Quintin Vespa Co. Inc. v. Construction Service Co.

179 N.E.2d 895, 343 Mass. 547, 1962 Mass. LEXIS 843
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 6, 1962
StatusPublished
Cited by61 cases

This text of 179 N.E.2d 895 (Quintin Vespa Co. Inc. v. Construction Service Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quintin Vespa Co. Inc. v. Construction Service Co., 179 N.E.2d 895, 343 Mass. 547, 1962 Mass. LEXIS 843 (Mass. 1962).

Opinion

Cutter, J.

These are cross-actions (a) by Quintín Yespa Co., Inc. (Yespa) against Construction Service Company (Construction) and Maryland Casualty Company, surety on bonds furnished by Construction in connection with a contract, and (b) by Construction against Yespa. The eases were consolidated and referred to an auditor. After the filing of his report, the parties stipulated “that the auditor’s report will be accepted as an agreed statement of facts, subject to . . . [certain] additions, modifications, and amendments.” They also agreed that if, under the contract, 1 Construction was to do the work of sheeting and shoring, then the finding should be in favor of Yespa; if Yespa was to do the sheeting and shoring, then the finding should be in favor of Construction.” The cases were tried by a judge in the Superior Court, without jury, “upon the agreed facts.” Both parties submitted requests for rulings of law. The judge “found” for Construction in each case and, in the case brought by Construction, assessed its damages at $1,530.46. The case is here on Yespa’s exceptions to the findings and to the granting and denial of vari *549 ous requests for rulings. The facts are stated from the auditor’s report as augmented.

In 1956, Vespa was laying sewer pipe under a contract with the town of Framingham. It became necessary to place the pipe and its casing under an aqueduct. Vespa approached Construction to do the work, 1 and Construction offered to “take over the entire work that Vespa was to do in this segment [of the whole sewer job] — for . . . $5,000 . . .. Vespa refused this offer.” Construction then offered for $2,500 “to furnish the equipment and install the casing . . . [if] Vespa was to furnish the labor and materials and dig the required access trench.” Construction submitted a proposal to this effect which in part is set out in the margin. 2 The proposal was on a printed proposal form used by Construction. 3 “Vespa told Strickland, Con *550 struction’s foreman, that he would not sign the contract if he were required to install sheeting and shoring. Strickland thereupon telephoned Van Nest, Construction’s vice president, . . . and . . . repeated Vespa’s objections. . . . Van Nest asked Strickland if Strickland thought sheeting and shoring would be necessary, and Strickland said ‘no.’ Van Nest then authorized Strickland to strike out the following words in the proposal as originally submitted [the omitted material included the words “sheeting and shoring if required” and the other italicized words of the proposal, see footnote 2, supra] .... [B]oth parties initialed the deletions. Thereupon the contract was executed as per copy ...” attached to the auditor’s report.

“Shortly after the excavation work had started, water came into the trench in large quantities, causing the sloping sides to slough off and filling the trench so that pumps had to be operated continuously. This condition practically put a stop to the excavation work. Only thirty feet in length were completed and even that part was not fully down to grade. Pumps were supplied by Vespa and operated by Construction. At that point, the town engineer . . . ordered Vespa to put in shoring and sheeting at the aqueduct end of the trench, lest the stability of the aqueduct be affected by . . . erosion .... Vespa demanded that Strickland do the sheeting, but Strickland refused. Vespa thereupon installed some shoring and sheeting at the aqueduct end of the trench and about thirty feet down the sides, but not enough to box in the whole trench. . . . Vespa demanded that Construction pay for it. Construction refused. . . .

“Over twelve days . . . had elapsed by this time, during which . . . Construction had had its equipment and men *551 continuously on the job. The trench was still unfinished and it seemed unlikely that it could be finished at all unless a well-point system was installed. The sheeting used by Vespa . . . had been improperly placed. It failed to hold back either the water or the bank. It was in a state of collapse. Van Nest . . . inspected the work. . . . [H]e ordered Construction’s equipment to be removed, and called off his working force. ’ ’ Vespa then entered into a contract with another firm to do the work.

