Cannon v. Hunt

38 S.E. 983, 113 Ga. 501, 1901 Ga. LEXIS 291
Supreme Court of Georgia·Decided May 22, 1901·Published·Cited by 17 cases

Opinion

Little, J.

This case seems to have been tried under a misapprehension of the rules of law which govern the issues raised by the pleadings and evidence. Mrs. Hunt, administratrix, instituted her action against Mrs. Cannon, to recover what she alleged was due to [502] her intestate as a balance on the contract price for furnishing material and erecting a brick store and office building in the city of Dalton. The work was undertaken under a contract, the material stipulations of which are as follows: The intestate agreed to furnish all the materials and labor of every kind, and build complete, on the lot of the defendant, a brick store and office building, as shown on certain plans and set forth in certain specifications, under the personal and direct supervision of J. A. Blanton. The specifications were made part of the contract. It was further agreed that the intestate should complete the work and turn the building over to the owner on or before the first day of December, 1898; and that, in consideration of the performance of said work according to agreement, the defendant should pay to the intestate the sum of $7,650. It was alleged that the intestate performed his contract in accordance with its terms as to character of work and material, and, although there was some delay in completing the work, it was from providential cause; and that defendant accepted the work and went into possession of the building when completed; and that defendant had paid $6,000 on the contract price, leaving due thereon $1,650, which petitioner is entitled to recover. She prayed for a judgment having a special lien on the lot and building. The defendant admitted the execution of the contract, but denied liability for any sum in excess of that which she had paid, and denied also that the failure to complete the braiding at the time specified was from providential cause, but charged that it was on account of the fault and neglect of the intestate. Defendant also averred that intestate had used defective material in the construction of the building, and that the workmanship on the same was bad; and set out a detailed statement of particulars in which she claimed to have been injured by the use of improper material and workmanship, in an amount exceeding $3,000. Among other things she claimed that the lumber used in constructing the house was of inferior quality and unseasoned; that the cement used was not that called for by the contract, but of an inferior quality, which would not shut out water; that the roofing was not done according to contract; that the doors and windows were not according to contract; and because of these imperfections the house leaked, her goods were damaged, and it would require a considerable sum of money to obviate these defects in material and construction.

[503] A number of witnesses were introduced for both plaintiff and defendant, but we do not find it necessary to refer to their evidence in detail. It is sufficient to say that the evidence for the plaintiff tended to show that the building was properly constructed, and, in the main, the materials used were those set out in the specifications. It was not denied that in certain particulars materials different from those described in the specifications were used in the construction of the building, but it was testified by some of the witnesses that those so used were as good as the materials which were specified. It was admitted also that the building was not completed and turned over within the time specified by the contract. On this point the evidence was conclusive as to the fact that the work on the budding was not commenced for a considerable period of time after the contract had been entered into, but was commenced in time to have completed it on the date called for by the contract, but that delays were occasioned for the want of material, and, for a considerable time after work was commenced-, by excessive rain and general bad weather. The evidence for the defendant tended to show the use of materials different from those specified, and also that defective material was used in the construction, in consequence of which she suffered loss; that a considerable sum of money would be required to put the building in the condition that it would have been in had proper materials been used in its construction, and the work properly done; that the building was never fully completed by the contractor, and possession was not delivered until February 15th, 1899. Evidence was also introduced in reference to the value of the building for rental purr poses, and, by the plaintiff, to the fact that the material which differed from that named in the specifications was placed in the building with the approval of Blanton, the superintendent, and G. H. Cannon, the agent of the defendant. Concerning this agency Cannon testified that he represented Mrs. Cannon, his wife, in the construction of the building. The jury returned a verdict for the plaintiff for $1,492.50, and established a lien for the same on the building. The defendant made a motion for' a new trial on several grounds, among others, that the verdict was contrary to law and the evidence in the case. The motion was overruled, and defendant excepted and assigns such refusal as error. Inasmuch as there is to be another trial of the case, we express no opinion on these grounds of the motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Cannon v. Hunt, 38 S.E. 983, 113 Ga. 501, 1901 Ga. LEXIS 291 (Ga. 1901).

38 S.E. 983 (Cannon v. Hunt) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hussey, Gay & Bell v. Georgia Ports Authority
420 S.E.2d 50 (Court of Appeals of Georgia, 1992)
Ramco Roofing & Supply Co. v. Kaminsky
275 S.E.2d 764 (Court of Appeals of Georgia, 1980)
Norair Engineering Corp. v. Saint Joseph's Hospital, Inc.
249 S.E.2d 642 (Court of Appeals of Georgia, 1978)
College Park Builders, Inc. v. Uplands Construction Corp.
127 S.E.2d 812 (Court of Appeals of Georgia, 1962)
Brand Inv. Co. v. United States
58 F. Supp. 749 (Court of Claims, 1944)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
Schaff v. Daugherty
1925 OK 66 (Supreme Court of Oklahoma, 1925)
Hood v. Community High School District No. 304
223 Ill. App. 451 (Appellate Court of Illinois, 1921)
Harmony Grove Telephone Co. v. Potts
100 S.E. 236 (Court of Appeals of Georgia, 1919)
Parrish v. Parrish
94 S.E. 315 (Court of Appeals of Georgia, 1917)
Ryan v. Curlew Irrigation & Reservoir Co.
104 P. 218 (Utah Supreme Court, 1909)
Town of Sterling v. Hurd
44 Colo. 436 (Supreme Court of Colorado, 1908)
Standard Supply Co. v. Carter Harris
62 S.E. 150 (Supreme Court of South Carolina, 1908)
Tasker v. Baugh & Johnson
53 S.E. 266 (Supreme Court of Georgia, 1906)
Central of Georgia Railway Co. v. Hall
52 S.E. 679 (Supreme Court of Georgia, 1905)