Enfield Builders, Inc. v. the Commonwealth of Massachusetts, Division of Capital Asset Management and Maintenance

CourtMassachusetts Superior Court
DecidedMay 12, 2025
Docket2184CV01075-BLS2
StatusPublished

This text of Enfield Builders, Inc. v. the Commonwealth of Massachusetts, Division of Capital Asset Management and Maintenance (Enfield Builders, Inc. v. the Commonwealth of Massachusetts, Division of Capital Asset Management and Maintenance) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Enfield Builders, Inc. v. the Commonwealth of Massachusetts, Division of Capital Asset Management and Maintenance, (Mass. Ct. App. 2025).

Opinion

SUPERIOR COURT

ENFIELD BUILDERS, INC. v. THE COMMONWEALTH OF MASSACHUSETTS, DIVISION OF CAPITAL ASSET MANAGEMENT AND MAINTENANCE

Docket: 2184CV01075-BLS2
Dates: April 14, 2025
Present: Kenneth W. Salinger Justice of the Superior Court
County: SUFFOLK
Keywords: DECISION AND ORDER ALLOWING DEFENDANT’S MOTION FOR SUMMARY JUDGMENT AND DENYING PLAINTIFF’S MOTION TO STRIKE

The Division of Capital Asset Management and Maintenance for the Commonwealth of Massachusetts (“DCAMM”) hired Enfield Builders, Inc. (“EBI”) to build a new medical and intake facility at the Worcester County Jail. Although the construction contract provided that time was of the essence, EBI did not come close to completing the project on time. DCAMM claims that EBI also committed other material breaches of its contractual obligations. DCAMM eventually terminated the contract, hired another firm to complete the Project, and invoked its contractual right to have EBI reimburse and indemnify it for additional costs that DCAMM incurred to complete the project.

EBI brought suit claiming that the delays were DCAMM’s fault and that EBI is entitled to be paid in full under the contract or to additional compensation on theories of quantum meruit and unjust enrichment. DCAMM asserts counterclaims for breach of contract, breach of warranty, breach of the implied covenant of good faith, and to enforce its indemnification rights.

The Court will deny EBI’s motion to strike parts of the summary judgment record. It allow in part DCAMM’s motion for summary judgment with respect to EBI’s claims, EBI’s liability under DCAMM’s counterclaims for breach of contract and contractual indemnification, and EBI’s affirmative defense of failure to mitigate damages except as to the roofing system. These rulings establish that DCAMM is entitled to recover at least $7,449,415.05 from EBI, plus reasonable attorneys’ fees and court costs. The Court will deny in part the summary judgment motion with respect to whether DCAMM is entitled to recover an additional $1,415,703.00 that it paid to replace the roofing system on the new facility, and with respect to DCAMM’s counterclaim for breach of warranty. Finally, the Court will grant summary judgment in favor of EBI on DCAMM’s counterclaim for breach of the implied covenant of good faith.

                                                            -1-

1. Motion to Strike. EBI asks the Court to strike an affidavit authenticating documents as having been produced by one side or the other during discovery, to strike those documents on the ground that they have not been properly authenticated, and to strike a second affidavit concerning the total amount paid by DCAMM to complete the Project after EBI’s contract was terminated. This motion to strike is without merit.

1.1. Authentication Affidavit. The challenged affidavit of Attorney Kenneth Thayer merely establishes that the first 85 summary judgment exhibits were produced during discovery or constitute an excerpt of deposition testimony, and that exhibit 86 is an accurate copy of an affidavit by Catherine Walsh.

It is commonplace and entirely appropriate for an attorney representing a party moving for summary judgment to authenticate documents as having been produced during discovery. Indeed, EBI relies upon the affidavit of its counsel, Attorney Fredrick Hedberg, to authenticate numerous documents that were produced during discovery and marked as exhibits during depositions. There is no reason why Attorney Hedberg is competent to do so but Attorney Thayer is not.

Since EBI does not actually challenge the authenticity of any of the documents authenticated in the Thayer affidavit, no further proof of authenticity is required. Indeed, under these circumstances, the Court could consider these documents as being authentic without relying on the Thayer affidavit.

If a party seeking summary judgment relies on documents the authenticity of which is not challenged by the opposing party, those documents are “proper parts of the summary judgment record” even if the moving party presents no affidavit or other evidence authenticating the documents. See City of Boston v. Roxbury Action Program, Inc., 68 Mass. App. Ct. 468, 469 n.3, rev. denied, 449 Mass. 1101 (2007). Where the authenticity of an exhibit has not been attacked, it “must be accepted as true.” Northeastern Malden Barrel Co. v. Binder, 341 Mass. 710, 713 (1961); Gahn v. Leary, 318 Mass. 425, 427 (1945). In any case, Massachusetts law does not require trial judges to be “overly technical” in determining what they “should consider on a motion for summary judgment.” Correllas v. Viveiros, 410 Mass. 314, 317 (1991).

