Poorvu Constr. Co. Inc. v. Nelson Electrical Co. Inc.

140 N.E.2d 891, 335 Mass. 545, 1957 Mass. LEXIS 538
CourtMassachusetts Supreme Judicial Court
DecidedMarch 11, 1957
StatusPublished
Cited by13 cases

This text of 140 N.E.2d 891 (Poorvu Constr. Co. Inc. v. Nelson Electrical Co. Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Poorvu Constr. Co. Inc. v. Nelson Electrical Co. Inc., 140 N.E.2d 891, 335 Mass. 545, 1957 Mass. LEXIS 538 (Mass. 1957).

Opinion

Cutter, J.

The plaintiff is a contractor who was awarded the general contract for the construction of a school building in the town of Lynnfield. Each of the defendants was named in the plaintiff’s bid, under item 2 of the bid, as a subcontractor, each for a specified part of the work, and was approved as a subcontractor by the town. The bids were submitted to the town in accordance with G. L. (Ter. Ed.) c. 149, §§ 44A-44C, inclusive, as appearing in St. 1954, c. 645, §§ 1-3; § 44D, inserted by St. 1939, c. 480; and § 44E, inserted by St. 1954, c. 645, § 4. 1

After the award of the general contract to the plaintiff and prior to the execution of the subcontracts with the defendants, respectively, the plaintiff demanded from each of the defendants a performance bond and a payment bond covering work under its subcontract. It was contended by the defendants that, under the 1954 amendments of §§ 44A-44C, inclusive, an approved subcontractor could not be required to furnish a performance bond and a payment bond to the plaintiff, even if the plaintiff paid the bond premiums. The dispute was settled, apparently so that the work would not be delayed, by the execution of a subcontract by each defendant from which had been struck out printed provisions whereby “each of the defendants [was required] at *547 its own expense to furnish to the plaintiff a performance and payment bond . . . equal to 100% of the subcontract price”; “in place of” such provisions each defendant stipulated with the plaintiff that a performance bond would be furnished by the subcontractor “and in the event that the court determines that the cost of said . . . bond must be borne by the general contractor that the general contractor will reimburse the subcontractor for the cost.” Apparently, despite their stipulation, for reasons not apparent on this record, only one of the defendants actually furnished a performance bond on these terms.

The plaintiff brought this bill for declaratory relief as to its rights. The trial judge found the facts substantially as summarized above and entered a final decree outlining the situation and dismissing the bill and determining (a) that §§ 44A-44E (as amended by the 1954 legislation) bar the plaintiff from requiring the bonds here in issue and the insertion in the bid and subcontract documents of any requirement for such bonds, and (b) that the bond in fact given by one of the defendants should be cancelled and that this defendant should be reimbursed for the premium. The parties, in lieu of including certain testimony in the record, entered into a stipulation entitled “Agreed Statement of Facts on Appeal.” This was done with the approval of the trial judge. Apart from the facts summarized in the ‘ ‘ Agreed Statement,” the trial judge also found in substance that there was no evidence of any practice or custom or usage with respect to the requiring by general contractors of performance bonds from subcontractors under the 1954 legislation, inasmuch as no practice could have developed in the brief interval between the effective date of the 1954 amendments and the signing of the contracts here in issue.

The provisions of the General Laws governing bidding on public works of the type and value here involved were inserted by St. 1939, c. 480, and were comprehensively revised by St. 1941, c. 699, and St. 1954, c. 645. This court has had occasion to consider the earlier or the 1954 forms of the pro *548 visions principally 1 in three cases, Gifford v. Commissioner of Public Health, 328 Mass. 608; East Side Construction Co. Inc. v. Adams, 329 Mass. 347; Grande & Son, Inc. v. School Housing Committee of North Beading, 334 Mass. 252, in which various aspects of the general structure of the statute have been considered.

