NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
24-P-1215
REVOLI CONSTRUCTION CO., INC.
vs.
CITY OF WORCESTER.
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
Revoli Construction Co., Inc. (Revoli) brought this action
against the city of Worcester (city), alleging that the city
violated the public bidding laws, G. L. c. 30, § 39M, in bad
faith by rejecting Revoli's bid for the Route 20 sewer extension
project in that city (project). Following a trial in the
Superior Court, a jury found that the city acted in bad faith
and awarded Revoli $3 million in lost profits. On appeal, the
city argues that (1) the trial judge should have instructed the
jury on the presumption of good faith, (2) the trial judge erred
in denying the city's motions for a directed verdict and a
judgment notwithstanding the verdict, and (3) the evidence at trial was insufficient to support the damages award of $3
million in lost profits. We affirm.
Background. In reviewing a judgment notwithstanding the
verdict, "we consider the facts and inferences therefrom in the
light most favorable to the plaintiff to determine if 'anywhere
in the evidence, from whatever source derived, any combination
of circumstances could be found from which a reasonable
inference could be drawn in favor of the plaintiff.'" Phelan v.
May Dep't Stores Co., 60 Mass. App. Ct. 843, 844 (2004), quoting
Stapleton v. Macchi, 401 Mass. 725, 728 (1988). We recite the
facts in that light, reserving certain details for discussion of
specific issues.
In August 2017, Revoli submitted a bid for the project.
Mark Elbag, the city's director of engineering, and Antonio da
Cruz, a vice-president at Tighe & Bond, Inc. (Tighe & Bond), an
engineering firm,1 were present at the bid opening for the
project. Though neither Elbag nor da Cruz had firsthand
experience with Revoli they had a conversation at the bid
opening in which at least one of them raised concerns about
Revoli's being difficult to work with.2
1 The city hired Tighe & Bond to act as an engineer for the project. Tighe & Bond's duties included evaluating the bids the city received.
2 Elbag testified that da Cruz told him that "[h]e had concerns about Revoli," related to "general trouble through the
2 Revoli was the low bidder on the project. That same
morning, Elbag sent an e-mail message to Paul Moosey, the city's
commissioner of public works and parks, to inform him that
Revoli was the low bidder. Moosey, who also had no firsthand
experience with Revoli, responded, "What else for bad news."
Later that day, da Cruz emailed his colleagues at Tighe & Bond,
writing that the "[c]ity doesn't want Revoli so we're going to
inquire about Chicopee's approach to baring [sic] them."
Following these communications, Tighe & Bond began its
review process, which involved contacting cities and towns that
the bidders had previously worked with, filling out evaluation
forms, and drafting a recommendation letter to Moosey. The city
requested that the recommendation letter evaluate the bid
information for the three low bidders, which were Revoli, P.
Gioioso & Sons, Inc. (Gioioso), and RJV Construction Corp.
(RJV). Tighe & Bond's recommendation letter ultimately
concluded that "Revoli has not demonstrated that they are the
lowest responsible and eligible bidder." More specifically, the
letter opined that Revoli did not have the requisite experience
and ability to complete a construction contract as large as the
project. The recommendation letter also summarized Revoli's
construction process." Da Cruz testified that Elbag "voiced concerns about Revoli."
3 reference evaluations and found that "many contacted references
indicated a propensity to excessive change orders, unreasonable
change order requests, litigation and some would not recommend
Revoli for a project with difficult construction." Notably, the
recommendation letter contained no negative reference
information about the second and third lowest bidders -- Gioioso
and RJV.
After Tighe & Bonde completed its review, Moosey
recommended to the city manager that he reject Revoli's bid and
award the project to Gioioso, which the city manager did.
Discussion. 1. Jury instruction on presumption of good
faith. The city first argues that the trial judge erred by not
instructing the jury on the presumption of good faith and by not
applying the presumption in his denial of the city's motions for
a directed verdict and judgment notwithstanding the verdict. We
disagree.
