Revoli Construction Co., Inc. v. City of Worcester.

Massachusetts Appeals Court·Decided May 8, 2026·No. 24-P-1215·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

24-P-1215

REVOLI CONSTRUCTION CO., INC.

vs.

CITY OF WORCESTER.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

Revoli Construction Co., Inc. (Revoli) brought this action

against the city of Worcester (city), alleging that the city

violated the public bidding laws, G. L. c. 30, § 39M, in bad

faith by rejecting Revoli's bid for the Route 20 sewer extension

project in that city (project). Following a trial in the

Superior Court, a jury found that the city acted in bad faith

and awarded Revoli $3 million in lost profits. On appeal, the

city argues that (1) the trial judge should have instructed the

jury on the presumption of good faith, (2) the trial judge erred

in denying the city's motions for a directed verdict and a

judgment notwithstanding the verdict, and (3) the evidence at

trial was insufficient to support the damages award of $3 million in lost profits. We affirm.

Background. In reviewing a judgment notwithstanding the verdict, "we consider the facts and inferences therefrom in the light most favorable to the plaintiff to determine if 'anywhere in the evidence, from whatever source derived, any combination of circumstances could be found from which a reasonable inference could be drawn in favor of the plaintiff.'" Phelan v. May Dep't Stores Co., 60 Mass. App. Ct. 843, 844 (2004), quoting Stapleton v. Macchi, 401 Mass. 725, 728 (1988). We recite the facts in that light, reserving certain details for discussion of specific issues.

In August 2017, Revoli submitted a bid for the project.

Mark Elbag, the city's director of engineering, and Antonio da Cruz, a vice-president at Tighe & Bond, Inc. (Tighe & Bond), an engineering firm,1 were present at the bid opening for the project. Though neither Elbag nor da Cruz had firsthand experience with Revoli they had a conversation at the bid opening in which at least one of them raised concerns about Revoli's being difficult to work with.2

Revoli was the low bidder on the project. That same morning, Elbag sent an e-mail message to Paul Moosey, the city's commissioner of public works and parks, to inform him that Revoli was the low bidder. Moosey, who also had no firsthand experience with Revoli, responded, "What else for bad news." Later that day, da Cruz emailed his colleagues at Tighe & Bond, writing that the "[c]ity doesn't want Revoli so we're going to inquire about Chicopee's approach to baring [sic] them."

Following these communications, Tighe & Bond began its review process, which involved contacting cities and towns that the bidders had previously worked with, filling out evaluation forms, and drafting a recommendation letter to Moosey. The city requested that the recommendation letter evaluate the bid information for the three low bidders, which were Revoli, P. Gioioso & Sons, Inc. (Gioioso), and RJV Construction Corp. (RJV). Tighe & Bond's recommendation letter ultimately concluded that "Revoli has not demonstrated that they are the lowest responsible and eligible bidder." More specifically, the letter opined that Revoli did not have the requisite experience and ability to complete a construction contract as large as the project. The recommendation letter also summarized Revoli's

construction process." Da Cruz testified that Elbag "voiced concerns about Revoli."

reference evaluations and found that "many contacted references indicated a propensity to excessive change orders, unreasonable change order requests, litigation and some would not recommend Revoli for a project with difficult construction." Notably, the recommendation letter contained no negative reference information about the second and third lowest bidders -- Gioioso and RJV.

After Tighe & Bonde completed its review, Moosey recommended to the city manager that he reject Revoli's bid and award the project to Gioioso, which the city manager did.

Discussion. 1. Jury instruction on presumption of good faith. The city first argues that the trial judge erred by not instructing the jury on the presumption of good faith and by not applying the presumption in his denial of the city's motions for a directed verdict and judgment notwithstanding the verdict. We disagree.

"When reviewing jury instructions to which there has been an objection, we conduct a two-part test: whether the instructions were legally erroneous, and (if so) whether that error was prejudicial" (quotation and citation omitted). Main v. R.J. Reynolds Tobacco Co., 100 Mass. App. Ct. 827, 834 (2022). "In examining whether an instruction adequately explain[s] the applicable law, we consider the adequacy of the instructions as a whole" (quotations and citations omitted).

Governo Law Firm LLC v. Bergeron, 487 Mass. 188, 194 (2021). "An error in jury instructions is not grounds for setting aside a verdict . . . unless the result might have differed absent the error." Id., quoting Blackstone v. Cashman, 448 Mass. 255, 270 (2007).

