Oklahoma City v. Derr

1928 OK 159, 235 P. 218, 109 Okla. 192, 1925 Okla. LEXIS 708
CourtSupreme Court of Oklahoma
DecidedFebruary 24, 1925
Docket15238
StatusPublished
Cited by18 cases

This text of 1928 OK 159 (Oklahoma City v. Derr) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oklahoma City v. Derr, 1928 OK 159, 235 P. 218, 109 Okla. 192, 1925 Okla. LEXIS 708 (Okla. 1925).

Opinion

Opinion by

STEPHENSON, C.

The municipality of Oklahoma City entered into a contract with: Chas. T. Derr, in the year 1906, for the construction of a sewer system. It is claimed by the contractor that the city failed to pay him in accordance with his contracts. The plaintiff in due time commenced his action for the recovery of the indebtedness. The trial of the cause resulted' in judgment in favor of the plaintiff. The defendant has appealed the cause to this court and assigns several of the proceedings had in the trial of the cause as error for reversal here. The main contentions of the defendant, are: First, that the total claims of the plaintiff for the construction of the sewer system exceeded the estimate ; second, that the contract provided that changes in the contract must be made in writing in order to bind the city; third, that the changes and additional work for which recovery is sought in this case were not authorized by the city in writing.

There are several other errors assigned, but disposition of the foregoing questions may make their consideration unnecessary in this appeal.

The municipality, in the year 1906, voted its bond issue for about $225,000 to construct a certain sewer system. Plans, specifications, and estimate of the cost were prepared, filed, and approved by the city. The contract with the plaintiff appears to have been duly and regularly made. The original contracts of the plaintiff and other contractors were within the estimate and within the bond issue. Certain contingencies arose in the course of the work and other oral contracts were made between this plaintiff and the defendant, which, added to the original contracts, exceeded the estimate.

The position of the municipality is that the city is not liable for the contracts and items involved in this suit for the reason that the items plus the original contract price exceeded the estimate and bond issue. The circumstances and conditions which gave rise to the subsequent contracts and claims are: First, the city after it had prepared its plans and specifications, made a fill over a part of the line, which necessitated a greater depth for excavation than was shown by the plans. Second, the city decided after the preparation of the plans and the making of the contract, that it desired to change the location of the sewer line to another location. The new location necessitated extra excavation and removal of a considerable quantity of stone which was not estimated in the first instance. Third, the plaintiff in the course of the excavation of the ditch, at a depth of about 15 feet, severed a large water line with a steam shovel, that was not shown by the plans and specifications. The flow of water in the ditch imnaired the walls and caused them to cave. The water line which afforded fire protection for the portion of the city located north of Main street was threatened by the caving walls. It became necessary to go to considerable work and expense to remedy the threatened break of the water main. Fourth, the plaintiff in the course of his work came in contact with another water line which was severed by the steam shovel in excavating the earth. The plans and specifications did not show the location of this particular water line. Fifth, the municipality in the course of the excavation of the ditdb, in a certain portion of the city desired to change its course which entailed extra expense and work. Sixth, the remainder of the items involved in this appeal arose by reason of similar conditions.

The city placed its city engineer in charge of the supervision and direction of the work being done by the plaintiff. The city council ¡had also appointed a sewer committee to act in connection with the city engineer in the supervision and direction of the work.

The plaintiff called the engineer and the sewer committee and members of the council to view each situation at the time it arose, and sought their directions in meeting *194 the unexpected problems. The proof shows that the plaintiff performed the work, which gave rise to the items involved iu this appeal, under agreement made with the sewer committee and the engineer, with the knowledge of the members of the council. The work was completed and the system accepted by the city. No complaint is made by the city as to the manner of doing the work and its completion. There is no fraud alleged upon'the part of the plaintiff or in conjunction with the officers of the municipality.

The changes in the plans and specifications and the additional contracts were not reduced to writing. The.city contends that section 9 of the original contract denies the right of the plaintiff to recover for the several items involved in this action upon this ground. The section is in the following-language :

“No change shall be made in said contract or the plans and specifications for any section of the work done under this contract without the written consent of the said city or its engineer.”

It is clear that this provision was incorporated in the contract for the benefit of the city. It was sufficient to protect the city against any wrongful or fraudulent claims, which might be made, by the plaintiff in the course of the construction of the work. Tt was the duty of the city to cause any changes in the plans and specifications to be reduced to writing, and served on the contractor. The observance of this practice upon the part of the city would have avoided any controversy as to its authority for any particular change or controversy as to the compensation to be allowed for the work, but we may add that this suit does not rest upon a dispute between the parties as to whether the city authorized or directed the changes, or entered into the new contracts.

It is a well established rule of law that provisions incorporated into a written contract for the benefit of one of the parties may be asserted or waived- by the latter.

The municipal officers in making the contract and in directing the completion of the work were exercising powers delegated to them by the people of -the city. The status of principal and agent existed between the people of the city and its officers in relation to this subject-matter. It may be that it would be for the best interest of municipalities, in many instances, if the agents and officers of the city would enforce that portion of the contract regarding changes in the plans and specifications requiring the same to be reduced to writing. But is it the duty of the contractor to urge and insist upon the officers performing the obligation they may owe to the principal? And should the contractor refuse to carry out his contract and undertake to hold the city liable for a breach, because the agents and officers did not discharge their obligations owing to the principal? We think the answer is in the negative, if the contractor is free from fraud and wrong in the premises. The agents and officers of the city are elected by .the people and are answerable back to them for the faithful performance of their delegated official duties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)
Miller v. City of Broken Arrow
660 F.2d 450 (Tenth Circuit, 1981)
Flour Mills of America, Inc. v. American Steel Building Co.
449 P.2d 861 (Supreme Court of Oklahoma, 1969)
Puget Sound National Bank v. C. B. Lauch Const. Co.
245 P.2d 800 (Idaho Supreme Court, 1952)
Woods v. Amulco Products, Inc.
1951 OK 190 (Supreme Court of Oklahoma, 1951)
State Highway Commission v. Green-Boots Const. Co.
1947 OK 221 (Supreme Court of Oklahoma, 1947)
City of Lawton v. Sherman MacHine & Iron Works
1938 OK 175 (Supreme Court of Oklahoma, 1938)
Excise Board of Le Flore County v. Kansas City Southern Ry. Co.
1935 OK 688 (Supreme Court of Oklahoma, 1935)
City of Healdton v. Blackburn
1934 OK 573 (Supreme Court of Oklahoma, 1934)
State v. Commercial Casualty Insurance
248 N.W. 807 (Nebraska Supreme Court, 1933)
Severns Paving Co. v. Oklahoma City
1932 OK 307 (Supreme Court of Oklahoma, 1932)
Maney v. Oklahoma City
1931 OK 250 (Supreme Court of Oklahoma, 1931)
Peter Mintener Lumber Co. v. School District No. 56
277 P. 9 (Montana Supreme Court, 1929)
Boardman Co. v. Board of Com'rs, Ellis Co.
1929 OK 10 (Supreme Court of Oklahoma, 1929)
Board of Ed. of School Dist. No. 47 1/2 v. Jacobs
1928 OK 677 (Supreme Court of Oklahoma, 1928)
City of Pawhuska v. Dahlstrom
243 P. 248 (Supreme Court of Oklahoma, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
1928 OK 159, 235 P. 218, 109 Okla. 192, 1925 Okla. LEXIS 708, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oklahoma-city-v-derr-okla-1925.