City of Elgin v. Joslyn

26 N.E. 1090, 136 Ill. 525
CourtIllinois Supreme Court
DecidedMarch 30, 1891
StatusPublished
Cited by45 cases

This text of 26 N.E. 1090 (City of Elgin v. Joslyn) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Elgin v. Joslyn, 26 N.E. 1090, 136 Ill. 525 (Ill. 1891).

Opinion

Mr. Justice Magruder

delivered the opinion of the Court:

This is an action of assumpsit, brought by appellee against appellant in the Circuit Court of Kane County to recover for work and material furnished by appellee in the construction of the Elgin Water Works. The declaration contains the common counts only. There was a written contract between the parties, but the claim as made is for extras, and extra work and material, alleged to have been done and furnished on account of changes required to be made by the City. The verdict was for $2400.92, but plaintiff below remitted $400.92, and judgment was finally entered for $2000.00.

The first error complained of is the alleged contradiction, which is said to exist between the sixth instruction given for the plaintiff, and the first instruction given for the defendant. Plaintiff’s sixth instruction lays down the rule, that a contractor who bids for work is bound only by the specifications which are shown to him at the time he bids, and upon which his bid is based, and not by other specifications not then shown to him, and of which he was then ignorant so that he did not and could not consider them in making the estimates for his bid. This accords with the law as laid down by this Court in Sexton v. Chicago, 107 Ill. 323, and Kirk v. Wolf Man. Co. 118 id. 567. Plaintiff’s sixth instruction is qualified to a certain extent, but not contradicted by defendant’s, first instruction. The latter merely told the jury that if, when plaintiff executed the contract, his attention was called to “general” specifications which had not been shown to him when he made his bid, and if, at the time of the execution of the contract, he examined such “general” specifications and agreed to them, then, in that case, they became a part of his contract, and he would be bound by them. It was left to the jury to say, whether or not plaintiff was informed of any other; than the “special” specifications when he made his bid, and, also, whether or not he was informed of and assented to the “general” specifications when he afterwards signed the contract. Under the two instructions, the jury were merely required to determine whether or not the right of the plaintiff to complain of the City’s silence as to the “general” specifications when he made his bid, was afterwards waived by any knowledge of and assent to such “general” specifications on his part, when he executed the contract.

The contract in the case required the plaintiff to do certain “excavation and mason work.” The court admitted the oral evidence .of mechanics, and persons skilled in mason work, for the purpose of showing whether “mason work” included the laying of inlet, suction and drain pipes. The admission of this evidence is objected to, but we do not think that it was improper. The term “mason work” has not such a known legal meaning as would necessarily include the laying of the pipes in question. Where general words, in particular trades and branches of business, are used in a new, peculiar or technical sense, those conversant with such use of them therein may explain their meaning. Where terms of art or science, or technical phrases and local words, are used in a contract, they may be explained by parol testimony. (1 Greenl. on Ev. sec. 280; Brown v. Brown, 8 Mete. 576; Myers v. Walker, 24 Ill. 133.)

We see no necessary conflict between plaintiff’s seventh and defendant’s fourth instructions. Upon the theory of the former, plaintiff would not be required by his contract to lay said pipes, if the laying of them was not a part of the “mason work.” Upon the theory of the latter, he would be bound to lay them,' if there was a misunderstanding between him and "the city as to the meaning of “mason work,” and if they agreed to leave it to the engineer to decide what the term meant, and to abide by his decision, and if he decided that mason work included the laying of the pipes. The instructions left all. these matters of fact to the jury, and they found them against-the defendant.

Appellant objects to the fifth instruction given for the plaintiff, upon the alleged ground that it assumes that plaintiff was discharged by the city. The first clause of the instruction does contain the assumption complained of, and, if it stood alone, would require a reversal; but, after a careful examination of the other clauses of the fifth instruction, and of all the instructions given on both sides in the case, we are satisfied-' that the jury could not have been misled by this error to the prejudice of the defendant.