"When reviewing jury instructions to which there has been
an objection, we conduct a two-part test: whether the
instructions were legally erroneous, and (if so) whether that
error was prejudicial" (quotation and citation omitted). Main
v. R.J. Reynolds Tobacco Co., 100 Mass. App. Ct. 827, 834
(2022). "In examining whether an instruction adequately
explain[s] the applicable law, we consider the adequacy of the
instructions as a whole" (quotations and citations omitted).
4 Governo Law Firm LLC v. Bergeron, 487 Mass. 188, 194 (2021).
"An error in jury instructions is not grounds for setting aside
a verdict . . . unless the result might have differed absent the
error." Id., quoting Blackstone v. Cashman, 448 Mass. 255, 270
(2007).
To be sure, public officials are presumed to act in good
faith. See Nantasket Beachfront Condominiums, LLC v. Hull
Redev. Authority, 87 Mass. App. Ct. 455, 464 (2015). But "a
presumption, using the word in its technical and proper sense,
can have no operative effect unless it assists the party having
the burden of proof." Epstein v. Boston Hous. Authority, 317
Mass. 297, 302 (1944).
Here, the presumption of good faith in favor of the city
had no operative effect because Revoli always had the burden of
proving that the city acted in bad faith. See Modern Cont.
Constr. Co. v. Massachusetts Port Authority, 369 Mass. 825, 828
(1976) (bidder bears burden of proving awarding authority "acted
in bad faith or in an arbitrary or unreasonable manner").
Instead, the presumption was "merely a restatement that the
burden of persuasion . . . from the outset" was on Revoli
(quotation and citation omitted). General Elec. Co. v.
Assessors of Lynn, 393 Mass. 591, 598 (1984). Thus, it was not
5 legally erroneous for the trial judge not to instruct the jury
on the presumption of good faith.3
2. Motions for directed verdict and judgment
notwithstanding the verdict.
Free access — add to your briefcase to read the full text and ask questions with AI
NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
24-P-1215
REVOLI CONSTRUCTION CO., INC.
vs.
CITY OF WORCESTER.
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
Revoli Construction Co., Inc. (Revoli) brought this action
against the city of Worcester (city), alleging that the city
violated the public bidding laws, G. L. c. 30, § 39M, in bad
faith by rejecting Revoli's bid for the Route 20 sewer extension
project in that city (project). Following a trial in the
Superior Court, a jury found that the city acted in bad faith
and awarded Revoli $3 million in lost profits. On appeal, the
city argues that (1) the trial judge should have instructed the
jury on the presumption of good faith, (2) the trial judge erred
in denying the city's motions for a directed verdict and a
judgment notwithstanding the verdict, and (3) the evidence at trial was insufficient to support the damages award of $3
million in lost profits. We affirm.
Background. In reviewing a judgment notwithstanding the
verdict, "we consider the facts and inferences therefrom in the
light most favorable to the plaintiff to determine if 'anywhere
in the evidence, from whatever source derived, any combination
of circumstances could be found from which a reasonable
inference could be drawn in favor of the plaintiff.'" Phelan v.
May Dep't Stores Co., 60 Mass. App. Ct. 843, 844 (2004), quoting
Stapleton v. Macchi, 401 Mass. 725, 728 (1988). We recite the
facts in that light, reserving certain details for discussion of
specific issues.
In August 2017, Revoli submitted a bid for the project.
Mark Elbag, the city's director of engineering, and Antonio da
Cruz, a vice-president at Tighe & Bond, Inc. (Tighe & Bond), an
engineering firm,1 were present at the bid opening for the
project. Though neither Elbag nor da Cruz had firsthand
experience with Revoli they had a conversation at the bid
opening in which at least one of them raised concerns about
Revoli's being difficult to work with.2
1 The city hired Tighe & Bond to act as an engineer for the project. Tighe & Bond's duties included evaluating the bids the city received.
2 Elbag testified that da Cruz told him that "[h]e had concerns about Revoli," related to "general trouble through the
2 Revoli was the low bidder on the project. That same
morning, Elbag sent an e-mail message to Paul Moosey, the city's
commissioner of public works and parks, to inform him that
Revoli was the low bidder. Moosey, who also had no firsthand
experience with Revoli, responded, "What else for bad news."
