Sciaba Construction Corp. v. City of Boston

617 N.E.2d 1023, 35 Mass. App. Ct. 181, 1993 Mass. App. LEXIS 830
CourtMassachusetts Appeals Court
DecidedAugust 23, 1993
Docket92-P-328
StatusPublished
Cited by36 cases

This text of 617 N.E.2d 1023 (Sciaba Construction Corp. v. City of Boston) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sciaba Construction Corp. v. City of Boston, 617 N.E.2d 1023, 35 Mass. App. Ct. 181, 1993 Mass. App. LEXIS 830 (Mass. Ct. App. 1993).

Opinions

Dreben, J.

Sciaba Construction Corporation (Sciaba) filed suit in the Superior Court against the city of Boston (city) and Modern Continental Construction Co., Inc. (Modern), seeking preliminary and permanent injunctions to prevent the city from awarding a contract for the repair of the North Washington Street Bridge to Modern on the ground that the award would be in violation of G. L. c. 30, § 39M,3 the stat[183]*183ute governing competitive bidding procedures on public works projects. The Department of Labor and Industries (department) was allowed to intervene as a party plaintiff.4 A judge of the Superior Court denied the application for a preliminary injunction as did a single justice of this court upon Sciaba’s petition for relief under G. L. c. 231, § 118, first par. Sciaba then filed this appeal under the second paragraph of G. L. c. 231, § 118. We agree that no injunction should have issued.

The facts are not in dispute. The city solicited competitive bids for the repair of the North Washington Street bridge pursuant to G. L. c. 30, § 39M. Each bidder was required to list separate prices for the various categories of work to be performed. For each item for which a quantity was listed by the city, the bidder was to specify a unit price in both words and figures and to compute the extended bid price by multiplying the unit price by the estimated quantity. The bidder was also required to provide a total bid price by adding the various extended bid prices.

Upon opening the bids on September 19, 1991, the three lowest bidders were as follows:

Modern Continental Construction $2,287,950.
Sciaba Construction Corporation $2,338,200.
N.E.L. Corp. $2,655,462.

Modern’s bid contained an error in item No. 860.04 for the painting of a four-inch, reflectorized white line. While Modern listed a unit price of fifteen dollars in words and figures for an estimated quantity of 6,400 linear feet, its extended price was $960, a figure that was also reflected in Modern’s total bid price. See note 5, infra.

[184]*184The bid package furnished by the city to all bidders provided: “In case of a discrepancy between the prices written in words and those written in figures, the written words shall govern. In the event there is a discrepancy between the unit prices and the total sum of all the Items, the unit prices shall govern.” If this formula had been applied, Modern’s total bid price would have been based on a figure of $96,000 (6,400 x $15) for the white line, and Sciaba claims it would have been the lowest bidder.

Based upon the prices for the item quoted by Sciaba (twenty-five cents per linear foot) and the other low bidder, N.E.L. Corp. (twelve cents per linear foot), and the city’s own estimate of ten cents per linear foot, the city’s commissioner of public works concluded that Modern had made an obvious clerical error in its bid. For this reason he declined to apply the formula. Instead, relying on another provision in the bid specifications that reserved to him “the right to reject any and all proposals, or any Item or Items of the proposal should he deem it to be for the best interest of the City so to do,” the commissioner rejected all bids for the painting of the reflectorized white lines.

The commissioner then awarded the contract to Modern, basing his decision on the following grounds: (1) the painting of the lines involved very minor work not directly connected to the main purpose of the contract, and it could easily be performed by a separate service order or by the city itself; (2) the dollar amount of the repair work was insignificant in relation to the total contract, representing a mere .03% of the entire project; (3) Modern’s unit price was, on its face, an obvious clerical error; and (4) the rejection of all bids for this item would prevent an unnecessary expenditure of approximately $50,000 in public funds (the difference between Modern’s and Sciaba’s bid).

When notified of the city’s decision, Sciaba filed a protest with the department, and, when advised that the city would ignore the department’s determination in Sciaba’s favor, see note 4, supra, Sciaba filed this action. It now appeals from the denial of a preliminary injunction.

[185]*185Since the contract has been awarded and the bidding documents provided that the work was to be completed “within 180 consecutive days,” there is presently nothing to enjoin. Accordingly, the appeal from the denial of the application for a preliminary injunction is moot. See Utility Contractors Assn. of New England, Inc. v. Department of Pub. Works, 29 Mass. App. Ct. 726, 729 (1991). Nevertheless, as (1) the matter has been briefed and argued at some length, the issue is one of public importance and is likely to arise again in similar factual circumstances and is likely to evade judicial review, and (2) a decision will probably prevent further litigation between the parties as to bid preparation costs, we consider it appropriate to express our views on the merits of this controversy. See Ciszewski v. Industrial Acc. Bd., 367 Mass. 135, 141-142 (1975).

