Brait Builders Corp. v. Town of Hingham

28 Mass. L. Rptr. 445
CourtMassachusetts Superior Court
DecidedDecember 6, 2010
DocketNo. PLCA200800862A
StatusPublished

This text of 28 Mass. L. Rptr. 445 (Brait Builders Corp. v. Town of Hingham) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brait Builders Corp. v. Town of Hingham, 28 Mass. L. Rptr. 445 (Mass. Ct. App. 2010).

Opinion

Hely, Charles J., J.

A. Introduction

In 2008, the Town of Hingham conducted a bidding procedure for the construction of a new school. The project was a state assisted building project. Hingham awarded the general contract to the lowest bidder, CTA Construction Co., Inc. The plaintiff, Brait Builders Corp., was the second lowest bidder.

In a prior Superior Court action, Brait sought an injunction that would prohibit Hingham from awarding the contract to CTA. The application for an injunction was denied. CTA built the school. CTA’s construction of the school was substantially completed in July 2009.

In the present action, Brait seeks monetary damages from Hingham. Both counts in Brait’s complaint allege that Hingham violated the public bidding laws, G.L.c. 149, §§44A-44J, and G.L.c. 30, §39M, the minority and women business participation requirements of G.L.c. 7, §40N, and the Municipalities General Guidelines of the State Office of Minority and Women Business Assistance (“SOMWBA”). Brait’s specific violation-of-law argument is that Hingham allowed an untimely request by CTA for a reduction of the minority and women business participation goals. Brait also argues that Hingham allowed CTA’s goals reduction request without proper notice to Brait. Brait’s complaint seeks to recover from the town $2,150,000 in lost profit and bid cost damages.

Hingham is entitled to judgment as a matter of law. There is an absence of evidence that the contract award to CTA, the lowest bidder, violated any substantive statutory requirement. See Kourouvacilis v. General Motors Corp., 410 Mass. 706, 711-12, 716 (1991).

B. Undisputed Material Facts

The facts stated in this decision are drawn from undisputed portions of the Mary Mahoney affidavit, the bid and contract documents and correspondence attached to the Mahoney affidavit, Hingham’s Interrogatory Answers, the Robert Brait affidavit, and the parties’ statement of facts.

(1) The Bid Documents and the SOMWBA General Guidelines

The 2008 bidding procedure for the school project was conducted by the Hingham School Building Committee and the Owner’s Project Manager, Mary Mahoney. Hingham distributed Bid Documents to pre-qualified general contractors including CTA and Brait. The portions of the Bid Documents that pertained to minority and women business participation goals were in the Invitation to Bid, Instructions to Bidders, and sections of the Contract for Construction Services and General Conditions (“the Contract”). Mahoney Aff. Ex. 2.

The Invitation to Bid and the Instructions to Bidders informed bidders that “before the contract award” the lowest general bidder would be required to provide the Owner with documentation stating how it intends to meet the minority and women business enterprise participation goals for the project. The Invitation to Bid and the Instructions to Bidders stated that the goal for minority business enterprise participation was 7.4% of the construction contract amount and that the goal for women business enterprise participation was 4% of the construction contract amount.

Neither the Invitation to Bid nor the Instructions to Bidders nor the Contract required general contract bidders to provide documentation with their bids on how the bidder intended to comply with the minority and women business participation goals. Instead, the Invitation to Bid and the Instructions to Bidders “strongly encouraged” general bidders and filed sub-bidders to include such documentation with their bids submissions.

Article 16 of the Contract was also included in the bid documents. Article 16 stated the same minority and women business participation goals as in the Invitation to Bid and the Instructions to Bidders. Article 16 refers to Appendix A to the Contract. Appendix A is the SOMWBA Municipalities General Guidelines of Januaiy 10, 2007 (“General Guidelines”).

