Morgan v. Town of Burlington

55 N.E.2d 758, 316 Mass. 413, 1944 Mass. LEXIS 726
CourtMassachusetts Supreme Judicial Court
DecidedJune 5, 1944
StatusPublished
Cited by19 cases

This text of 55 N.E.2d 758 (Morgan v. Town of Burlington) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morgan v. Town of Burlington, 55 N.E.2d 758, 316 Mass. 413, 1944 Mass. LEXIS 726 (Mass. 1944).

Opinion

Ronan, J.

This is an action of contract in which the plaintiff in the first count of his declaration seeks to recover the sum of $1,000 which the defendant claims to hold as liquidated damages, and, in the second count, damages which he alleges were caused by various breaches on the part of the defendant. The plaintiff had a verdict on both counts. The defendant excepted to the denial of its motions for directed verdicts, to the refusal of the judge to grant its requests, and to a portion of the charge.

There was evidence that the plaintiff entered into a written contract with the town by which he was to construct a high school building and complete the work in two hundred eighty-five days. He began work on October 12, 1938. The plans and specifications called for the disposal of drainage by a series of dry wells, but after the wells were dug it was discovered that such a system would not be practical on account of the nature of the soil, and the architect on October 28, 1938, ordered the plaintiff not to do any more work with reference to the drainage until a new system could be devised. Thereafter the architect drafted five different sets of plans for the new system, the final set being completed on March 1, 1939. There was evidence that two weeks would be a reasonable time for the preparation of a set of plans. The plaintiff’s bid for the installation of the new system was rejected and the defendant on August 1, 1939, awarded this work to another contractor. On account of the location of the pipes in the building the plaintiff was delayed in the performance of his work by the delay in furnishing plans and completing the drainage work. He also claims damages on account of the failure of the town to give him the work of installing the revised system of drainage. There was evidence that the plaintiff, the architect and the building committee which represented the town considered [415]*415this work as an extra under the contract. This work was not given to the plaintiff because the building committee thought his bid was too high. The building committee refused to grant an extension of time to the plaintiff from July 23, 1939, the time fixed by the contract for the completion of the work, to September 1, 1939, and the town has retained $1,000 for delay during this period of forty days at the contract price of $25 per day. This committee, however, granted the plaintiff an extension of time from September 2, 1939, to September 29, 1939, when a controversy was pending between the committee and certain public works administration officials with reference to electrical equipment. The school was completed before the last mentioned date. The bill of exceptions states that the case was referred to an auditor who filed a report which was put in evidence. The report is not referred to in the bill of exceptions other than by stating certain findings made by the auditor, which in effect were that the architect in revising the plans for the new drainage system acted in good faith but with a complete disregard of the effect of the delay on the plaintiff; that the delay in the completion of the building was due primarily to the delay in determining the new drainage system; that inclement weather caused some delay which could have been lessened if the building had been “closed in” by the plaintiff; that the plaintiff’s request for the forty-day extension should have been granted because the failure of the plaintiff to complete the building at the time fixed by the contract was not due to his fault or neglect; and that the work involved in the new drainage system should have been awarded to the plaintiff in accordance with the contract.

The contract defined “extra work” as work required by the town which in the judgment of the architect involved changes in or additions to the work required by the plans and specifications. The contract authorized the town to require the performance by the plaintiff of such extra work as the town might deem necessary, payment for which was to be computed in one of three ways mentioned. It contained a separate article which provided that, if the plain[416]*416tiff encountered subsurface conditions different from those shown on the plans or indicated by the specifications, he should immediately notify the architect, who should promptly investigate the conditions and, if he found them to be different from those represented by the plans or specifications, should at once make such changes in the plans and specifications as were necessary, and that any increase or decrease of cost resulting from such changes was “to be adjusted in the manner provided herein for adjustments as to extra and/or additional work and changes.” The contract provided for liquidated damages for each day the work remained uncompleted after July 23, 1939. It authorized the building committee to grant an extension of time for the completion of the work where the delay was not due to the fault or negligence of the plaintiff. It was expressly provided that the architect should represent the town in the performance of the work, all of which was to be performed under the direction and to the satisfaction of the architect. He was to determine the amount and suitability of all parts of the work, “interpret the plans, specifications, contract documents, and any extra work orders and . . . decide all other questions in connection with the work.”

