Verderber v. Perry

CourtCourt of Appeals for the First Circuit
DecidedMarch 10, 1999
Docket98-1625
StatusPublished

This text of Verderber v. Perry (Verderber v. Perry) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Verderber v. Perry, (1st Cir. 1999).

Opinion

USCA1 Opinion
[NOT FOR PUBLICATION     NOT TO BE CITED AS PRECEDENT]


United States Court of Appeals
For the First Circuit
____________________
No. 98-1625
PAULA VERDERBER and JOSEPH VERDERBER,

Plaintiffs, Appellants,

v.

WINSTON C. PERRY, PARKER D. PERRY,
and ANDREA J. PERRY,

Defendants, Appellees.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MASSACHUSETTS

[Hon. William G. Young, U.S. District Judge]

____________________

Before

Boudin, Circuit Judge,
Gibson, Senior Circuit Judge,and Lynch, Circuit Judge.

____________________

Barry S. Scheer, with whom Parker | Scheer, Attorneys were on brief, for appellants.
Rosemary Traini, with whom Robert G. Cohen and Gittelsohn, Traini & Cohen were on brief, for appellees.

____________________

March 8, 1999
____________________
LYNCH, Circuit Judge. Winston, Parker, and Andrea Perry owned twenty-three acres of undeveloped land in Walpole, Massachusetts ("the land"). The Perrys contracted with Paula Verderber, a local real estate agent, and Joseph Verderber, a local contractor, to subdivide and develop the land. When the Perrys canceled the deal, the Verderbers filed suit. The district court found the Perrys liable for breach of contract, but awarded damages well below the Verderbers' demand. The Verderbers appeal from this damage award.
I
We discuss only those facts relevant to this appeal. The parties formalized their contract through a letter agreement, the validity of which is not challenged before this court. The contract was quite simple; its relevant aspects were even simpler. The Perrys would provide the land in exchange for the first $800,000 from its sale. Verderber Real Estate (essentially, Paula Verderber) would provide "marketing and sales effort" in return for a 5% brokerage commission on all sales. The Perrys would pay 60%, and the Verderbers 40%, of expenses incurred in the development process. These payments would be reimbursed "in full from the proceeds of the sale of the lots before the net amount is divided." (emphasis in original). The net amount -- the profits -- would be apportioned 60% to the Perrys and 40% to the Verderbers.
The project moved through its preliminary phases. Despite the sixty-forty split intended by the contract, the Perrys paid the vast majority of the expenses incurred. Before ground was broken on the development's homes, however, Winston Perry lost confidence in the Verderbers, and the Perrys canceled the contract. The Verderbers filed this action in Superior Court, and the Perrys removed to federal court under diversity jurisdiction. The district court heard the case on an expedited, jury-waived basis. After a three-day trial, the court found the Perrys in breach, and awarded damages to the Verderbers of $41,656.59. The Verderbers moved to amend the judgment, challenging the award as too low. The district court denied this motion, citing the contract doctrines of setoff and unjust enrichment. The Verderbers appealed. Before this court, the parties dispute neither the district court's factual findings nor most of its arithmetic; their arguments focus on a single aspect of the damages calculation.
II
This court reviews "the district court's findings of fact for clear error and its conclusions of law de novo." Arthur D. Little, Inc. v. Dooyang Corp., 147 F.3d 47, 54 (1st Cir. 1998) (citing Cambridge Plating Co. v. Napco, Inc., 85 F.3d 752, 769 (1st Cir. 1996)). In its initial ruling from the bench, the district court grounded its decision on the facts; in denying the motion to amend the judgment, however, the court relied on contract doctrines. We examine these rulings from both perspectives: first, as to whether the description of facts is clear error, and second, to see if the court correctly applied the law.The district court calculated damages based on the parties' expectations, or the "value of performance of [the] contract to the plaintiff[s]." To find this value, the court made several subsidiary findings of fact. The court found that "the fair per lot valuation" was $147,500, and that the land included fifteen lots. To develop and sell these lots, the court found, the parties would have to pay $740,649 in development costs. The court projected the contract's value by subtracting costs from revenue:
$2,212,500 Sale value of 15 lots at $147,500 each
-800,000 Payment for the land (paid to the Perrys)
-110,575 5% commissions (paid to Paula Verderber)
-740,649 Repayment of costs incurred
-----------
$561,276 Profit (revenues less costs)