The undisputed evidence on both sides shows, that, at a certain point, the city took charge of the work and finished it. The fifth instruction taken as a whole, and the second and seventh instructions given for the plaintiff, fairly left to the determination of the jury the question of fact, whether or not-’ the defendant interfered with the plaintiff and prevented him-from finishing the work, and dismissed him and rescinded his-contract without sufficient cause. A slight or partial neglect' to observe some of the terms or conditions of a contract will' mot justify a rescission or abandonment. (Weintz v. Hafner, 78 Ill. 27; Sanger v. Chicago, 65 id. 506.) Where a party performs his contract in part and is prevented by the other party from finishing it, he will have the legal right to abandon or treat it as rescinded, and sue and recover for the work and materials furnished by him. (Guerdon v. Corbett, 87 Ill. 272; Bonnet v. Glattfeldt, 120 id. 166.)

On the other hand, the second, fifth and sixth instructions given for the defendant, fairly left it to the jury to say, whether or not the plaintiff voluntarily abandoned the work and refused to finish it, and thereby gave the defendant the right declare the contract forfeited and to proceed with its completion. The fact that the plaintiff left the work before it was finished being admitted, the instructions on both sides so often and so fully presented to the minds of the jury the question, whether such fact was due to a voluntary or to an enforced' abandonment, that they could not have regarded the discharge: of the plaintiff as a matter of course, or as a matter taken for granted.

The first instruction given for the plaintiff is complained of, because it authorized the jury to allow the plaintiff the amount of such items of extra work and materials set forth in his bill of particulars, “as they believe the plaintiff is entitled to from the evidence.” It is said that this language .compelled the jury to allow what the testimony might show .the extras to be worth independently of the contract, whereas the contract, provided that extra work should be paid for according to the schedule of prices bid, and that the city engineer was to determine what was extra work and the price of it. •

Extra work and materials of the same character as the work and materials named in the contract, are to be paid for according to the schedule of prices fixed by the contract. But where the extra work and materials are of a different character from those specified in the contract, the rates named in the contract will not apply, and the party performing will be entitled to recover according to the value as fixed by the evidence. (Chi. & Great East. R’y Co. v. Vosburgh, 45 Ill. 311; Western Union R. R. Co. v. Smith, 75 id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Standhardt v. Flintkote Co.
508 P.2d 1283 (New Mexico Supreme Court, 1973)
Standhardt v. Flintkote Company
508 P.2d 1283 (New Mexico Supreme Court, 1973)
Strom v. Lipschultz
282 N.E.2d 257 (Appellate Court of Illinois, 1972)
Worley Bros. v. Marus Marble & Tile Co.
161 S.E.2d 796 (Supreme Court of Virginia, 1968)
Watson Lumber Co. v. Guennewig
226 N.E.2d 270 (Appellate Court of Illinois, 1967)
Staley v. New
250 P.2d 893 (New Mexico Supreme Court, 1952)
Galion Iron Works & Manufacturing Co. v. City of Georgetown
54 N.E.2d 601 (Appellate Court of Illinois, 1944)
Town of Milford v. O'Neil Bros., Inc.
8 Conn. Super. Ct. 403 (Connecticut Superior Court, 1940)
Ambursen Dam Co. v. United States
86 Ct. Cl. 478 (Court of Claims, 1938)
Clements v. Second National Bank
266 Ill. App. 225 (Appellate Court of Illinois, 1932)
Meacham v. Dioguardi
8 P.2d 293 (Washington Supreme Court, 1932)
Salomon-Waterton Co. v. Union Asbestos & Rubber Co.
263 Ill. App. 583 (Appellate Court of Illinois, 1931)
B. F. & C. M. Davis Co. v. W. E. Callaghan Const. Co.
298 S.W. 273 (Texas Commission of Appeals, 1927)
Drainage Dist. No. 1 v. Rude
21 F.2d 257 (Eighth Circuit, 1927)
Goetz v. Continental Casualty Co.
245 Ill. App. 350 (Appellate Court of Illinois, 1925)
Oklahoma City v. Derr
1928 OK 159 (Supreme Court of Oklahoma, 1925)
Adam Groth & Co. v. Goss & Guise
232 Ill. App. 450 (Appellate Court of Illinois, 1924)
State ex rel. Ottesen v. Clausen
223 P. 591 (Washington Supreme Court, 1924)
Ippolito v. Borough of Ridgefield
109 A. 337 (Supreme Court of New Jersey, 1920)
Conaway v. Pepper
108 A. 676 (Superior Court of Delaware, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
26 N.E. 1090, 136 Ill. 525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-elgin-v-joslyn-ill-1891.