of the parties.
“2l Admitted the execution of the contract, and that it undertook to construct an improved water system.
“3. Admitted it 'was necessary to construct a by-pass.
“4 Admitted it caused maps and drawings to be made and showing that borings and soundings had been made by it to ascertain the character of the material to be excavated.
“5. Admitted that such borings and soundings disclosed that the material to be excavated consisted of a quantity of earth and dirt with a small quantity of rock.
“6. Admitted plaintiffs completed to the satisfaction and written acceptance of the city and its engineer the work.”

The cause was tried to a jury and resulted in a verdict for the defendant. Motion for new trial was filed and overruled. Plaintiffs brought the cause here for review.

The. first proposition presented by the plaintiffs is as follows:

“Under the undisputed evidence the plaintiffs were entitled to a directed verdict holding the city liable for the rock excavation in. question. The only question to be submitted to the'jury was the reasonable cost thereof.”

At the close of the trial the plaintiffs requested the following instruction:

“Tou are hereby instructed that the plaintiffs and defendant have stipulated that the actual amount of rock excavated by the plaintiffs for which they have not been paid amounts to 60,000 cubic yards. In this connection you are further instructed that the only question for you to determine is the reasonable value of such excavation at the time the same was performed, less the sum of 10c per cubic yard”

—which was refused by the court and exceptions allowed.

The undisputed facts in the case show:

That the defendant in error, in contemplation of construction of its improvements to its water supply system, had maps, plans, profiles, and specifications prepared by its engineers, as well as soundings made to ascertain the character of material that was supposed to be in the by-pass, and that said soundings showed very small amount of rock not exceeding 407 cubic yards, which would be a negligible quantity of rock, taking into, consideration the entire project. The soundings were transferred onto a blue print and kept in the commissioner’s and engineer’s office. The prospective bidders secured copies of the. plans and specifications, drawings and profiles from the city clerk’s office, and also saw and used a sounding sheet and profile showing soundings which were in the city engineer’s office and showed the character of the material to be encountered in the by-pass; that said sounding sheet showed only negligible or very small quantity of rock. Plaintiffs used the plans, drawings, specifications, profiles prepared by the defendant city, together with the sounding-sheet, and the information furnished by the city engineer in the preparation and submission of their bid. Plaintiffs were shown the sounding sheet by the. said city engineer and were advised by the city engineer there-was a very negligible quantity of rock. That’ the bid and contract were made and entered into for the excavation of earth and dirt and not solid rock, except the very small quantity as shown on the sounding sheet. The term “earth” and expression “earth excavation,” as used in such contracts, mean earth only, and that there was no rock or anything else except earth. The bidders did not have sufficient length of time to make their independent soundings, and had to rely on the maps, drawings, profiles, and sounding sheet and the. information furnished by the city ' engineer as to the character of the material to be encountered. That plaintiffs were the successful bidders and entered into the contract for the construction of section “B” of the project, being the “by-pass,” at the price of 16e per cubic yard, subject to the provisions in the contract and specifications. That plaintiffs fully performed the contract, and that the work was completed and accepted by the defendant city and plaintiffs received compensation therefor at the contract price of ICC per cubic yard for earth excavation, but did not receive compensation for the extra work of rock excavation.

It was stipulated at the trial below that the plaintiffs excavated 60,000 cubic yards of rock from said by-pass. That after the work had progressed for sometime a change *79 was made in. tlie -lin'e. of tlie by-páss from that originally staked out.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)
Peter Salvucci & Sons, Inc. v. State
268 A.2d 899 (Supreme Court of New Hampshire, 1970)
Reed v. Lock
1965 OK 2 (Supreme Court of Oklahoma, 1965)
Clark v. City of Humansville, Missouri
348 S.W.2d 369 (Missouri Court of Appeals, 1961)
Gardner v. City of Englewood
282 P.2d 1084 (Supreme Court of Colorado, 1955)
Furton v. City of Menasha
71 F. Supp. 568 (E.D. Wisconsin, 1947)
Gogo v. Los Angeles County Flood Control District
114 P.2d 65 (California Court of Appeal, 1941)
Scherrer v. State Highway Commission
80 P.2d 1105 (Supreme Court of Kansas, 1938)
Powell v. State
118 S.W.2d 960 (Court of Appeals of Texas, 1938)
City of Lawton v. Sherman MacHine & Iron Works
1938 OK 175 (Supreme Court of Oklahoma, 1938)
Leonard v. Town of Waynesboro
193 S.E. 503 (Supreme Court of Virginia, 1937)
State Ex Rel. Woods v. Cole
1936 OK 565 (Supreme Court of Oklahoma, 1936)
Wussow v. State
267 N.W. 56 (Wisconsin Supreme Court, 1936)
Davis v. Commissioners of Sewerage
13 F. Supp. 672 (W.D. Kentucky, 1936)
Hale v. Warren
1935 OK 1040 (Supreme Court of Oklahoma, 1935)
City of Dallas v. Shortall
87 S.W.2d 844 (Court of Appeals of Texas, 1935)
City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
1931 OK 250, 300 P. 642, 150 Okla. 77, 76 A.L.R. 258, 1931 Okla. LEXIS 287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maney-v-oklahoma-city-okla-1931.