Sections 44A-44C contemplate that requests for bids will designate certain work on each project to be done by subcontractors. General contractors are required to file their bids on a form set out in § 44C (G) in two parts, “Item 1, covering all the work of the general contractor” and “Item 2, covering the work and the bid prices therefor of the subcontractors.” By § 44C (B) all principal and designated minor subcontractors are required to “deliver or mail to the awarding authority record copies of all bids sent by them to the general contractor” on the bid form set forth in § 44C (H). Section 44C (B) also directs, by a provision which was new in 1954, that “Bids which are incomplete, conditional or obscure, or which contain additions not called for, shall be rejected” (emphasis supplied). By § 44C (C) only those subbidders who have filed their bids in this manner may be used by the general contractor in his bid. The statute and the statutory bid forms contain various provisions, not here relevant in detail, for the substitution of subbidders by subsequent arrangement (in precise conformity with the statutory procedure) between a successful general bidder and the awarding authority, but from all of these provisions it appears that the general contractor is not to be required to employ for work any subcontractor (at least if not included in his own bid for that work) against whose standing and ability the general contractor makes objection.

The bid form for general contractors found in § 44C (G) as amended in 1954 provides that he “within five days . . . after presentation thereof by the awarding authority, [will] *549 execute the contract and furnish a performance bond and also a labor and materials or payment bond . . . each in the sum of at least fifty per cent of the contract price, the premiums for which are to be paid by the general contractor and are included in the contract price.”

The provisions of § 44C (E) and the related bid form have gone through various changes in 1941 and 1954 since their original enactment in 1939, which, in major degree, give rise to the present controversy. The changes in § 44C (E) are best shown by the following excerpt from the section as amended by St. 1941, c. 699, § 4. The words in italics were added in 1941. The other words were in the original form of the section as enacted in 1939. “(E) If a sub-contractor who has been selected and included in the general contract fails to sign the sub-contract within ten days after notice of selection, or fails to furnish a performance bond to the general contractor within ten days after notice of selection if required so to do by the general contractor or the awarding authority, by an instrument in writing mailed or delivered to such sub-contractor with, or within five days after, such notice of selection, the awarding authority, architect and engineer, or any one or more of them, and the general contractor shall select, from the sub-bidders who have conformed to the bidding procedure, the next lowest bidder at the amount named in such sub-bid, and the total contract price shall be revised in accordance with the change in figures as submitted.”

By St. 1954, c. 645, § 3, § 44C (E) was restored to its 1939 form in all substantial respects here pertinent. 1 All ref *550

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.F. White Contracting Co. v. Department of Public Works
508 N.E.2d 637 (Massachusetts Appeals Court, 1987)
Modern Continental Construction Co. v. Lowell
465 N.E.2d 1173 (Massachusetts Supreme Judicial Court, 1984)
Modern Continental Construction Co. v. City of Lowell
465 N.E.2d 1173 (Massachusetts Supreme Judicial Court, 1984)
Roblin Hope Industries, Inc. v. J. A. Sullivan Corp.
377 N.E.2d 962 (Massachusetts Appeals Court, 1978)
Interstate Engineering Corp. v. City of Fitchburg
329 N.E.2d 128 (Massachusetts Supreme Judicial Court, 1975)
AMERICAN AIR FILTER CO. INC. v. Innamorati Bros. Inc.
260 N.E.2d 718 (Massachusetts Supreme Judicial Court, 1970)
Rudolph v. City Manager of Cambridge
167 N.E.2d 151 (Massachusetts Supreme Judicial Court, 1960)
Fred C. McClean Heating Supplies, Inc. v. Jefferson Construction Co.
159 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1959)
FRED C. McCLEAN HEATING SUPPLIES v. JEFFERSON CONSTR.
159 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1959)
Pacella v. Metropolitan District Commission
159 N.E.2d 75 (Massachusetts Supreme Judicial Court, 1959)
Loranger v. MARTHA'S VINEYARD REGIONAL HIGH SCH. DIST.
155 N.E.2d 791 (Massachusetts Supreme Judicial Court, 1959)
Loranger v. Martha's Vineyard Regional High School District School Committee
155 N.E.2d 791 (Massachusetts Supreme Judicial Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
140 N.E.2d 891, 335 Mass. 545, 1957 Mass. LEXIS 538, Counsel Stack Legal Research, https://law.counselstack.com/opinion/poorvu-constr-co-inc-v-nelson-electrical-co-inc-mass-1957.