Ryan v. Curlew Irrigation & Reservoir Co.

104 P. 218, 36 Utah 382, 1909 Utah LEXIS 80
CourtUtah Supreme Court
DecidedSeptember 16, 1909
DocketNo. 1995
StatusPublished
Cited by18 cases

This text of 104 P. 218 (Ryan v. Curlew Irrigation & Reservoir Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryan v. Curlew Irrigation & Reservoir Co., 104 P. 218, 36 Utah 382, 1909 Utah LEXIS 80 (Utah 1909).

Opinion

FRICK, I.

On the 20th day of June, 1905, appellant and respondent entered into a contract by the terms of which appellant agreed to construct and complete a certain dam in Box Elder county, Utah, for the respondent. The contract, among other provisions, contained the following:

“The party of the second part [appellant] hereby undertakes and agrees to furnish the necessary labor and materials, including tools, implements and appliances, required, and to build and complete in a workmanlike manner an earthen dam and concrete tunnel across the creek mentioned above for the party of the first part [respondent], in the manner and under the condition and according to the specifications hereinafter set forth, and the plans for said work prepared by the engineer of the party of the first part.”

The contract specially provided when the work was to be commenced and when completed; the dimensions of the dam and the manner of its construction, together with the kind and quality of the materials to be used. In short the contract in terms provided what the contractor should do> and how the work should be done in constructing the dam. The contract also provided that payments to the contractor “are to be made on the 20th day of each month upon the report of the superintendent for the party of the first part.” In this way seventy-five per cent, of the work done and material furnished by the contractor was to be paid monthly, [386]*386and the remaining twenty-five per cent, of the contract price was to be paid sixty days after the “final completion of the entire work.” “All work to be inspected by the superintendent of the party of the first part, and no payments to be made except with his approval.” The contract also contained a special clause upon which appellant lays much stress, and for that reason we shall set it forth in full. It is as follows:

“To prevent disputes and litigation it is further agreed by and between the parties of this contract that E. J. Showell shall be referee in, all cases that may arise under this contract. In case the superintendent for the party of the first part shall question the work being done, either in workmanship or material, the contractor shall stop said work until the question has been settled by said referee and the decision of said referee shall be binding on the contractor.”

Appellant, in substance, alleged in his complaint that he had completed the dam in accordance with the terms of the contract, and that the same had been inspected by respondent’s superintendent, and accepted; that appellant had done certain extra work, and had furnished certain material not included in the original contract, and for which respondent was liable under the terms of the contract, amounting in round numbers to $704, and that there was due the appellant the sum of $1095.83 as the twenty-five per cent, remaining unpaid on the contract, the whole amount aggregating the sum of $1799.83, for which appellant demanded judgment. Respondent in its answer admitted the making of the contract, but denied that appellant had constructed the dam in accordance with its terms, or in accordance with the plans and specifications; denied that the dam had been completed and accepted, and also set forth several affirmative defenses and counterclaims which need not be specially mentioned. The case was tried to a jury, and the court withdrew from their consideration appellant’s claim for extra labor and material upon the ground that all the material claimed by appellant was in fact required to be furnished by him under the terms of the contract and as a part of it. The court also withdrew from the consideration of the jury respondent’s special counterclaims for damages, and submitted the case [387]*387to tbe jury upon tbe other issues presented by tbe pleadings. Tbe jury found tbe issues in favor of respondent, and returned a verdict against tbe appellant of “no cause of action.” Tbe court entered judgment upon tbe verdict, tbe effect of wbicb was a dismissal of tbe complaint, and for costs, against appellant.

Appellant contends that tbe court erred in its rulings by excluding bis claim for extra labor and material. We are of tbe opinion that tbe labor and material claimed by appellant as extra were not sucb, but that both tbe labor and material claimed as extra clearly came witbin tbe terms of tbe contract as labor and material to be provided by appellant as part of tbe contract and upon tbe terms and conditions therein specified. Appellant’s contention in this regard, therefore, cannot be sustained.