The auditor found that, if there was a breach of contract by Construction, Vespa’s damages were $3,500 and that, if there was a breach by Vespa, " Construction should be awarded as . . . [the] sum by it expended . . . $1,530'.46 . . . in furnishing equipment and crew.” His conclusions are summarized in the margin. 4

1. The agreement as to the facts contained in the augmented auditor’s report, which had attached the contract itself, presents a case stated. No evidence was considered by the trial judge. It would have avoided some doubt and confusion if the parties had been explicit in stipulating that they intended to present a case stated. Nevertheless, this is the substance of what they have done. Their agreement was not merely an agreement as to evidence. Cf. King Features Syndicate, Inc. v. Cape Cod Bdcst. Co. Inc. 317 Mass. 652, 653. The interpretation of the written contract is, of course, a matter of law. The requests for rulings need not concern us. They have no standing. It was the duty of the trial judge and it is our duty to order the correct *552 judgment on the agreed facts. Richard D. Kimball Co. v. Medford, 340 Mass. 727, 728-729.

2. The interpretation of the contract 5 involves, among other things, the significance, if any, of (a) the deletion of the words “sheeting and shoring if required” (see footnote 2, supra, at point [0]); (b) the presence in the proposal of such provisions as those with respect to a trench and a possible well point system (see footnote 2, supra, at points [N] and [P]); and (c) par. (14) of the printed standard proposal provisions (see footnote 3, supra). We consider these matters in order.

(a) The deletion of the words “sheeting and shoring if required” grew out of Vespa’s refusal to “sign the contract if he [Vespa] were required to install sheeting and shoring.” Although it was found that the words were omitted after Construction’s foreman expressed the opinion that no sheeting and shoring “would be necessary,” the precise reasons and motives for the deletion are not clear from the auditor’s report. Construction may have agreed to the deletion, in part at least, because it was of opinion (a) that the deleted words were unnecessary or redundant, and that the remaining contract provisions adequately protected it, or (b) that they had at least primary reference to the burden of shoring as a safety precaution for workmen which was unlikely to be necessary, and which, perhaps, might be covered by par. (15). See footnote 3, supra. See Fred C. McClean Heating Supplies, Inc. v. Jefferson Constr. Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mt. Ivy Press, L.P. v. Defonseca
937 N.E.2d 501 (Massachusetts Appeals Court, 2010)
T.T.K., Inc. v. Columbia Speedway Plaza Member, LLC
26 Mass. L. Rptr. 235 (Massachusetts Superior Court, 2009)
Astra USA, Inc. v. Bildman
455 Mass. 116 (Massachusetts Supreme Judicial Court, 2009)
Astra USA, Inc. v. Bildman
19 Mass. L. Rptr. 368 (Massachusetts Superior Court, 2005)
Cadle Co. v. DeVincent
781 N.E.2d 817 (Massachusetts Appeals Court, 2003)
Zero Stage Capital, Inc. v. Harvard Clinical Technology, Inc.
14 Mass. L. Rptr. 690 (Massachusetts Superior Court, 2002)
Firstar Communications of Louisiana, LLP v. Tele-Publishing, Inc.
798 So. 2d 1032 (Louisiana Court of Appeal, 2001)
Thompson v. Daluise (In Re Wet-Jet International, Inc.)
235 B.R. 142 (D. Massachusetts, 1999)
Verderber v. Perry
First Circuit, 1999
Besicorp Group, Inc. v. Thermo Electron Corp.
981 F. Supp. 86 (N.D. New York, 1997)
Horton v. Horton
487 S.E.2d 200 (Supreme Court of Virginia, 1997)
National Private Truck Council v. Commissioner of Revenue
6 Mass. L. Rptr. 350 (Massachusetts Superior Court, 1997)
Lease-It, Inc. v. Massachusetts Port Authority
600 N.E.2d 599 (Massachusetts Appeals Court, 1992)
Bonnano v. Sotir
1992 Mass. App. Div. 202 (Mass. Dist. Ct., App. Div., 1992)
ITT Corp. v. LTX Corp.
774 F. Supp. 681 (D. Massachusetts, 1991)
O'Connell Management Co. v. Carlyle-XIII Managers, Inc.
765 F. Supp. 779 (D. Massachusetts, 1991)
Ritchie v. Shay
1991 Mass. App. Div. 42 (Mass. Dist. Ct., App. Div., 1991)
DeSanctis v. Labell's Airport Parking, Inc.
1991 Mass. App. Div. 37 (Mass. Dist. Ct., App. Div., 1991)

Cite This Page — Counsel Stack

Bluebook (online)
179 N.E.2d 895, 343 Mass. 547, 1962 Mass. LEXIS 843, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quintin-vespa-co-inc-v-construction-service-co-mass-1962.