EBI’s throw-away argument that “[n]ot all documents produced in discovery or that are part of the discovery record are admissible” is correct but beside the point. EBI makes no attempt to show that any of the documents submitted by DCAMM is inauthentic or that it is inadmissible for any other reason.

                                                            -2-

1.2. Extra Cost Affidavit. EBI’s challenge to parts of Ms. Walsh’s affidavit is also without merit. Ms. Walsh testifies under oath that (among other things): (I) she has been a project manager at DCAMM for about 20 years, and was DCAMM’s project manager for construction of the Worcester County Jail Medical and Intake Facility; (ii) she reviewed all payment requisitions for the Project “to determine whether, in my opinion, the invoices sought payments for charges that were reasonable and necessary in connection with the work that had been performed;” (iii) DCAMM made payments totaling $8,865,118.05 to complete the Project after it terminated EBI; (iv) Walsh “approved those payments as reasonable and necessary in order to complete the project in order to achieve a final facility that could be used, as intended, by the Worcester County Sheriff’s Office;” and (v) Walsh understands that those payments are detailed in a particular summary judgment exhibit.

Ms. Walsh’s opinion that these payments were reasonable and necessary is relevant and admissible. The reasonableness of those payments is relevant to DCAMM’s counterclaim for indemnification. And Ms. Walsh’s opinion is admissible because she has the requisite expertise to determine whether costs incurred for the Project were reasonable, her opinion would assist the factfinder if the case were to go to trial, and her opinion is based on her actual, real-time review of payment requisitions as the Project was being completed.

Whether compensation for construction work performed was reasonable is a question of fact, and therefore a topic as to which expert testimony is permissible, not a legal conclusion as to which expert opinion would be improper. See Towner v. Bennington Const. Co., Inc., 2005 WL 3105653, at *11 (Mass. Super. Oct. 12, 2005) (Rufo, J.); see also In re Will of Crabtree, 449 Mass. 128, 142 (2007) (reasonableness of compensation for trustee is question of fact); Guenard v. Burke, 387 Mass. 802, 808 (1982) (reasonable compensation owed to attorney with unenforceable contingent fee agreement is question of fact); Irwin v. Degtiarov, 85 Mass. App. Ct. 234, 238–239 (2014) (reasonableness of veterinary costs is question of fact); Crowley v. Communications for Hospitals, Inc., 30 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guenard v. Burke
443 N.E.2d 892 (Massachusetts Supreme Judicial Court, 1982)
Ward v. American Mutual Liability Insurance
443 N.E.2d 1342 (Massachusetts Appeals Court, 1983)
George v. Goldman
131 N.E.2d 772 (Massachusetts Supreme Judicial Court, 1956)
Northeastern Malden Barrel Co. Inc. v. Binder
172 N.E.2d 123 (Massachusetts Supreme Judicial Court, 1961)
Glynn v. City of Gloucester
487 N.E.2d 230 (Massachusetts Appeals Court, 1986)
Frank Fitzgerald, Inc. v. PACELLA BROTHERS, INC
310 N.E.2d 379 (Massachusetts Appeals Court, 1974)
Zarum v. Brass Mill Materials Corp.
134 N.E.2d 141 (Massachusetts Supreme Judicial Court, 1956)
Crowley v. Communications for Hospitals, Inc.
573 N.E.2d 996 (Massachusetts Appeals Court, 1991)
Correllas v. Viveiros
572 N.E.2d 7 (Massachusetts Supreme Judicial Court, 1991)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Welch v. Keene Corp.
575 N.E.2d 766 (Massachusetts Appeals Court, 1991)
Alpert v. Commonwealth
258 N.E.2d 755 (Massachusetts Supreme Judicial Court, 1970)
Quintin Vespa Co. Inc. v. Construction Service Co.
179 N.E.2d 895 (Massachusetts Supreme Judicial Court, 1962)
Kass v. Todd
284 N.E.2d 590 (Massachusetts Supreme Judicial Court, 1972)
Commonwealth v. Johnson
21 N.E.3d 937 (Massachusetts Supreme Judicial Court, 2014)
Commonwealth v. DiCicco
25 N.E.3d 859 (Massachusetts Supreme Judicial Court, 2015)
Coghlin Electrical Contractors, Inc. v. Gilbane Building Co.
472 Mass. 549 (Massachusetts Supreme Judicial Court, 2015)
Robert and Ardis James Foundation v. Meyers
48 N.E.3d 442 (Massachusetts Supreme Judicial Court, 2016)
A.L. Prime Energy Consultant, Inc. v. Mass. Bay Transportation Authority
95 N.E.3d 547 (Massachusetts Supreme Judicial Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Enfield Builders, Inc. v. the Commonwealth of Massachusetts, Division of Capital Asset Management and Maintenance, Counsel Stack Legal Research, https://law.counselstack.com/opinion/enfield-builders-inc-v-the-commonwealth-of-massachusetts-division-of-masssuperct-2025.