Petricca Construction Co. v. Commonwealth

640 N.E.2d 780, 37 Mass. App. Ct. 392, 1994 Mass. App. LEXIS 898
CourtMassachusetts Appeals Court
DecidedOctober 5, 1994
DocketNo. 93-P-75
StatusPublished
Cited by31 cases

This text of 640 N.E.2d 780 (Petricca Construction Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petricca Construction Co. v. Commonwealth, 640 N.E.2d 780, 37 Mass. App. Ct. 392, 1994 Mass. App. LEXIS 898 (Mass. Ct. App. 1994).

Opinions

Greenberg, J.

In Modern Continental Constr. Co. v. Lowell, 391 Mass. 829, 840 (1984), the court, examining G. L. c. 30, § 39M,1 and G. L. c. 149, §§ 44A-44H, stated that “the purpose of competitive bidding statutes is not only to ensure that the awarding authority obtain the lowest price among responsible contractors, but also to establish an open and honest procedure for competition for public contracts.” The question now presented is whether there is found in § 39M a power of awarding authorities to recapture the benefit of a lower bid that was properly rejected for noncompliance with the bidding procedures. We conclude that § 39M does not contain such a prerogative and that the Commonwealth, acting through the board of commissioners of its Highway Department (department), was mistaken when it decided to rebid a “public works” contract.2

1. Prior proceedings. We digress to explain the procedural posture under which we have considered the appeal. At the bid opening on February 19, 1992, Gagliarducci Construction Corp. was the apparent low bidder and the plaintiff, Petricca Construction Company, the third lowest among the five bids submitted. Because of an error in arithmetic in the Gagliarducci bid, and a potential “pricing” problem with the [394]*394bid of E.T. & L. Construction Corp., the second lowest bidder, the department rejected all bids and decided to readvertise the contract. A protest was filed by E.T. & L. Construction with the Department of Labor and Industries (DOLI), on May 12, 1992. Under G. L. c. 149, § 44H, the commissioner of DOLI is empowered by the Legislature to “enforce” the competitive bidding laws. Concerning this power we stated in Doric Bldg. Assocs. v. Department of Labor & Indus., 27 Mass. App. Ct. 1175, 1177 (1989), that DOLI “has general authority to see that the bidding system of c. 149 is carried out faithfully.” We also noted that DOLI has no enforcement power when it finds a violation, but may commence an action in the Superior Court when it spots an error.

Following an investigation DOLI agreed with the department that the bid of Gagliarducci had a computational error which caused it to become the second lowest bidder. DOLI found substantive defects in E.T. & L.’s bid as well. As the department acknowledged that Petricca’s bid was in order, it became the lowest, eligible bid. However, on account of purported concerns over potential delay of the project and the threat of litigation by all bidders, the department chose instead, to readvertise, rather than following the DOLI’s administrative decision awarding the contract to Petricca.

This action was commenced on June 5, 1992, by Petricca, as an application for preliminary injunction to require the department to comply with DOLFs decision. After hearing on June 16, 1992, a judge of the Superior Court enjoined the department from rebidding or awarding the contract to any party other than Petricca. On a petition of the department to this court seeking relief under G. L. c. 231, § 118, first par., a single justice ordered that the injunction be dissolved and this appeal ensued. The rebidding process, meanwhile, continued apace. On August 4, 1992, the department awarded the contract to Gagliarducci, and construction began on September 28, 1992.

2. Mootness and standard of review. Ordinarily, we review the single justice’s order “in the same manner as if it were an [395]*395identical order by the trial judge considering the matter in the first instance.” Jet-Line Servs., Inc. v. Selectmen of Stoughton, 25 Mass. App. Ct. 645, 646 (1988). Thus we ask whether the single justice abused his discretion by entering an order without having a supportable basis for doing so. See Carabetta Enterprises, Inc. v. Schena, 25 Mass. App. Ct. 389, 392 (1988). Here, the public construction has been started and the aggrieved party failed to move for an expedited appeal. The threshold question posed by the department is whether the matter is moot.