Later that day, da Cruz emailed his colleagues at Tighe & Bond,
writing that the "[c]ity doesn't want Revoli so we're going to
inquire about Chicopee's approach to baring [sic] them."
Following these communications, Tighe & Bond began its
review process, which involved contacting cities and towns that
the bidders had previously worked with, filling out evaluation
forms, and drafting a recommendation letter to Moosey. The city
requested that the recommendation letter evaluate the bid
information for the three low bidders, which were Revoli, P.
Gioioso & Sons, Inc. (Gioioso), and RJV Construction Corp.
(RJV). Tighe & Bond's recommendation letter ultimately
concluded that "Revoli has not demonstrated that they are the
lowest responsible and eligible bidder." More specifically, the
letter opined that Revoli did not have the requisite experience
and ability to complete a construction contract as large as the
project. The recommendation letter also summarized Revoli's
construction process." Da Cruz testified that Elbag "voiced concerns about Revoli."
3 reference evaluations and found that "many contacted references
indicated a propensity to excessive change orders, unreasonable
change order requests, litigation and some would not recommend
Revoli for a project with difficult construction." Notably, the
recommendation letter contained no negative reference
information about the second and third lowest bidders -- Gioioso
and RJV.
After Tighe & Bonde completed its review, Moosey
recommended to the city manager that he reject Revoli's bid and
award the project to Gioioso, which the city manager did.
Discussion. 1. Jury instruction on presumption of good
faith. The city first argues that the trial judge erred by not
instructing the jury on the presumption of good faith and by not
applying the presumption in his denial of the city's motions for
a directed verdict and judgment notwithstanding the verdict. We
disagree.
"When reviewing jury instructions to which there has been
an objection, we conduct a two-part test: whether the
instructions were legally erroneous, and (if so) whether that
error was prejudicial" (quotation and citation omitted). Main
v. R.J. Reynolds Tobacco Co., 100 Mass. App. Ct. 827, 834
(2022). "In examining whether an instruction adequately
explain[s] the applicable law, we consider the adequacy of the
instructions as a whole" (quotations and citations omitted).
4 Governo Law Firm LLC v. Bergeron, 487 Mass. 188, 194 (2021).
"An error in jury instructions is not grounds for setting aside
a verdict . . . unless the result might have differed absent the
error." Id., quoting Blackstone v. Cashman, 448 Mass. 255, 270
(2007).
To be sure, public officials are presumed to act in good
faith. See Nantasket Beachfront Condominiums, LLC v. Hull
Redev. Authority, 87 Mass. App. Ct. 455, 464 (2015). But "a
presumption, using the word in its technical and proper sense,
can have no operative effect unless it assists the party having
the burden of proof." Epstein v. Boston Hous. Authority, 317
Mass. 297, 302 (1944).
Here, the presumption of good faith in favor of the city
had no operative effect because Revoli always had the burden of
proving that the city acted in bad faith. See Modern Cont.
Constr. Co. v. Massachusetts Port Authority, 369 Mass. 825, 828
(1976) (bidder bears burden of proving awarding authority "acted
in bad faith or in an arbitrary or unreasonable manner").
Instead, the presumption was "merely a restatement that the
burden of persuasion . . . from the outset" was on Revoli
(quotation and citation omitted). General Elec. Co. v.
Assessors of Lynn, 393 Mass. 591, 598 (1984). Thus, it was not
5 legally erroneous for the trial judge not to instruct the jury
on the presumption of good faith.3
2. Motions for directed verdict and judgment
notwithstanding the verdict. "The denial of a motion for
directed verdict or a motion for judgment notwithstanding the
verdict both present questions of law reviewed under the same
standard used by the trial judge." O'Brien v. Pearson, 449
Mass. 377, 383 (2007). In reviewing these motions, we "construe
the evidence in the light most favorable to the nonmoving party
and disregard that favorable to the moving party." Id. "The
verdict will be upheld if it may be determined that anywhere in
the evidence, from whatever source derived, any combination of
circumstances could be found from which a reasonable inference
could be drawn in favor of the plaintiff" (quotation and
citation omitted). Sullivan v. Five Acres Realty Trust, 487
Mass. 64, 68 (2021).
