Annese Electrical Services, Inc. v. City of Newton

730 N.E.2d 290, 431 Mass. 763, 2000 Mass. LEXIS 360
CourtMassachusetts Supreme Judicial Court
DecidedJune 21, 2000
StatusPublished
Cited by34 cases

This text of 730 N.E.2d 290 (Annese Electrical Services, Inc. v. City of Newton) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Annese Electrical Services, Inc. v. City of Newton, 730 N.E.2d 290, 431 Mass. 763, 2000 Mass. LEXIS 360 (Mass. 2000).

Opinion

Spina, J.

Annese Electrical Services, Inc. (Annese), brought suit against the city of Newton (Newton), claiming that it was [764]*764entitled to the subcontract for electrical work on a public building project and that Newton’s resolicitation of electrical subbids for the project violated G. L. c. 149, § 44E (1). The parties filed cross motions for summary judgment. A Superior Court judge denied Annese’s motion and granted Newton’s motion, concluding that Newton acted within its discretion to rebid the work. On appeal, Annese argues that the judge erred because (1) Newton lacked discretion under G. L. c. 149, § 44E (1), to resolicit subbids after its first solicitation yielded five bids, none of which had been rejected; (2) Newton was required to award the electrical subcontract to Annese under G. L. c. 149, § 44F (4) (c); (3) Newton’s sole and impermissible purpose for resoliciting electrical subbids was to obtain a lower price; and (4) the decision of the Attorney General that Newton’s resolicitation was contrary to law was not given appropriate weight. The plaintiff further claims it is entitled to damages in the form of bid preparation costs or lost profits. We transferred this case from the Appeals Court on our own motion. We affirm.

1. Background facts. We summarize the material facts which are undisputed and present only a question of law.2 On May 8, 1995, Newton invited general contractors and subcontractors to bid on a project to renovate and make additions to Newton South High Scho(ol (project). The project required general construction work as well as work in numerous sub trades, including electrical. Newton had estimated the cost of the proposed electrical work to be $487,000. In accordance with G. L. c. 149, §§ 44A-44H, Newton invited electrical subcontractors to submit bids for the work by May 31, 1995. On that date, Newton opened five filed electrical subbids3 with the following prices:

[765]*765 Company Base Bid
Campbell Electric, Inc. $496,000
The Sentry Corporation $620,000
James Galvin Electrical Contracting Corp. $675,000
Annese Electrical Services, Inc. $855,000
CNM Electrical Construction, Inc. $883,000

The bids, including limitations as to use by general contractors, were placed on a list and sent to “every person on record as having taken a set of plans and specifications,” conformably with G. L. c. 149, § 44F (3).

On June 14, 1995, the general bids were opened. Later that day Campbell Electric, Inc. (Campbell), and James Galvin Electrical Contracting Corp. notified Newton that they had made errors in their bid calculations and requested withdrawal of their bids. Newton determined that each subcontractor had made a bona fide clerical error of a substantial nature in its bid and returned their bid deposits.4

On July 7, 1995, Newton awarded5 the general contract to TLT Construction Corporation (TLT). In its award letter to TLT, Newton followed the procedure set out in G. L. c. 149, § 44F (4) (c), and adjusted TLT’s bid price to reflect the substitution of The Sentry Corporation (Sentry) for Campbell, which had been named in TLT’s original bid.6 On July 13, 1995, Sentry requested permission to withdraw its bid because of a clerical error. Its bid deposit [766]*766was returned after Newton determined that Sentry had made a bona fide clerical error of a substantial nature in its bid. As a consequence, there remained only two filed electrical subbids: Annese at $855,000 and CNM Electrical Construction, Inc. (CNM), at $883,000. The remaining bids were significantly higher than the $487,000 Newton had estimated for the electrical work. Due to the substantial difference in price between the remaining bids and Newton’s cost estimate, Newton deemed the bids uneconomical without further competition, and on August 4, 1995, invited electrical subcontractors to bid on the project again. The second set of bid documents was restructured so that part of the original scope of work was set out as an alternate, giving Newton the option whether to proceed with the additional work.