Even though the requested injunctive relief is now academic, Petricca does have a continuing interest in pursuing a judgment against the department for bid preparation costs. See Paul Sardella Constr. Co. v. Braintree Hous. Authy., 371 Mass. 235, 243 (1976). More significantly, “we have on occasion answered questions in moot cases where the issue was one of public importance, where it was fully argued on both sides, where the question was certain, or at least very likely, to arise again in similar factual circumstances, and especially where appellate review could not be obtained before the recurring question would again be moot.” Lockhart v. Attorney Gen., 390 Mass. 780, 783 (1984). See Sciaba Constr. Corp. v. Boston, 35 Mass. App. Ct. 181, 185 (1993). Cf. Grande & Son, Inc. v. School Hous. Comm, of North Reading, 334 Mass. 252, 259 (1956). Because of the significance of the question to the public and because the facts as developed permit us to do so, we have decided the ultimate question: whether the public interest warranted rejection of the original bids.3

3. Interpretation of G. L. c. 30, § 39M. Section 39M of the act provides that the “awarding authority may reject any and all bids, if it is in the public interest to do so.” Some courts in other jurisdictions have clearly defined the meaning of “public interest” within the context of their public bidding statutes to mean guarding “against favoritism, improvidence, [396]*396extravagance and corruption.” Morie Energy Mgmt., Inc. v. Badame, 241 N.J. Super. 572, 576 (1990), quoting from Hillside Township v. Sternin, 25 N.J. 317, 322 (1957). See Conduit & Foundation Corp. v. Metropolitan Transp. Authy., 66 N.Y.2d 144, 148 (1985); Nelson Inc. of Wis. v. Sewerage Commn. of Milwaukee, 12 Wis. 2d 400, 408 (1976).

Similar objectives are found in this State’s scheme. Read in conjunction with G. L. c. 149, §§ 44-44M, the legislative goals of § 39M are two-fold. First, to create an open and honest competition with all bidders on an equal footing. Interstate Engr. Corp. v. Fitchburg, 367 Mass. 751, 758 (1975). Absent such a restriction, an awarding authority would be free to rebid a contract until a preferred bidder submitted the lowest bid price, and thwart one of the important legislative goals. See Cardell, Inc. v. Wood-bridge, 115 N.J. Super. 442, 450 (1971). Second, § 39M enables the public contracting authority to obtain the lowest eligible bidder. Interstate Engr. Corp. v. Fitchburg, supra at 757. In reviewing the conduct of awarding authorities in regard to bid protests, we think equal weight should be given to the two stated purposes of the statute. While there is no Massachusetts case directly on the point, other courts have made clear that awarding authorities may not reject bids simply to obtain a lower price. See Superior Oil Co. v. Secretary of the Interior, 409 F.2d 1115, 1120 (D.C. Cir. 1969); Caruci v. Dulan, 41 Misc. 2d 859, 864 (1964), rev’d on other grounds, 24 A.D.2d 529 (N.Y. 1965). Cf. Grande & Son, Inc. v. School Hous. Comm, of North Quincy, 334 Mass. at 258.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Adoption Gemma
113 N.E.3d 934 (Massachusetts Appeals Court, 2018)
A.L. Prime Energy Consultant, Inc. v. Mass. Bay Transportation Authority
95 N.E.3d 547 (Massachusetts Supreme Judicial Court, 2018)
Bos. Globe Media Partners, LLC v. Dep't of State Police
94 N.E.3d 878 (Massachusetts Appeals Court, 2017)
Penebre v. Kurland
33 Mass. L. Rptr. 621 (Massachusetts Superior Court, 2016)
A.R.S. Services, Inc. v. Morse
31 Mass. L. Rptr. 227 (Massachusetts Superior Court, 2013)
Doe v. Superintendent of Schools of Weston
461 Mass. 159 (Massachusetts Supreme Judicial Court, 2011)
E.H. Perkins Construction, Inc. v. Town of Lincoln
936 N.E.2d 890 (Massachusetts Appeals Court, 2010)
Opare's Case
932 N.E.2d 863 (Massachusetts Appeals Court, 2010)
BNY Mellon, N.A. v. Schauer
27 Mass. L. Rptr. 329 (Massachusetts Superior Court, 2010)
Don v. Soo Hoo
912 N.E.2d 18 (Massachusetts Appeals Court, 2009)
Love v. Pratt
833 N.E.2d 674 (Massachusetts Appeals Court, 2005)
Casavant v. Norwegian Cruise Line, Ltd.
829 N.E.2d 1171 (Massachusetts Appeals Court, 2005)
Aspinall v. Philip Morris Companies, Inc.
442 Mass. 381 (Massachusetts Supreme Judicial Court, 2004)
E. Amanti & Sons, Inc. v. R.C. Griffin, Inc.
758 N.E.2d 153 (Massachusetts Appeals Court, 2001)
J.F. White Contracting Co. v. Massachusetts Port Authority
748 N.E.2d 1020 (Massachusetts Appeals Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
640 N.E.2d 780, 37 Mass. App. Ct. 392, 1994 Mass. App. LEXIS 898, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petricca-construction-co-v-commonwealth-massappct-1994.