Revoli Construction Co., Inc. v. City of Worcester.

CourtMassachusetts Appeals Court
DecidedMay 8, 2026
Docket24-P-1215
StatusUnpublished

This text of Revoli Construction Co., Inc. v. City of Worcester. (Revoli Construction Co., Inc. v. City of Worcester.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Revoli Construction Co., Inc. v. City of Worcester., (Mass. Ct. App. 2026).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

24-P-1215

REVOLI CONSTRUCTION CO., INC.

vs.

CITY OF WORCESTER.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

Revoli Construction Co., Inc. (Revoli) brought this action

against the city of Worcester (city), alleging that the city

violated the public bidding laws, G. L. c. 30, § 39M, in bad

faith by rejecting Revoli's bid for the Route 20 sewer extension

project in that city (project). Following a trial in the

Superior Court, a jury found that the city acted in bad faith

and awarded Revoli $3 million in lost profits. On appeal, the

city argues that (1) the trial judge should have instructed the

jury on the presumption of good faith, (2) the trial judge erred

in denying the city's motions for a directed verdict and a

judgment notwithstanding the verdict, and (3) the evidence at trial was insufficient to support the damages award of $3

million in lost profits. We affirm.

Background. In reviewing a judgment notwithstanding the

verdict, "we consider the facts and inferences therefrom in the

light most favorable to the plaintiff to determine if 'anywhere

in the evidence, from whatever source derived, any combination

of circumstances could be found from which a reasonable

inference could be drawn in favor of the plaintiff.'" Phelan v.

May Dep't Stores Co., 60 Mass. App. Ct. 843, 844 (2004), quoting

Stapleton v. Macchi, 401 Mass. 725, 728 (1988). We recite the

facts in that light, reserving certain details for discussion of

specific issues.

In August 2017, Revoli submitted a bid for the project.

Mark Elbag, the city's director of engineering, and Antonio da

Cruz, a vice-president at Tighe & Bond, Inc. (Tighe & Bond), an

engineering firm,1 were present at the bid opening for the

project. Though neither Elbag nor da Cruz had firsthand

experience with Revoli they had a conversation at the bid

opening in which at least one of them raised concerns about

Revoli's being difficult to work with.2

1 The city hired Tighe & Bond to act as an engineer for the project. Tighe & Bond's duties included evaluating the bids the city received.

2 Elbag testified that da Cruz told him that "[h]e had concerns about Revoli," related to "general trouble through the

2 Revoli was the low bidder on the project. That same

morning, Elbag sent an e-mail message to Paul Moosey, the city's

commissioner of public works and parks, to inform him that

Revoli was the low bidder. Moosey, who also had no firsthand

experience with Revoli, responded, "What else for bad news."

Later that day, da Cruz emailed his colleagues at Tighe & Bond,

writing that the "[c]ity doesn't want Revoli so we're going to

inquire about Chicopee's approach to baring [sic] them."

Following these communications, Tighe & Bond began its

review process, which involved contacting cities and towns that

the bidders had previously worked with, filling out evaluation

forms, and drafting a recommendation letter to Moosey. The city

requested that the recommendation letter evaluate the bid

information for the three low bidders, which were Revoli, P.

Gioioso & Sons, Inc. (Gioioso), and RJV Construction Corp.

(RJV). Tighe & Bond's recommendation letter ultimately

concluded that "Revoli has not demonstrated that they are the

lowest responsible and eligible bidder." More specifically, the

letter opined that Revoli did not have the requisite experience

and ability to complete a construction contract as large as the

project. The recommendation letter also summarized Revoli's

construction process." Da Cruz testified that Elbag "voiced concerns about Revoli."

3 reference evaluations and found that "many contacted references

indicated a propensity to excessive change orders, unreasonable

change order requests, litigation and some would not recommend

Revoli for a project with difficult construction." Notably, the

recommendation letter contained no negative reference

information about the second and third lowest bidders -- Gioioso

and RJV.

After Tighe & Bonde completed its review, Moosey

recommended to the city manager that he reject Revoli's bid and

award the project to Gioioso, which the city manager did.

Discussion. 1. Jury instruction on presumption of good

faith. The city first argues that the trial judge erred by not

instructing the jury on the presumption of good faith and by not

applying the presumption in his denial of the city's motions for

a directed verdict and judgment notwithstanding the verdict. We

disagree.