The defendant makes three contentions, to wit, the plaintiff was not entitled to secure the new drainage work; the architect was not the agent of the defendant and it was not liable for his unreasonable delay in drafting plans for the new drainage system; and the defendant had a right to withhold the $1,000 as liquidated damages for the plaintiff’s delay in completing the work.

No question is raised but that the architect had the right to order the drainage work stopped when it was discovered that the nature of the soil would not make practicable the installation of the system originally contemplated. The installation of a system for the disposal of the drainage by dry wells in accordance with the plans and specifications could be found to indicate that the character of the subsoil was such as to permit the successful operation of such a system. When it was discovered that the subsoil would not permit the use of such a system, it became the duty of the [417]*417architect to devise a new system and to make “at once” the necessary “changes in the Plans and/or Specifications.” It is conceded by the defendant that there was unreasonable delay in changing the plans but it contends that it was not liable for the delay because the architect was not the agent of the defendant. There are two answers to this contention. In the first place, the contract expressly provided that in the performance of the work the architect was to be the representative of the defendant. To that extent, at least, he was the agent of the defendant. Leverone v. Arancio, 179 Mass. 439. The change in plans was an essential part of the work that he was employed to do in behalf of the town, which had the right to insist upon the prompt performance of this work by him, and in the performance of this particular detail of the work he was not acting in any dual capacity, or as an arbiter or in behalf of the plaintiff. We think that in respect to this change in the plans the architect was the agent of the defendant, and that the latter was hable for his unreasonable delay. Snead & Co. Iron Works v. Merchants Loan & Trust Co. 225 Ill. 442. Mayor & City Council of Baltimore v. Clark, 128 Md. 291. Mosler Safe Co. v. Maiden Lane Safe Deposit Co. 199 N. Y. 479.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

XL Specialty Insurance v. Massachusetts Highway Department
31 Mass. L. Rptr. 147 (Massachusetts Superior Court, 2013)
John J. Petruzzi-William E. Forrester, Inc. v. Massachusetts Turnpike Authority
9 Mass. L. Rptr. 184 (Massachusetts Superior Court, 1998)
Peabody N.E., Inc. v. Town of Marshfield
689 N.E.2d 774 (Massachusetts Supreme Judicial Court, 1998)
Peabody N.E., Inc. v. Town of Marshfield
6 Mass. L. Rptr. 473 (Massachusetts Superior Court, 1996)
Stamski & McNary, Inc. v. Anderson
1996 Mass. App. Div. 199 (Mass. Dist. Ct., App. Div., 1996)
Fontaine Brothers, Inc. v. Springfield
617 N.E.2d 1002 (Massachusetts Appeals Court, 1993)
Smith v. Allmon
461 N.E.2d 1237 (Massachusetts Appeals Court, 1984)
Thomas O'Connor & Co. v. City of Medford
448 N.E.2d 1276 (Massachusetts Appeals Court, 1983)
John F. Miller Co. v. George Fichera Construction Corp.
388 N.E.2d 1201 (Massachusetts Appeals Court, 1979)
Henry B. Byors & Sons, Inc. v. Board of Water Commissioners of Northborough
264 N.E.2d 657 (Massachusetts Supreme Judicial Court, 1970)
Wes-Julian Construction Corp. v. Commonwealth
223 N.E.2d 72 (Massachusetts Supreme Judicial Court, 1967)
Quintin Vespa Co. Inc. v. Construction Service Co.
179 N.E.2d 895 (Massachusetts Supreme Judicial Court, 1962)
Salem Glass Co. v. Joseph Rugo, Inc.
176 N.E.2d 30 (Massachusetts Supreme Judicial Court, 1961)
Fred C. McClean Heating Supplies, Inc. v. Jefferson Construction Co.
159 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1959)
FRED C. McCLEAN HEATING SUPPLIES v. JEFFERSON CONSTR.
159 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1959)
H. H. Hawkins & Sons Co. v. Robie
153 N.E.2d 768 (Massachusetts Supreme Judicial Court, 1958)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Garfield v. Smith
59 N.E.2d 287 (Massachusetts Supreme Judicial Court, 1945)
Edmund Wright Ginsberg Corp. v. C. D. Kepner Leather Co.
59 N.E.2d 253 (Massachusetts Supreme Judicial Court, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
55 N.E.2d 758, 316 Mass. 413, 1944 Mass. LEXIS 726, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morgan-v-town-of-burlington-mass-1944.