Grande & Son, Inc. v. School Housing Committee of North Reading

135 N.E.2d 6, 334 Mass. 252, 1956 Mass. LEXIS 655
CourtMassachusetts Supreme Judicial Court
DecidedJune 1, 1956
StatusPublished
Cited by37 cases

This text of 135 N.E.2d 6 (Grande & Son, Inc. v. School Housing Committee of North Reading) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grande & Son, Inc. v. School Housing Committee of North Reading, 135 N.E.2d 6, 334 Mass. 252, 1956 Mass. LEXIS 655 (Mass. 1956).

Opinion

Wilkins, J.

This is a petition for a writ of certiorari to quash the action of the respondent school housing committee of the town of North Reading in awarding a contract for the construction of a Junior-Senior High School to L & R Construction of Medford, Inc. (hereinafter called L & R), as general contractor. The petitioner (hereinafter called Grande) was an unsuccessful general contract bidder, which contends that, had proper action been taken, it would have been selected as the “lowest responsible and eligible bidder for the complete work.” G. L. (Ter. Ed.) c. 149, § 44A, as appearing in St. 1954, c. 645, § 1. The respondent committee filed a return. In the Superior Court a final judgment was entered dismissing the petition, and the pe *254 titioner appealed. G. L. (Ter. Ed.) c. 213, § ID, inserted by St. 1943, c. 374, § 4.

The commissioner of labor and industries and the members of the department of labor and industries of the Commonwealth should not have been made parties respondent. 1 The only proper respondents to a petition for a writ of certiorari are the members of the tribunal whose action is to be examined. Marcus v. Commissioner of Public Safety, 255 Mass. 5, 8. Marshall v. Registrar of Motor Vehicles, 324 Mass. 468, 469. Massachusetts Feather Co. v. Aldermen of Chelsea, 331 Mass. 527, 528-529.

The sole question presented to the court below was whether G. L. (Ter. Ed.) c. 149, § 44C (A) cl. 1, as appearing in St. 1954, c. 645, § 3, because of the Connor subbid, hereinafter referred to, made it mandatory upon the respondent committee to reject the bid of L & R. The case presents issues under the statutes regulating the award of contracts for public building projects by competitive bidding. The provisions of § 44C (A) cl. 1 are: “Bids from general contractors shall be for the complete work as specified [emphasis suppliedj and shall include the names of subcontractors and the amounts of their bids as designated in item two of the bid form and the general contractor shall be selected on the basis of such bid. Bids from general contractors must be submitted on the bid form for general contractors as set forth in (G) of this section [§ 44C (G)[. Bid forms shall be completely filled in. Bids which are incomplete, conditional or obscure, or which contain additions not called for, shall be rejected.”

These are the facts giving rise to the dispute. The town, represented by the respondent committee, invited sealed bids to be submitted in accordance with specifications for the school building, which is a project subject to G. L. *255 (Ter. Ed.) c. 149, §§ 44A-44C, as appearing in St. 1954, c. 645, §§ 1-3, § 44D, inserted by St. 1939, c. 480, and § 44E, inserted by St. 1954, c. 645, § 4. Bids of general contractors were to be submitted to the respondent committee at the town hall not later than 8 p.m. on April 22, 1955, at which time all bids were to be opened. Bids of subcontractors, including those for work on acoustical tile ceilings, were to be submitted two days earlier. The bid form for general contractors called for bids in two items, item 1 to be the work of the general contractor, and item 2 to consist of the subbids, in this instance twenty-three in number. This was required by G. L. (Ter. Ed.) c. 149, § 44C (A) cl. 2, as appearing in St. 1954, c. 645, § 3.

When the bids of the general contractors were publicly opened and read, the two lowest were as follows:

Grande, accordingly, was low on item 1, but L & R was low on item 2 and on the total bid.

In item 2 under the subbid for acoustical tile ceilings Grande listed Acoustical Contractors, Inc., as the bidder and $26,656 as the amount, and L & R listed Frederick A. Connor as the bidder and $18,000 as the amount. When the respondent committee opened the subbids, they discovered that the Connor subbid was based, not upon the specified acoustical tile ceilings, but upon acoustical plastic mechanically applied. L & R already knew, or should have known of the contents of the Connor subbid, which carried the statement authorized by § 44C (B) that it was being sent to all general bidders except one, not L & R. For subbid form see § 44C (H). While not a fact essential to our decision, the observation is material that making an intelligent general bid involves knowledge of the contents of the subbids listed in it. It may be noted that there is no contractual relation between the awarding authority and a subbidder. East Side Construction Co. Inc. v. Adams, 329 *256 Mass. 347, 353. M. Ahern Co. v. John Bowen Co. Inc. ante, 36, 41.

