Worley Bros. v. Marus Marble & Tile Co.

161 S.E.2d 796, 209 Va. 136, 1968 Va. LEXIS 206
CourtSupreme Court of Virginia
DecidedJune 10, 1968
DocketRecord 6679
StatusPublished
Cited by4 cases

This text of 161 S.E.2d 796 (Worley Bros. v. Marus Marble & Tile Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Worley Bros. v. Marus Marble & Tile Co., 161 S.E.2d 796, 209 Va. 136, 1968 Va. LEXIS 206 (Va. 1968).

Opinion

Harrison, J.,

delivered the opinion of the court.

Marus Marble and Tile Company, Inc. (hereinafter referred to as Marus), the plaintiff, filed a motion for judgment against Worley Brothers Company, Inc. (hereinafter referred to as Worley), the defendant, seeking to recover the sum of $14,725.75. The trial court, sitting without a jury, entered final judgment in favor of the plaintiff for the full amount of its claim and the defendant was granted this writ of error.

In 1962, Worley, as general contractor, entered into a contract with the City of Richmond for the construction of jail facilities. Thereafter, Worley subcontracted with Marus, a the contractor, to perform the tile work in accordance with plans and specifications (hereinafter referred to as specifications), dated July 2, 1962, prepared by the architects on the job. Our inquiry is limited to Section 20 of the specifications which concerns the installation of the tile. It provides in part as follows:

“Set quarry tile in accordance with Specification No. 3 of American Standard Specification A108-1958, except at vertical joints which are to be filled with black Furnane instead of with pointing mortar.” (Italics supplied.)

Under date of August 7, 1962, the architects issued their Addendum No. 1 to the original specifications wherein certain changes and additions were made. Included in this addendum is the following:

“Section No. 20 — Ceramic and Quarry Tile Under ‘Setting, Grouting and Cleaning,’ revise first sentence of second paragraph to read:
“Set in accordance with Specification No. 3 of the American Standard Specification A108-1958, except fill all joints within the quarry tile with black Furnane instead of with ‘pointing mortar’.” (Italics supplied.)

A bid was submitted to Worley by Marus for the installation of *138 the terrazzo and tile as provided by the specifications. Mr. Marus testified he received from Worley only the original specifications, dated July 2, 1962, and that at no time prior to his bid, and until after the partial performance of his contract, did he receive or have any knowledge of Addendum No. 1. The controversy swirls about this addendum.

An agreement was negotiated and reduced to writing on December 6, 1962, whereby Worley accepted a proposal by Marus to furnish and install, for $78,000, ceramic and quarry tile in accordance with Section 20 of the project specifications as prepared by the architects — and also the terrazzo work, which is not involved here.

Marus began the performance of its contract and by December 5, 1963, the tile floor in the dining area of the jail was estimated at from 75% to 90% laid. On that date, Miles Cary Johnston, Jr., one of the architects, noted that Lumnite was being used to fill or grout the joints instead of black Furnane joint compound. The architect called this to the attention of Worley and Joseph F. Still, a foreman for Marus. His notes show that he then advised Worley that “ ‘. . . all joints would have to be raked out and then filled with Furnane’ ”.

Still told the architect that in using Lumnite he was using the proper material as his specifications did not call for the use of black Furnane. Upon being shown the Addendum No. 1 to the specifications, which were on file in an office at the construction site, Still advised the architect and Worley that “. . . I don’t have that addenda”. Upon being advised that his company did have it, he responded: “. . . I don’t think my company does. If they did, they certainly would not try to be using Lumnite instead of black Furnane”. Still reported this development to Mr. Marus who told him to stop all work on the project.

The testimony of Mr. Marus was that Worley never sent him Addendum No. 1, and that the bid of his company was based upon the specifications as originally prepared by the architects and furnished him by Worley. This position he reiterated repeatedly in the correspondence that ensued between him and Worley.

Mr. Worley testified as to the diligence that he, as a general contractor, customarily used to assure that all specifications furnished subcontractors were complete with addenda. He was positive that he followed this procedure on the city jail job, and in connection with the specifications furnished Marus, but could not testify that Marus received the addendum.

*139 Mr. Worley admitted that his first knowledge of any difficulty in connection with the use of Lumnite instead of Furnane came when Johnston made his inspection and inquired as to the material being used. He said that, in his opinion, he, Still and Johnston, all gained knowledge of the error at the same time.

Afterwards numerous conferences were had and correspondence exchanged, exploring the possibility of having the city accept the work that had been performed, i.e. the quarry tile installed with Lumnite instead of black Furnane, and with a reduction in cost to the city by reason of the installation of a less costly material. Worley referred to the mistake as “an honest mistake”.

We observe that the specifications provided for the installation of quarry tile,, factory waxed, of a certain size, to be set in Portland cement. Between the tile and the setting bed, the plans provided for a layer of “neat” cement. Mr. Marus testified that he used Portland cement as directed by the specifications for the setting bed, and used Lumnite, which he called “a high grade Portland cement”, as pointing mortar for the filler or grout, although he could have used Portland cement. Lumnite is a dark gray color and more expensive than the Portland. It is also more resistant to stains, makes a better job and is used because it will not darken if grease is spilled on it.

Black Furnane is described as shiny or jet black and finishes like asphalt. It has two components, a powder and a liquid catalyst. It is regarded as superior and more resistant to stains than ordinary Portland or Lumnite and is much more costly. The architect stated that black Furnane was specified because the city wanted a mortar of superior quality, as did the State Department of Welfare and Institutions which had to approve the plans.

The negotiations between the interested parties looking to the acceptance of Lumnite instead of black Furnane in the tile joints proved fruitless. On April 3, 1964, the architect, in a letter to Worley, advised that these joints would have to be removed and replaced with black Furnane. The architect testified the city could have accepted “. . . something that is not in accordance with the contract. But we said we were not able to recommend it under any conditions. It had to be removed”.

Worley then called upon Marus to correct the condition. Marus, as previously, again denied ever having received the addendum and responsibility for the error. Worley threatened to have a local subcontractor correct the condition and to deduct all costs from money *140 due Marus under its contract. After an exchange of letters, Mr. Marus ultimately agreed to proceed with the removal of the Lumnite cement from the joints and to replace it with black Furnane.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ressa Construction, Inc. v. Jason Dillaman
Court of Appeals of Virginia, 2025
Modern Continental South v. Fairfax County Water Authority
72 Va. Cir. 268 (Fairfax County Circuit Court, 2006)
Chantilly Construction Corp. v. Department of Highways & Transportation
369 S.E.2d 438 (Court of Appeals of Virginia, 1988)
Service Steel Erectors Co. v. SCE, INC.
573 F. Supp. 177 (W.D. Virginia, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
161 S.E.2d 796, 209 Va. 136, 1968 Va. LEXIS 206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/worley-bros-v-marus-marble-tile-co-va-1968.