Mallard, Stacy & Co. v. Moody

31 S.E. 45, 105 Ga. 400, 1898 Ga. LEXIS 524
CourtSupreme Court of Georgia
DecidedJuly 21, 1898
StatusPublished
Cited by13 cases

This text of 31 S.E. 45 (Mallard, Stacy & Co. v. Moody) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mallard, Stacy & Co. v. Moody, 31 S.E. 45, 105 Ga. 400, 1898 Ga. LEXIS 524 (Ga. 1898).

Opinion

Simmons, C. J.

Mallard, Stacy & Co., tbe owners of a lot ■of land in the city of Atlanta, entered into a contract with the •George H. Holliday Lumber' Company, whereby the latter agreed,' for a certain consideration, to build' for thé former a hotel to -be known as the “Alhambrá.” ■ The articles of agreement mentioned certain drawings and specifications 'as a part of the contract, and also contained the following stipulation: “Should any difference of opinion arise respecting the true construction or meaning of the drawings-or specifications, the saíne shall be decided by the architect, and his decision shall be final and Conclusive.”'" The hotel was to be- completed by September 18,’ 1895. :The lumber coínpány claimed that they had completed the building' according to contract, ánd that the owners were indebted to them in a certain amount. Shortly after the completion -of their work, the lumber company filed and recorded its lien' for this amount. The lien was transferred by the contractor to Moody & Brewster', who brought suit upon it against Mallard, Stacy & Co. The defendants filed certain pleas, among them one to the effect that the contractor had not •completed the hotel according to the contract, having failed to put in a certain heating-apparatus required by the specifications, to wit: “Furnace. — The same to be furnished and set up at the designated place, a number 14 Mott Furnace with the usual fixtures, furnished with cold-air ducts, etc., for general [402]*402heating of all the halls, cafe, offices, parlor, and other parts, as per the plans prepared for heating. The furnace to be set up in the best possible manner and so arranged as to give the best possible results, and on the floors the requisite warm-air registers as marked, the registers to be not less than 12 by 14, and to have an independent line for each register.” Moody & Brewster replied that no specifications were ever signed by the contracting parties, and that, if such specifications had been signed, under the stipulation above cited, the architect had decided that the contractor was not bound by the contract to put in any sort of heating-apparatus. The trial judge in his charge to the jury instructed them to ascertain whether the specifications had been signed by the parties ; and that if the specifications had been signed by the parties and had become a part of the contract, and a difference had arisen as to the true construction or meaning of the clause in regard to heating, and the architect, under the authority given him by the- contract, decided that it did not include an obligation on the part of the lumber company to put in heating-apparatus, there would be no obligation on the part of the contractor to put in this heating-apparatus under this clause, and the defendants could not set up a failure to do so as any reason why they could decline to pay any part of the contract price. We think the learned judge of the court below misconstrued the meaning of the clause of the contract in relation to the power and authority of the architect. The architect had power under this clause simply to pass upon the meaning and construction of the drawings and specifications. He had the power to decide whether the work done was of the character or quality mentioned in the specifications. The specifications called for one Mott furnace with usual fixtures, etc. The architect had power to decide, had the contractor put in a furnace, whether it was the furnace required, and whether the usual fixtures, cold-air ducts, etc., were furnished according to the specifications, whether the apparatus heated the halls, cafe, offices, etc., and whether it was in accordance with “other parts, as per the plans prepared for heating.” He had also power to decide as to the materials used, and as to whether the furnace 'and fixtures were put up in a workmanlike manner. [403]*403If the specification as to heating-apparatus was agreed upon by the parties, it became a part of the contract, and there is nothing in the clause relative to the decision of the architect which gave him power to decide that a part of the contract between the parties is not binding. To give him such power would be to allow him to make a new contract for the parties. He could construe the contract and decide what it meant, or determine the nature and character of the work or materials required, but he could not eliminate or abrogate any of its terms. If the parties did agree upon these specifications and the clause requiring the heating-apparatus was a part of them, the decision of the architect, to the effect that the contractor was not bound to put in heating-apparatus, entirely eliminated this, clause and to that extent varied the contract made by the parties.