The court then determined the Verderbers' share of the profits, and added the commissions Mrs. Verderber would have received:
$561,276 Profit
*40% Verderbers' percentage share
-----------
$224,510.40 Verderbers' share of profits
110,575.00 Commissions paid to Paula Verderber
-----------
$335,085.40 Net due the Verderbers under the contract

The parties do not contest the calculations thus far.
On appeal, the Verderbers challenge only the district court's additional adjustment, explained in its ruling from the bench:
That gives us, when I sum those, a total of $335,085.40. But against that, against that, there must be deducted so much of the development costs to which [the Verderbers] should have but have not contributed, giving them credit against the development costs, the soft development costs of $115,000, giving the Verderbers credit for $2,028 and then taking the sum of the hard and the soft development costs as reduced, their contribution would have been $293,428.81, which leaves judgment for the plaintiffs in the amount of $41,656.59. Judgment will enter for the plaintiff in that sum.

This final calculation can be restated as a formula:
$335,085.40 Net due the Verderbers under the contract
-293,428.81 Verderbers' contribution to development costs -----------
$41,656.59 Recovery for Verderbers

The Verderbers dispute this portion of the ruling, contending that the district court deducted their share of the development costs twice. When the court subtracted total costs of $740,649 from the profits, the Verderbers argue, it fully accounted for their failure to pay their share of these costs.
The Verderbers' argument is best understood by looking at the contract from their perspective. Expectation damages should place the Verderbers in the position they would occupy had the contract been executed in full. Adopting the district court's factual findings, the Verderbers claim their final position should be as follows:
$0 Verderbers' baseline net worth
-296,259.60 Verderbers' share of costs (40% of $740,649)
296,259.60 Reimbursement of costs under 4 of contract
110,575 Commissions paid to Paula Verderber
224,510.40 Verderbers' share of profits (40% of $561,276)
-----------

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adams v. Zimmerman
73 F.3d 1164 (First Circuit, 1996)
Cambridge Plating Co. v. Napco, Inc.
85 F.3d 752 (First Circuit, 1996)
Arthur D. Little, Inc. v. Dooyang Corp.
147 F.3d 47 (First Circuit, 1998)
U.S. Controls Corp. v. Windle
509 F.2d 909 (Seventh Circuit, 1975)
Bushkin Associates, Inc. v. Raytheon Company
906 F.2d 11 (First Circuit, 1990)
Ward v. American Mutual Liability Insurance
443 N.E.2d 1342 (Massachusetts Appeals Court, 1983)
Massachusetts Motor Vehicle Reinsurance Facility v. Commissioner of Insurance
400 N.E.2d 221 (Massachusetts Supreme Judicial Court, 1980)
Zarum v. Brass Mill Materials Corp.
134 N.E.2d 141 (Massachusetts Supreme Judicial Court, 1956)
Lease-It, Inc. v. Massachusetts Port Authority
600 N.E.2d 599 (Massachusetts Appeals Court, 1992)
Realty Developing Co. v. Wakefield Ready-Mixed Concrete Co.
100 N.E.2d 28 (Massachusetts Supreme Judicial Court, 1951)
Quintin Vespa Co. Inc. v. Construction Service Co.
179 N.E.2d 895 (Massachusetts Supreme Judicial Court, 1962)
Perry v. Pye
102 N.E. 653 (Massachusetts Supreme Judicial Court, 1913)
Peabody N.E., Inc. v. Town of Marshfield
689 N.E.2d 774 (Massachusetts Supreme Judicial Court, 1998)
Hastings Associates, Inc. v. Local 369 Building Fund, Inc.
675 N.E.2d 403 (Massachusetts Appeals Court, 1997)
Garnick & Scudder, P.C. v. Dolinsky
701 N.E.2d 357 (Massachusetts Appeals Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Verderber v. Perry, Counsel Stack Legal Research, https://law.counselstack.com/opinion/verderber-v-perry-ca1-1999.