To be sure, public officials are presumed to act in good faith. See Nantasket Beachfront Condominiums, LLC v. Hull Redev. Authority, 87 Mass. App. Ct. 455, 464 (2015). But "a presumption, using the word in its technical and proper sense, can have no operative effect unless it assists the party having the burden of proof." Epstein v. Boston Hous. Authority, 317 Mass. 297, 302 (1944).

Here, the presumption of good faith in favor of the city had no operative effect because Revoli always had the burden of proving that the city acted in bad faith. See Modern Cont. Constr. Co. v. Massachusetts Port Authority, 369 Mass. 825, 828 (1976) (bidder bears burden of proving awarding authority "acted in bad faith or in an arbitrary or unreasonable manner"). Instead, the presumption was "merely a restatement that the burden of persuasion . . . from the outset" was on Revoli (quotation and citation omitted). General Elec. Co. v. Assessors of Lynn, 393 Mass. 591, 598 (1984). Thus, it was not

legally erroneous for the trial judge not to instruct the jury on the presumption of good faith.3 2. Motions for directed verdict and judgment notwithstanding the verdict. "The denial of a motion for directed verdict or a motion for judgment notwithstanding the verdict both present questions of law reviewed under the same standard used by the trial judge." O'Brien v. Pearson, 449 Mass. 377, 383 (2007). In reviewing these motions, we "construe the evidence in the light most favorable to the nonmoving party and disregard that favorable to the moving party." Id. "The verdict will be upheld if it may be determined that anywhere in the evidence, from whatever source derived, any combination of circumstances could be found from which a reasonable inference could be drawn in favor of the plaintiff" (quotation and citation omitted). Sullivan v. Five Acres Realty Trust, 487 Mass. 64, 68 (2021).

Free access — add to your briefcase to read the full text and ask questions with AI

Revoli Construction Co., Inc. v. City of Worcester., (Mass. Ct. App. 2026).

Revoli Construction Co., Inc. v. City of Worcester. (Revoli Construction Co., Inc. v. City of Worcester.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Interstate Engineering Corp. v. City of Fitchburg
329 N.E.2d 128 (Massachusetts Supreme Judicial Court, 1975)
Blake v. Commissioner of Correction
532 N.E.2d 671 (Massachusetts Supreme Judicial Court, 1989)
Stapleton v. MacChi
519 N.E.2d 273 (Massachusetts Supreme Judicial Court, 1988)
Pheasant Ridge Associates Ltd. Partnership v. Town of Burlington
506 N.E.2d 1152 (Massachusetts Supreme Judicial Court, 1987)
Modern Continental Construction Co. v. Massachusetts Port Authority
343 N.E.2d 362 (Massachusetts Supreme Judicial Court, 1976)
Nantasket Beachfront Condominiums, LLC v. Hull Redevelopment Authority
32 N.E.3d 318 (Massachusetts Appeals Court, 2015)
Buffalo-Water 1, LLC v. Fidelity Real Estate Company, LLC
111 N.E.3d 266 (Massachusetts Supreme Judicial Court, 2018)
Spiegel v. Beacon Participations, Inc.
8 N.E.2d 895 (Massachusetts Supreme Judicial Court, 1937)
Epstein v. Boston Housing Authority
58 N.E.2d 135 (Massachusetts Supreme Judicial Court, 1944)
General Electric Co. v. Board of Assessors
472 N.E.2d 1329 (Massachusetts Supreme Judicial Court, 1984)
Ayash v. Dana-Farber Cancer Institute
822 N.E.2d 667 (Massachusetts Supreme Judicial Court, 2005)
Blackstone v. Cashman
860 N.E.2d 7 (Massachusetts Supreme Judicial Court, 2007)
O'Brien v. Pearson
868 N.E.2d 118 (Massachusetts Supreme Judicial Court, 2007)
Baudanza v. Comcast of Massachusetts I, Inc.
912 N.E.2d 458 (Massachusetts Supreme Judicial Court, 2009)
Fordyce v. Town of Hanover
457 Mass. 248 (Massachusetts Supreme Judicial Court, 2010)
Petricca Construction Co. v. Commonwealth
640 N.E.2d 780 (Massachusetts Appeals Court, 1994)
Northeast Reclamation Corp. v. Town of Wareham
766 N.E.2d 560 (Massachusetts Appeals Court, 2002)
Phelan v. May Department Stores Co.
806 N.E.2d 939 (Massachusetts Appeals Court, 2004)
Brewster Wallcovering Co. v. Blue Mountain Wallcoverings, Inc.
864 N.E.2d 518 (Massachusetts Appeals Court, 2007)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)