Appellant further asserts that tbe court erred in refusing appellant’s request to instruct tbe jury to return a verdict in favor of appellant, for tbe sum of $1095.83, tbe amount representing tbe twenty-five per cent claimed to be due him under tbe contract. This claim is based upon tbe provision of tbe contract as construed by appellant, and especially that clause of tbe contract wbicb provided for a referee in case of disputes. As we construe this clause, it was what is usually termed by tbe courts a “precautionary stipulation,” inserted in tbe contract for tbe benefit of tbe contractee. It is not a stipulation whereby tbe 1 whole matter as to whether tbe labor and material were of tbe kind and quality named in tbe contract, and whether tbe work required to be done was to tbe satisfa.etion of a certain person agreed upon by tbe parties. Under sucb stipulations tbe courts have frequently held that if the material is accepted by, and tbe work is done to tbe satisfaction of, tbe person named, then tbe contractee, in tbe absence of fraud, is estopped from subsequently disputing tbe fact that tbe work was completed and accepted in accordance with tbe stipulations of tbe contract. Moore v. Kerr, 65 Cal. 519, 4 Pac. 542, cited by appellant, is a case in wbicb tbe rale just referred to is illustrated and applied. In that [388]*388case tbe contract contained a stipulation that tbe bridge agreed to be constructed was “to, be built under tbe direction and to tbe satisfaction of tbe superintendent appointed by said board [tbe contráete©] in good and workmanlike manner.” Tbe trial court found that the bridge bad been built and completed to' tbe satisfaction of tbe superintendent, and that be bad accepted tbe same. Tbe Supreme Court of California accordingly beld that, in tbe absence of any allegation or proof of collusion and fraud between tbe superintendent and tbe contractor, tbe contractor, upon tbe findings made by tbe court, was, as a matter of law, entitled to judgment for tbe unpaid balance of tbe contract price. In tbe case of Wright v. Meyer, 25 S. W. 1125, tbe Court of Civil Appeals of Texas states tbe rule in tbe following language:

“The rule is that when the architect is, by the terms on, the contract, made the sole arbiter between the parties of matters concerning material and character of work: used in construction, the exercise of his judgment on such matters will be binding on the parties, unless some species of fraudulent conduct in respect thereto is pleaded and proved.”

Tbe referee clause of tbe contract in question is, however, not like tbe one passed on by tbe Supreme-Court of California nor like tbe one referred to by tbe Texas Court of Civil Appeals. This is clearly pointed out by tbe last-named court in tbe Wright Case. It is there in effect beld that tbe rule does not apply if the contract in terms provides tbe bind and quality of tbe material, and bow tbe work 2 shall be done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mid-America Pipeline Co. v. Four-Four, Inc.
2009 UT 43 (Utah Supreme Court, 2009)
Bailey-Allen Co., Inc. v. Kurzet
876 P.2d 421 (Court of Appeals of Utah, 1994)
Southwest Engineering Co. v. Reorganized School District R-9
434 S.W.2d 743 (Missouri Court of Appeals, 1968)
Worley Bros. v. Marus Marble & Tile Co.
161 S.E.2d 796 (Supreme Court of Virginia, 1968)
Lowe v. Rosenlof
364 P.2d 418 (Utah Supreme Court, 1961)
Fanderlik-Locke Co. v. United States
285 F.2d 939 (Tenth Circuit, 1960)
Wunderlich Contracting Company v. United States
240 F.2d 201 (Tenth Circuit, 1957)
Staley v. New
250 P.2d 893 (New Mexico Supreme Court, 1952)
Black v. Acers
178 S.W.2d 152 (Court of Appeals of Texas, 1943)
Gillespie Land & Irrigation Co. v. Hamilton
29 P.2d 158 (Arizona Supreme Court, 1934)
Murphy v. Salt Lake City
236 P. 680 (Utah Supreme Court, 1925)
Stephens v. Doxey
198 P. 261 (Utah Supreme Court, 1921)
Hansen v. Oregon Short Line R.
188 P. 852 (Utah Supreme Court, 1920)
Smith v. Columbus Buggy Co.
123 P. 580 (Utah Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
104 P. 218, 36 Utah 382, 1909 Utah LEXIS 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryan-v-curlew-irrigation-reservoir-co-utah-1909.