3 Because Revoli's burden was unaffected by the presumption of good faith, we also reject the city's argument that the trial judge erred by not applying the presumption in his review of the city's motions for a directed verdict and judgment notwithstanding the verdict. The trial judge only had to determine whether, in the light most favorable to Revoli, there was sufficient evidence for the jury to draw a reasonable inference that the city acted in bad faith. See O'Brien v. Pearson, 449 Mass. 377, 383-384 (2007). As discussed infra, the evidence was sufficient for the jury to find bad faith.
6 "Bad faith is a 'general and somewhat indefinite term' that
goes beyond 'bad judgment' or 'negligence,' suggesting 'a
dishonest purpose or some moral obliquity,' a 'conscious doing
of wrong,' or a 'breach of a known duty through some motive of
interest or ill will.'" Buffalo-Water 1, LLC v. Fidelity Real
Estate Co., LLC, 481 Mass. 13, 25-26 (2018), quoting Spiegel v.
Beacon Participations, Inc., 297 Mass. 398, 416 (1937). "In the
context of State action, [bad faith] includes the use of an
otherwise lawful power for an improper purpose." Judge
Rotenberg Educ. Ctr., Inc. v. Commissioner of the Dep't of
Developmental Servs., 492 Mass. 772, 790 (2023). See Pheasant
Ridge Assocs. Ltd. Partnership v. Burlington, 399 Mass. 771,
777-780 (1987) (taking of land for public park pursuant to town
meeting vote was invalid where manifest purpose behind taking
was to block low or moderate income housing); Northeast
Reclamation Corp. v. Wareham, 54 Mass. App. Ct. 564, 566 (2002)
(jury's finding of bad faith supported by evidence of "town's
pretextual rejection of the plaintiff's bid because of threats
of litigation made by an ineligible bidder").
The public bidding laws establish "an honest and open
procedure for competition for public contracts and, in so doing,
places all general contractors and subbidders on an equal
footing in the competition to gain the contract." Interstate
Eng'g Corp. v. Fitchburg, 367 Mass. 751, 758 (1975). "[A]n
7 essential element of the equal footing principle not only
requires that bidders have the opportunity to bid in the same
way, but mandates that bidders bear the same risk of rejection"
(emphasis added; quotation and citation omitted). Petricca
Constr. Co. v. Commonwealth, 37 Mass. App. Ct. 392, 397 (1994).4
Here, in the light most favorable to Revoli, there was
ample evidence from which the jury could infer that the city
acted in bad faith in rejecting Revoli's bid. First, at the
time of the bid opening, neither Moosey nor Elbag nor da Cruz
had firsthand experience with Revoli. Second, just hours after
bids were opened, da Cruz sent an e-mail message to his
colleagues at Tighe & Bond stating that the "[c]ity doesn't want
Revoli so we're going to inquire about Chicopee's approach to
baring [sic] them," and that Moosey wanted Tighe & Bond "to look
into the possibility of throwing out Revoli." Moosey also left
a voice message for the vice-president of another engineering
firm, saying that "he has heard Revoli is a poor contractor and
wanted some references to call so he could build a case to
reject them." Third, Tighe & Bond omitted from its
4 In arguing that the city did not act in bad faith, the city relies on bid protest decisions from the Attorney General, but these decisions "carry no precedential weight" because "they arise from the Attorney General's prosecutorial, rather than her adjudicative, function." Fordyce v. Hanover, 457 Mass. 248, 257 (2010).
8 recommendation letter several positive reviews it received for
Revoli while highlighting negative reviews it received for
Revoli.5 Tighe & Bond's recommendation letter also did not
mention that Gioioso had twenty-two Occupational Safety and
Health Administration violations from 2007 to 2017, whereas
Revoli only had two violations in that same time period.
In the light most favorable to Revoli, the jury could have
reasonably concluded that the city did not want to award Revoli
the project, and that the city acted in bad faith by putting its
thumb on the scale of the bid review process to ensure that
Revoli would not be awarded the project. Regardless of whether
the city's concerns about Revoli were genuine, the jury could
conclude that it was an affront to the public bidding laws for
the city to use rumor, innuendo, or speculation as a pretext to
disqualify Revoli before the bid review process even began. See
Northeast Reclamation, 54 Mass. App. Ct. at 566.
