This text of 159 N.E.2d 95 (Fred C. McClean Heating Supplies, Inc. v. Jefferson Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fred C. McClean Heating Supplies, Inc. v. Jefferson Construction Co., 159 N.E.2d 95, 339 Mass. 356, 1959 Mass. LEXIS 812 (Mass. 1959).

Opinion

Cutter, J.

This is a bill in equity brought by a subcontractor to establish a hen (see G. L. c. 30, § 39, as amended through St. 1935, c. 472, § 12) for amounts not paid under its subcontract (a) upon money retained by the Commonwealth from amounts owing to the prime contractor, Jefferson Construction Co. (hereinafter called Jefferson), for construction at a teachers college, and (b) against a bond, executed by Jefferson and a surety company, to secure payments for work and materials. The case was referred to a master. Two exceptions (later mentioned) to the master’s report were sustained and, as thus modified, the report was confirmed by interlocutory decree. A final decree was entered adjudging Jefferson to be indebted to the subcontractor in the sum of $17,513.45 with interest and costs and directing that this sum, if not paid by Jefferson, be paid out of funds retained by the Commonwealth from the contract price or, in the alternative, by the surety on the bond. A counterclaim by Jefferson (for amounts alleged to have been spent by Jefferson for the account of the subcontractor) was dismissed. Jefferson has appealed from the interlocutory decree and the final decree. The facts are stated on the basis of the master’s report.

On September 10, 1954, Jefferson made a written proposal for construction for the Commonwealth at the State Teachers’ College at Westfield. In this proposal the subcontractor was named as subbidder for heating and ventilating under § 24. The subcontractor had previously submitted a bid “to furnish all labor and materials for the completion of all work under the subheading ‘Heating and [358]*358Ventilating’ Item H-V, pages 24-1 to 39 inclusive, in accordance with the plans and specifications prepared by Abbott Associates, Inc.” Jefferson was successful bidder for the building construction and the subcontractor’s bid for the heating and ventilating was approved.

On September 24, 1954, Jefferson executed a prime contract with the Commonwealth for the building construction and, shortly thereafter, the subcontractor entered into a subcontract on a standard form (American Institute of Architects) “to furnish labor, materials, tools, equipment, staging and do all heating and ventilating work as called for under, but not limited to [S]ection 24, [p]ages 24-1 thru 24-39 of the contract specifications.” Pertinent provisions of these and other specifications not later quoted in full in this opinion are set out in the margin.3 oil From this sub[359]*359contract, after it was signed by the subcontractor, Jefferson struck out the words “That there will be no temporary heat included” and returned to the subcontractor the contract signed, but thus altered. The subcontractor accepted the subcontract with the deletion.

Early in November, 1955, Jefferson notified the subcontractor that it was necessary that the permanent heating system be made available. Such heat was available, at the latest, by November 17,1955. The subcontractor, however, apparently did not make arrangements to operate the heating system after 4:30 p.m. on that day. Jefferson notified the subcontractor that it was “putting engineers on this heating system as of 4:30 p.m., November 17, and all costs in connection therewith will be charged against your contract due to your refusal to man the heating system.” Jefferson on November 17 also wrote to the subcontractor’s attorney that Jefferson agreed “that the cost of fuel is to be borne by the general contractor” but later attempted to withdraw this statement, as in effect an offer of compromise, by a letter of January 15, 1957.

From November 17,1955, through May 4,1956, to provide essential heat, Jefferson retained firemen to operate the permanent heating system and furnished the necessary oil. Although the subcontract provided that Jefferson would “perform no work chargeable to the Subcontractor without a written order from the” latter, the master found that a request for such an order would have been useless in view of the subcontractor’s contention that it was not obligated to provide labor and oil for operating the permanent heating system.

On May 31, 1956, Jefferson sent the subcontractor a bill for $11,772.29 for labor of firemen on the heating system [360]*360and, on November 21, 1956, many months after temporary heating had ended, a bill for $7,942.55 for oil. These charges the master found to be fair and reasonable. The subcontractor, however, prior to receipt of the later bill had no knowledge that Jefferson intended to hold it liable for oil.