The certificate of the architect, upon the completion of the work, that the contract had been fully complied with, can not aid the plaintiffs as to their failure to put in the heating-apparatus. If a contractor agree to put in a heating-apparatus and fail entirely to comply with this agreement, or if he agree to build a house of stone and in fact build it of wood, the certificate of the architect that the work had been completed according to contract would not bind the owner. In the case of Bond v. Mayor etc. of Newark, 19 N. J. Eq. 376, it was held: “The certificate of a superintendent, surveyor, or architect, who by the contract for any work is to superintend its performance, and whose approval is required before any payment is due, can not dispense with the performance of any substantial part of the contract, but may be binding as to the fact whether the work certified to- was done in a workmanlike manner, or of proper materials of the kind required. But such certificate would not make building a brick house a compliance with a contract to build one of marble. Nor would the fact that a house built of brick is substantially, and for service, as good or better than one of marble, make such a building a performance of the contract, upon being certified to be so.” In the case of Woodruff v. Rochester & P. R. Co., 108 N. Y. 39, Earl, J., in speaking on this subject, said, in relation to the power of [404]*404engineers in accepting work done on a railroad: “But they had no power to alter or vary the terms of the contract or to create obligations binding upon the defendant not embraced in the contract,” citing many cases. Wait, in his work on Engineering and Architectural Jurisprudence, in speaking of the powers of architects and engineers, says (§ 371) : “The engineer is an agent with special powers, simply to do the engineering and to superintend and direct the work. "Unless specially conferred, he has no power to contract or to vary the terms of the parties’ agreement. He can create no new obligations not embraced by the contract.” And in section 402 he says: “It is usual to constitute the engineer a referee as to the meaning of the plans and specifications which are his own invention and handiwork, a certain construction of which is necessary to the proper erection and completion of the works. His powers can not be enlarged by implication, but they will be confined strictly within the terms of the contract.” In 2 Am. & Eng. Enc. L. (2d ed.) p. 820, it is said: “An architect superintending the erection of a building has no authority generally to make alterations in the plans and specifications and bind his employer for extra work, or to make any changes in the original contract.” “ He can not bind the employer by accepting a class of work inferior to or different from that called for by the contract.” In Glacius v. Black, 50 N. Y. 145, s. c. 10 Am. Rep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norair Engineering Corp. v. Saint Joseph's Hospital, Inc.
249 S.E.2d 642 (Court of Appeals of Georgia, 1978)
Cross v. State
221 S.E.2d 615 (Court of Appeals of Georgia, 1975)
Inc. Town of Bono v. Universal Tank & Iron Works
395 S.W.2d 330 (Supreme Court of Arkansas, 1965)
McJenkin Insurance & Realty Co. v. Thompson
54 S.E.2d 336 (Court of Appeals of Georgia, 1949)
Morgan v. Town of Burlington
55 N.E.2d 758 (Massachusetts Supreme Judicial Court, 1944)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
Oliver v. Head
2 S.E.2d 716 (Court of Appeals of Georgia, 1939)
Alexander v. Grenada Bank
2 Tenn. App. 580 (Court of Appeals of Tennessee, 1926)
Savannah Lighting Co. v. Fidelity & Deposit Co.
95 S.E. 113 (Court of Appeals of Georgia, 1918)
Eagle Brewing Co. v. Colaluca
94 A. 680 (Supreme Court of Rhode Island, 1915)
Rudulph v. State
85 S.E. 365 (Court of Appeals of Georgia, 1915)
McNulty v. Keyser Office Building Co.
76 A. 1113 (Court of Appeals of Maryland, 1910)
Cannon v. Hunt
38 S.E. 983 (Supreme Court of Georgia, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
31 S.E. 45, 105 Ga. 400, 1898 Ga. LEXIS 524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mallard-stacy-co-v-moody-ga-1898.