3. Damages. The city argues that there was insufficient
evidence to support the jury's damages award of $3 million in
lost profits. We are not convinced.
"[T]he allowance of a motion for a new trial based upon an
inadequate or excessive award of damages, and the direction of
5 Elbag and Moosey were involved with the bid review process.
9 an addition or remittitur, rests in the sound discretion of the
judge." Baudanza v. Comcast of Mass. I, Inc., 454 Mass. 622,
630 (2009), quoting Blake v. Commissioner of Correction, 403
Mass. 764, 771 (1989). We apply a "highly deferential" standard
in assessing the evidence supporting a jury's award of damages
and will overturn such an award only if it is "clearly excessive
in relation to what the plaintiff's evidence ha[d] demonstrated
damages to be." Spinosa v. Tufts, 98 Mass. App. Ct. 1, 10
(2020), quoting Ayash v. Dana-Farber Cancer Inst., 443 Mass.
367, 404, cert. denied sub nom. Globe Newspaper Co. v. Ayash,
546 U.S. 927 (2005).
Here, Revoli's principal, Shawqi Alsarabi, testified that
after analyzing the project plans and spending eighteen hours
over two days at the job site to become familiar with it, he
created a spreadsheet to estimate the cost of the project. The
spreadsheet consisted of each individual bid item and the
estimated labor and equipment costs. The spreadsheet also
included indirect overhead costs, which Alsarabi described as
the costs to operate and oversee the project.6 The sum of the
direct and indirect expenses in the spreadsheet amounted to
slightly over $11.3 million. Based on the bid and the
6 Example costs included the bond guaranteeing Revoli would perform the project, a health and safety plan, the field office trailer, and a project superintendent -- among other things.
10 anticipated competition, Alsarabi estimated that a profit figure
of about $4.6 million would give Revoli a competitive price
against other bidders. Alsarabi testified that the $4.6 million
constituted a net profit of forty percent on the project, which
was lower than the profit percentage on three-fourths of
Revoli's completed projects from October 2008 to September 2018.
Adding the anticipated profit to the direct and indirect costs,
Alsarabi calculated a total bid price of $15.9 million.
Both parties also called experts to testify regarding
damages.7 Revoli retained David Ponte, a construction claims
consultant, to review and validate the veracity of Revoli's cost
estimate on the project. Ponte testified that Revoli's cost
estimate was reasonable, and that his independent cost estimate
was around $12.3 million -- or about $1 million more than
Revoli's cost estimate. The city's expert, William McConnell,
testified that a reasonable estimate of Revoli's anticipated
profit on the project was $344,000. Notably, McConnell's cost
estimate also included an additional $600,000 in field
supervision costs.
7 To the extent that the city argues Revoli needed to call an expert to testify regarding its anticipated profits, the city's argument is misplaced. See Spinosa, 98 Mass. App. Ct. at 11 (opinion testimony of small business owner regarding company's value was admissible where owner was sufficiently aware of business's contracts and liabilities).
11 Considered in its totality, and with regard for the highly
deferential standard of review, we conclude that this evidence
was sufficient to allow the jury "to arrive at a reasonably
approximate estimate of damages." Brewster Wallcovering Co. v.
Blue Mountain Wallcoverings, Inc., 68 Mass. App. Ct. 582, 609
(2007). While the jury did not entirely agree with either
Revoli's profit figure of $4.6 million or the city's profit
figure of $344,000, the testimony of Alsarabi, Ponte, and
McConnell provided an "adequate factual basis to support" the
jury's award of $3 million in net profit. Spinosa, 98 Mass.
App. Ct. at 11. Thus, the jury's award of $3 million in lost
profit was not "clearly excessive in relation to what [Revoli's]
evidence ha[d] demonstrated damages to be" (citation omitted).
Spinosa, supra at 10.
Judgment affirmed.
By the Court (Blake, C.J., Henry & Hershfang, JJ.8),
Clerk
Entered: May 8, 2026.
8 The panelists are listed in order of seniority.