The prime contract (art. Ill) between Jefferson and the Commonwealth contained a provision that the architect “shall decide all questions which may arise as to the quantity, quality, acceptability, fitness and rate of progress of the several kinds of work and materials to be performed and furnished under this contract, and shall decide all questions ... as to the interpretation of the plans and specifications and as to the fulfillment of this contract on the part of the Contractor,4 and his . . . decision shall be final . . . except as may be otherwise determined by the Division; and such . . . decision, in case any question shall arise, shall be a condition precedent to the right of the Contractor to receive any money hereunder ” (emphasis supplied).

On January 11, 1957, the architect wrote to Jefferson purporting to give “our interpretation of the specifications . . . namely, that (1) temporary heat, not using the permanent heating system is to be provided and cared for in its entirety by the General Contractor, and (2) temporary heat which uses the permanent heating system must be provided and cared for in its entirety by the heating subcontractor.” The master admitted this letter in evidence over the subcontractor’s objection. He also admitted, subject to objection, a letter of February 14, 1957, to Jefferson from the Commonwealth’s director of building construction expressing the “opinion of this [division that the architects [sic] interpretation of the specifications ... is correct.” Between the dates of these letters representatives of the interested parties and the architect were given a hearing before the division of building construction. The [361]*361subcontractor’s exceptions to the master’s report, based upon the objections to the admission of these two letters, were the two exceptions, already mentioned, which were sustained by the trial judge.

On January 15, 1957, Jefferson notified the subcontractor of four obviously trivial “discrepancies” in the subcontractor’s work. These were corrected by January 25. The Commonwealth had “formally accepted the . . . [pjroject ... on November 15, 1956, as of November 14, 1956.” The master, apparently relying on the correction of the alleged “discrepancies,” found that on “January 25, 1957, the . . . [subcontractor] ceased to perform labor and to furnish materials, appliances and equipment on said job and, on February 15, 1957, it filed a sworn statement of its claim with the [division . . . showing a balance due it of $17,513.45.” This amount the master found to be correct if the subcontractor “was not required to operate the permanent heating system for furnishing temporary heat . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Striar v. American Medical International, Inc.
695 N.E.2d 1079 (Massachusetts Appeals Court, 1998)
Jim Walsh Plumbing Co. v. Cresta Construction, Inc.
3 Mass. L. Rptr. 29 (Massachusetts Superior Court, 1994)
J.F. White Contracting Co. v. Department of Public Works
508 N.E.2d 637 (Massachusetts Appeals Court, 1987)
Bank of New England-Bay State v. Gillespie
1987 Mass. App. Div. 63 (Mass. Dist. Ct., App. Div., 1987)
Strand v. Herrick & Smith
489 N.E.2d 179 (Massachusetts Supreme Judicial Court, 1986)
Hardware Specialties, Inc. v. Mishara Construction Co.
311 N.E.2d 564 (Massachusetts Appeals Court, 1974)
Metro Insulation Corp. v. Leventhal
294 N.E.2d 508 (Massachusetts Appeals Court, 1973)
Henry B. Byors & Sons, Inc. v. Board of Water Commissioners of Northborough
264 N.E.2d 657 (Massachusetts Supreme Judicial Court, 1970)
ALBRE MARBLE & TILE CO. INC. v. Goverman
233 N.E.2d 533 (Massachusetts Supreme Judicial Court, 1968)
Harold L. Baker Co. v. Meledones
34 Mass. App. Dec. 103 (Mass. Dist. Ct., App. Div., 1966)
Quintin Vespa Co. Inc. v. Construction Service Co.
179 N.E.2d 895 (Massachusetts Supreme Judicial Court, 1962)
Farm-Rite Implement Co. v. Fenestra Inc.
163 N.E.2d 285 (Massachusetts Supreme Judicial Court, 1960)
FRED C. McCLEAN HEATING SUPPLIES v. JEFFERSON CONSTR.
159 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
159 N.E.2d 95, 339 Mass. 356, 1959 Mass. LEXIS 812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fred-c-mcclean-heating-supplies-inc-v-jefferson-construction-co-mass-1959.