While strict adherence to statutory bidding requirements is required in matters of substance, Grande & Son, Inc. v. School Hous. Comm. of N. Reading, 334 Mass. 252, 258 (1956); Gil-Bern Constr. Corp. v. Brockton, 353 Mass. 503, 505-506 (1968), and this is so even in cases where the violation benefits the public, Phipps Prod. Corp. v. Massachusetts Bay Transp. Authy., 387 Mass. 687, 692 (1982), minor deviations from statutory bidding requirements do not compel rejection of the bid or invalidation of a contract.

Absent other considerations, an obvious clerical error that deceives no one does not require rejection of a bid. Fred C. McClean Heating Supplies Inc. v. School Bldg. Commn. of Springfield, 341 Mass. 322, 324 (1960). Thus, in that case the court held that the obvious clerical error of a bidder (West Side) in placing the figure for a deduction in “Alternate A” and writing “none” in “Alternate B,” when the figure should have been placed in “Alternate B,” did not compel rejection of the bid. The petitioner had relied on G. L. c. 149, § 44H, which requires rejection of every subbid “which is on a form . . . which is incomplete, ... or which contains any addition not called for.” Rejecting the petitioner’s claim that the subbid was “incomplete” since there was no figure for “Alternate B” and that it contained an “addition not [186]*186called for” by reason of the presence of a figure in “Alternate A,” the court, at 324, stated, “The legislative intent to protect the public (Grande & Son, Inc. v. School Hous. Comm. of N. Reading, 334 Mass. 252, 258) does not require that § 44H be given the harsh and unreasonable construction which would be necessary to strike down the West Side subbid.” Similarly in DiMinico & Cincotta, Inc. v. Fire Commr. of Boston, 346 Mass. 766 (1963), the court held that a bid was not “incomplete” and could be accepted even though a requested figure for the amount to be charged by the general contractor had been omitted. The bidder was required to list in item 1 all the charges of the general contractor, in item 2 the charges of the subcontractors, and to compute the total charges.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MARK A. ADAMS v. SCHNEIDER ELECTRIC USA.
101 Mass. App. Ct. 516 (Massachusetts Appeals Court, 2022)
COMMONWEALTH v. MICHAEL RODRIGUEZ.
101 Mass. App. Ct. 439 (Massachusetts Appeals Court, 2022)
COMMONWEALTH v. TIMOTHY M. LAVIN (and ten companion cases ).
101 Mass. App. Ct. 278 (Massachusetts Appeals Court, 2022)
ANTONIO LACY v. JOHN COUGHLIN & another.
100 Mass. App. Ct. 321 (Massachusetts Appeals Court, 2021)
COMMONWEALTH v. RALPH R., a juvenile.
100 Mass. App. Ct. 150 (Massachusetts Appeals Court, 2021)
DON PERRY v. ZONING BOARD OF APPEALS OF HULL & others.
100 Mass. App. Ct. 19 (Massachusetts Appeals Court, 2021)
Commonwealth v. Alves
Massachusetts Appeals Court, 2019
Commonwealth v. Summers
Massachusetts Appeals Court, 2018
Commonwealth v. O'Leary
Massachusetts Appeals Court, 2017
Jane J. v. Commonwealth
Massachusetts Appeals Court, 2017
Commonwealth v. Drapaniotis
89 Mass. App. Ct. 267 (Massachusetts Appeals Court, 2016)
A.T. v. C.R.
Massachusetts Appeals Court, 2015
Pfannenstiehl v. Pfannenstiehl
88 Mass. App. Ct. 121 (Massachusetts Appeals Court, 2015)
Commonwealth v. Warren
87 Mass. App. Ct. 476 (Massachusetts Appeals Court, 2015)
Washington v. Cranmer
20 N.E.3d 613 (Massachusetts Appeals Court, 2014)
Bulwer v. Mount Auburn Hospital
16 N.E.3d 1090 (Massachusetts Appeals Court, 2014)
Brait Builders Corp. v. Town of Hingham
28 Mass. L. Rptr. 445 (Massachusetts Superior Court, 2010)
Commonwealth v. Lindsey
893 N.E.2d 52 (Massachusetts Appeals Court, 2008)
INTERNATIONAL SALT CO., LLC v. City of Boston
547 F. Supp. 2d 62 (D. Massachusetts, 2008)
Balyozian v. City of Somerville
22 Mass. L. Rptr. 303 (Massachusetts Superior Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
617 N.E.2d 1023, 35 Mass. App. Ct. 181, 1993 Mass. App. LEXIS 830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sciaba-construction-corp-v-city-of-boston-massappct-1993.