"When reviewing jury instructions to which there has been

an objection, we conduct a two-part test: whether the

instructions were legally erroneous, and (if so) whether that

error was prejudicial" (quotation and citation omitted). Main

v. R.J. Reynolds Tobacco Co., 100 Mass. App. Ct. 827, 834

(2022). "In examining whether an instruction adequately

explain[s] the applicable law, we consider the adequacy of the

instructions as a whole" (quotations and citations omitted).

4 Governo Law Firm LLC v. Bergeron, 487 Mass. 188, 194 (2021).

"An error in jury instructions is not grounds for setting aside

a verdict . . . unless the result might have differed absent the

error." Id., quoting Blackstone v. Cashman, 448 Mass. 255, 270

(2007).

To be sure, public officials are presumed to act in good

faith. See Nantasket Beachfront Condominiums, LLC v. Hull

Redev. Authority, 87 Mass. App. Ct. 455, 464 (2015). But "a

presumption, using the word in its technical and proper sense,

can have no operative effect unless it assists the party having

the burden of proof." Epstein v. Boston Hous. Authority, 317

Mass. 297, 302 (1944).

Here, the presumption of good faith in favor of the city

had no operative effect because Revoli always had the burden of

proving that the city acted in bad faith. See Modern Cont.

Constr. Co. v. Massachusetts Port Authority, 369 Mass. 825, 828

(1976) (bidder bears burden of proving awarding authority "acted

in bad faith or in an arbitrary or unreasonable manner").

Instead, the presumption was "merely a restatement that the

burden of persuasion . . . from the outset" was on Revoli

(quotation and citation omitted). General Elec. Co. v.

Assessors of Lynn, 393 Mass. 591, 598 (1984). Thus, it was not

5 legally erroneous for the trial judge not to instruct the jury

on the presumption of good faith.3

2. Motions for directed verdict and judgment

notwithstanding the verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Engineering Corp. v. City of Fitchburg
329 N.E.2d 128 (Massachusetts Supreme Judicial Court, 1975)
Blake v. Commissioner of Correction
532 N.E.2d 671 (Massachusetts Supreme Judicial Court, 1989)
Stapleton v. MacChi
519 N.E.2d 273 (Massachusetts Supreme Judicial Court, 1988)
Pheasant Ridge Associates Ltd. Partnership v. Town of Burlington
506 N.E.2d 1152 (Massachusetts Supreme Judicial Court, 1987)
Modern Continental Construction Co. v. Massachusetts Port Authority
343 N.E.2d 362 (Massachusetts Supreme Judicial Court, 1976)
Nantasket Beachfront Condominiums, LLC v. Hull Redevelopment Authority
32 N.E.3d 318 (Massachusetts Appeals Court, 2015)
Buffalo-Water 1, LLC v. Fidelity Real Estate Company, LLC
111 N.E.3d 266 (Massachusetts Supreme Judicial Court, 2018)
Spiegel v. Beacon Participations, Inc.
8 N.E.2d 895 (Massachusetts Supreme Judicial Court, 1937)
Epstein v. Boston Housing Authority
58 N.E.2d 135 (Massachusetts Supreme Judicial Court, 1944)
General Electric Co. v. Board of Assessors
472 N.E.2d 1329 (Massachusetts Supreme Judicial Court, 1984)
Ayash v. Dana-Farber Cancer Institute
822 N.E.2d 667 (Massachusetts Supreme Judicial Court, 2005)
Blackstone v. Cashman
860 N.E.2d 7 (Massachusetts Supreme Judicial Court, 2007)
O'Brien v. Pearson
868 N.E.2d 118 (Massachusetts Supreme Judicial Court, 2007)
Baudanza v. Comcast of Massachusetts I, Inc.
912 N.E.2d 458 (Massachusetts Supreme Judicial Court, 2009)
Fordyce v. Town of Hanover
457 Mass. 248 (Massachusetts Supreme Judicial Court, 2010)
Petricca Construction Co. v. Commonwealth
640 N.E.2d 780 (Massachusetts Appeals Court, 1994)
Northeast Reclamation Corp. v. Town of Wareham
766 N.E.2d 560 (Massachusetts Appeals Court, 2002)
Phelan v. May Department Stores Co.
806 N.E.2d 939 (Massachusetts Appeals Court, 2004)
Brewster Wallcovering Co. v. Blue Mountain Wallcoverings, Inc.
864 N.E.2d 518 (Massachusetts Appeals Court, 2007)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Revoli Construction Co., Inc. v. City of Worcester., Counsel Stack Legal Research, https://law.counselstack.com/opinion/revoli-construction-co-inc-v-city-of-worcester-massappct-2026.