The bid of Acoustical Contractors, Inc., was the lowest of four proper subbids for acoustical tile ceilings, all by sub-bidders whose responsibility and eligibility were not questioned by the respondent committee. Likewise the responsibility and eligibility of Grande as a general contractor were not so questioned.

On May 20, 1955, the respondent committee and L & R signed a contract for construction of the school building. The contract price was $1,544,298.80; item 1 was $686,-514.30; and item 2 was $857,784.50. 1 Under the work covered by four subbids appeared the word “allowance”: acoustical tile ceilings $18,000; stage curtains and lighting $6,200; bleachers $7,242; and household arts equipment $13,992. In view of the fact that the one question raised in the court below concerned the Connor subbid, the only so called allowance we shall consider is that relating to acoustical tile ceilings.

It is manifest that the original bid of L & R was not “for the complete work as specified” and was not a compliance with the statute. In substance, there is no difference between a subbid changed by the general contractor, as in Gifford v. Commissioner of Public Health, 328 Mass. 608, or the failure to include a subbid, as in East Side Construction Co. Inc. v. Adams, 329 Mass. 347, and the facts confronting us, where one of the subbids utterly failed to comply with the specifications. This, indeed, was the opinion of the commissioner of labor and industries, whose advice had been sought, which he gave in a letter dated May 3, 1955, to the town counsel who represented the respondent committee. There is nothing in Capuano, Inc. v. School Building Committee of Wilbraham, 330 Mass. 494, which aids the respondent committee. We are dealing with a case of “illegal” action and not with “conclusions as to matters of fact within their jurisdiction” (page 496).

*257 In justification of the award of the contract to L & R on a new basis not in accordance with the specifications, several arguments have been advanced. One is that pursuant to c. 149, § 44C (D), as appearing in St. 1954, c. 645, § 3, 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. Amanti & Sons, Inc. v. R.C. Griffin, Inc.
758 N.E.2d 153 (Massachusetts Appeals Court, 2001)
J.F. White Contracting Co. v. Massachusetts Port Authority
748 N.E.2d 1020 (Massachusetts Appeals Court, 2001)
White's Farm Dairy, Inc. v. City of New Bedford
10 Mass. L. Rptr. 348 (Massachusetts Superior Court, 1999)
Nercessian v. Board of Appeal on Motor Vehicle Liability Policies & Bonds
709 N.E.2d 1134 (Massachusetts Appeals Court, 1999)
Construction Industries of Massachusetts, Inc. v. City of Peabody
6 Mass. L. Rptr. 615 (Massachusetts Superior Court, 1997)
Bowman v. Drewry
5 Mass. L. Rptr. 104 (Massachusetts Superior Court, 1996)
ASEC Corp.-Holden Engineering v. Massachusetts Highway Department
4 Mass. L. Rptr. 604 (Massachusetts Superior Court, 1995)
Petricca Construction Co. v. Commonwealth
640 N.E.2d 780 (Massachusetts Appeals Court, 1994)
Sciaba Construction Corp. v. City of Boston
617 N.E.2d 1023 (Massachusetts Appeals Court, 1993)
Peabody Construction Co. v. City of Boston
546 N.E.2d 898 (Massachusetts Appeals Court, 1989)
Phipps Products Corp. v. Massachusetts Bay Transportation Authority
443 N.E.2d 115 (Massachusetts Supreme Judicial Court, 1982)
Datatrol Inc. v. State Purchasing Agent
400 N.E.2d 1218 (Massachusetts Supreme Judicial Court, 1980)
Commonwealth v. Gill
363 N.E.2d 267 (Massachusetts Appeals Court, 1977)
Paul Sardella Construction Co. v. Braintree Housing Authority
356 N.E.2d 249 (Massachusetts Supreme Judicial Court, 1976)
PAUL SARDELLA CONSTR. v. Braintree Hous. Auth.
329 N.E.2d 762 (Massachusetts Appeals Court, 1975)
Sardella Construction Co. v. Braintree Housing Authority
329 N.E.2d 762 (Massachusetts Appeals Court, 1975)
Interstate Engineering Corp. v. City of Fitchburg
329 N.E.2d 128 (Massachusetts Supreme Judicial Court, 1975)
Hardware Specialties, Inc. v. Mishara Construction Co.
311 N.E.2d 564 (Massachusetts Appeals Court, 1974)
Carrier v. Board of Health
236 N.E.2d 922 (Massachusetts Supreme Judicial Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
135 N.E.2d 6, 334 Mass. 252, 1956 Mass. LEXIS 655, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grande-son-inc-v-school-housing-committee-of-north-reading-mass-1956.