The section of the General Guidelines relied on by Brait in this case is Attachment C, Section 9. This [446]*446section states that for contracts in which filed sub-bids are solicited requests by prospective general bidders to reduce the minority and women business participation goals “must be received by the Awarding Authority no later than five (5) working days after the list of filed sub-Bidders is mailed by the Awarding Authority to persons who have taken out plans for the Contract.” Attachment C, Section 9, of the General Guidelines states that the Awarding Authority “WILL NOT CONSIDER ANYREQUESTTO REDUCE OR WAIVE THE MBE/WBE PARTICIPATION GOALS FOR THIS CONTRACT THAT IS RECEIVED AFTER THESE DEADLINES."

Attachment C, Section 9, of the General Guidelines also states: “Any redaction or waiver of the MBE/WBE participation goals for this Contract will be made by written addendum mailed to all persons who have taken out plans for the project”

(2) CTA’s Waiver Request, Hingham’s Review of the Waiver Request, and the Award of the Contract

The filed sub-bids for the project were filed on March 5, 2008. In three of the sub-bid categories (masomy, waterproofing and plumbing), all of the sub-bids were rejected. At this point, because no filed sub-bids were accepted for these three trades, Hingham directed the general bidders to include in their general contract bid price allowances for these three trades totaling $3,610,000.

The bids for the general contract were submitted on March 26. CTA’s general contract bid of $21,295,000 was the lowest. Brait’s general contract bid of $21,748,000 was the second lowest.

On March 28, Hingham asked CTA to begin assembling documents and information to confirm the value of the work that CTA intended to subcontract to minority businesses and women businesses. Mahoney Aff. After the receipt of the general bids, Hingham asked CTA to submit its Schedule of Participation for minority and women businesses before Hingham decided whether CTA should be awarded the contract. Higham Int. Answer 6. Hingham also required CTA to provide it with information describing the extent of CTA’s pre-bid efforts to solicit interest for the project from minority and women business enterprises.

On April 4, Brait sent the Building Committee a bid protest letter formally protesting CTA’s bid. Mahoney Aff. Ex. 6. Brait’s letter contended that CTA’s bid should be rejected because CTA did not submit to the town its minority and women business enterprise Schedule of Participation within five days of the opening of the general bids.

On April 8, CTA sent the Building Committee a letter formally requesting a waiver in the form of a reduction of the minority and women business participation goals. CTA’s letter contained a detailed explanation of its good faith efforts to comply with the goals. In its April 8 letter and ensuing discussions with Hingham, CTA maintained that at the time of its general bid submission it had no control over the selection of subcontractors for the three trades for which filed sub-bids had been rejected. Mahoney Aff. Ex.; Hingham Int. Answer 6.

CTA pointed out that the available subcontract work for minority and women business participation was further reduced because a number of the subcontract trades had no viable SOMWBA certified subcontractors. CTA stated that it had directly solicited interest from approximately 365 SOMWBA certified subcontractors and 67 Blue Book minority and women subcontractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Engineering Corp. v. City of Fitchburg
329 N.E.2d 128 (Massachusetts Supreme Judicial Court, 1975)
Sciaba Construction Corp. v. City of Boston
617 N.E.2d 1023 (Massachusetts Appeals Court, 1993)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Peabody Construction Co. v. City of Boston
546 N.E.2d 898 (Massachusetts Appeals Court, 1989)
Gil-Bern Construction Corp. v. City of Brockton
233 N.E.2d 197 (Massachusetts Supreme Judicial Court, 1968)
John T. Callahan & Sons, Inc. v. City of Malden
713 N.E.2d 955 (Massachusetts Supreme Judicial Court, 1999)
Annese Electrical Services, Inc. v. City of Newton
730 N.E.2d 290 (Massachusetts Supreme Judicial Court, 2000)
J. J. & V. Construction Corp. v. Commissioner of Public Works
363 N.E.2d 303 (Massachusetts Appeals Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
28 Mass. L. Rptr. 445, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brait-builders-corp-v-town-of-hingham-masssuperct-2010.