On August 10, 1995, Newton and TLT executed the general contract, which contained a clause stating that Sentry was entitled by statute to withdraw its bid, that Newton intended to rebid the electrical work, and that the parties agreed to amend the contract to reflect the bid price of the lowest responsible and eligible electrical subbidder in the second round of bidding. On August 21, 1995, the second round of electrical subbids were opened, the results of which were as follows:

Company Base Bid
CNM Electrical Construction, Inc. $663,000
Annese Electrical Services, Inc. $696,000
James Galvin Electrical Contracting Corp. $805,000

In the interim, on August 11, 1995, Annese protested the second solicitation for electrical work to the Commissioner of Labor and Industries (commissioner), pursuant to G. L. c. 149, § 44H. The protest was heard by the Attorney General, the commissioner’s designee.7 On September 6, 1995, the Attorney General concluded that Newton’s second solicitation of electrical subbids was a violation of the public bidding laws.8 Notwithstanding the decision of the Attorney General, and with Newton’s approval, TLT executed a subcontract with CNM, [767]*767which subsequently performed and completed the electrical work.9

2. Overview. General Laws c. 149, §§ 44A-44H, is known as the competitive bidding statute. It provides comprehensive and detailed requirements for public agencies that award building contracts estimated to cost more than $25,000. G. L. c. 149, § 44A (2). “We construe G. L. c. 149, §§ 44A-44[H], as we must, in light of the legislative objectives which were served by its enactment so as to effectuate the purpose of the framers.” John T. Callahan & Sons v. Malden, 430 Mass. 124, 128 (1999), quoting Interstate Eng’g Corp. v. Fitchburg, 367 Mass. 751, 757 (1975)." The purposes of the competitive bidding statute are “to ensure that the awarding authority obtain the lowest price among responsible contractors” and “to establish an open and honest procedure for competition for public contracts.” John T. Callahan & Sons v. Malden, supra, quoting Modern Cont. Constr. Co. v. Lowell, 391 Mass. 829, 840 (1984), and James J. Welch & Co. v. Deputy Comm’r of Capital Planning & Operations, 387 Mass. 662, 666 (1982). The statute “places all general contractors and subbidders on an equal footing in the competition to gain the contract.” John T. Callahan & Sons v. Malden, supra. Interstate Eng’g Corp. v. Fitchburg, supra at 757-758. “The statutory procedure facilitates the elimination of favoritism and corruption as factors in the awarding of public contracts and emphasizes the part which efficient, low-cost operation should play in winning public contracts.” John T. Callahan & Sons v. Malden, supra. Interstate Eng’g Corp. v. Fitchburg, supra.

3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HAVERHILL STEM LLC v. JAMES J. FIORENTINI & Another
Massachusetts Superior Court, 2024
McCormick v. Mass. Bay Transp. Auth.
95 N.E.3d 298 (Massachusetts Appeals Court, 2017)
Net Technologies, Inc. v. Massachusetts Department of Transportation
33 Mass. L. Rptr. 344 (Massachusetts Superior Court, 2016)
Goduti v. City of Worcester
31 N.E.3d 70 (Massachusetts Appeals Court, 2015)
Flaherty v. Sheriff of Suffolk County
26 N.E.3d 1124 (Massachusetts Appeals Court, 2015)
Brait Builders Corp. v. Town of Hingham
28 Mass. L. Rptr. 445 (Massachusetts Superior Court, 2010)
Fordyce v. Town of Hanover
457 Mass. 248 (Massachusetts Supreme Judicial Court, 2010)
Brasi Development Corp. v. Attorney General
925 N.E.2d 826 (Massachusetts Supreme Judicial Court, 2010)
Cape Cod Builders, Inc. v. Commonwealth
25 Mass. L. Rptr. 571 (Massachusetts Superior Court, 2009)
Seideman v. City of Newton
23 Mass. L. Rptr. 274 (Massachusetts Superior Court, 2007)
Molly A. v. Commissioner of the Department of Mental Retardation
867 N.E.2d 350 (Massachusetts Appeals Court, 2007)
Taylor v. Burke
866 N.E.2d 911 (Massachusetts Appeals Court, 2007)
McCoy v. Town of Kingston
864 N.E.2d 1251 (Massachusetts Appeals Court, 2007)
Aaron v. Boston Redevelopment Authority
850 N.E.2d 1105 (Massachusetts Appeals Court, 2006)
Mammoet Usa, Inc. v. Entergy Nuclear Generation Co.
831 N.E.2d 349 (Massachusetts Appeals Court, 2005)
Massachusetts Insurers Insolvency Fund v. Safety Insurance Co.
19 Mass. L. Rptr. 521 (Massachusetts Superior Court, 2005)
Audette v. Commonwealth
829 N.E.2d 248 (Massachusetts Appeals Court, 2005)
Breneman v. Massachusetts Aeronautics Commission
17 Mass. L. Rptr. 485 (Massachusetts Superior Court, 2004)
Town of Holden v. Wachusett Regional School District Committee
16 Mass. L. Rptr. 112 (Massachusetts Superior Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
730 N.E.2d 290, 431 Mass. 763, 2000 Mass. LEXIS 360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/annese-electrical-services-inc-v-city-of-newton-mass-2000.