Paul Sardella Construction Co. v. Braintree Housing Authority

356 N.E.2d 249, 371 Mass. 235, 1976 Mass. LEXIS 1157
CourtMassachusetts Supreme Judicial Court
DecidedOctober 21, 1976
StatusPublished
Cited by40 cases

This text of 356 N.E.2d 249 (Paul Sardella Construction Co. v. Braintree Housing Authority) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paul Sardella Construction Co. v. Braintree Housing Authority, 356 N.E.2d 249, 371 Mass. 235, 1976 Mass. LEXIS 1157 (Mass. 1976).

Opinion

Hennessey, C.J.

A judge of the Superior Court ruled, as matter of law, that the Braintree Housing Authority (authority) 2 was liable in damages for breach of contract to Paul Sardella Construction Co., Inc. (Sardella), for wrongfully rescinding the award to Sardella of a contract for the construction of a State-aided housing project for the elderly. 3 The matter was reported to the Appeals Court pursuant to Mass. R. Civ. P. 64, 365 Mass. 831 (1974), for determination of the correctness of the trial judge’s rulings. The Appeals Court rendered a decision, holding that the reported rulings were correct. Paul Sardella Constr. Co. *237 v. Braintree Housing Authority, 3 Mass. App. Ct. 326 (1975). The case was ordered remanded to the Superior Court for determination of the monetary damages to be assessed against the authority in accordance with the Appeals Court’s further holding that the proper measure of damages was the reasonable cost to Sardella of preparing its bid on the project. Both Sardella and the authority petitioned the Appeals Court for a rehearing of the case, which petitions were denied. We allowed the authority’s petition for leave to obtain further appellate review. Mass. R. A. P. 27.1, 365 Mass. 875 (1975).

We summarize the facts, as stated in the opinion of the Appeals Court, ‘3 Mass. App. Ct. at 327-328, and obtained originally from a stipulation of the parties.

Sometime prior to September 15, 1971, the authority invited bids pursuant to the provisions of the fair competition for bidders of public works act (G. L. c. 149, §§ 44A-44L) for the construction of a State-aided housing project for the elderly. Thereafter, the bids of the subcontractors were opened, with the defendant Mazza found to be the lowest responsible and eligible bidder for the plumbing subcontract. Mazza’s subbid was unrestricted with respect to its willingness to enter into a subcontract with any general contractor. On September 15, 1971, the bids of the general contractors were opened, with Sardella found to be the lowest responsible and eligible general bidder. Sardella listed Mazza as its plumbing subcontractor, as did the second lowest bidder. The defendant Findlen, the third lowest bidder, listed Duggan Construction Co., Inc., as its plumbing subcontractor.

On September 29, 1971, Mazza wired the authority purporting to withdraw its subbid on the basis of an alleged clerical error, and confirmed that action by a letter sent the following day.

On October 20, 1971, the authority voted to award the contract to Sardella as the lowest responsible and eligible general bidder. See G. L. c. 149, § 44A. The award was subject to the approval of the Department of Community Affairs. See G. L. c. 121B, § 31. On October 26, 1971, Sar *238 della notified Mazza that it had been selected by the authority as the subcontractor and on November 15 sent Mazza proper subcontracts for its signature.

Mazza failed to execute the subcontracts within five days (G. L. c. 149, § 441 [3]) and returned the unexecuted subcontracts to Sardella on November 22, 1971, notifying Sardella and the authority of its refusal to execute “due to a bona fide clerical error” in its bid.

Thereafter, the authority reviewed all the other eligible and responsible plumbing subbids and determined that if any one of those bids was to be substituted in place of Mazza’s, Findlen’s bid would be the lowest general bid. The authority then voted on November 24,1971, to rescind its award of the general contract to Sardella and to award that contract to Findlen. Sardella was not invited to nor was it represented at the meeting at which such votes were taken. A notice of the decision was mailed to Sardella, and it immediately lodged a protest with the Department of Labor and Industries, which conducted an investigation and held a conference on December 7, 1971. See G. L. c. 149, § 44K. On January 7, 1972, that department rendered its decision upholding the action of the authority in awarding the general contract to Findlen.

At a meeting held on December 15, 1971, the authority found that “a bona fide clerical error had been made by Mazza” and voted to return Mazza’s deposit (which it subsequently did). See G. L. c. 149, § 44B (3). Sardella was not notified of that meeting.

On January 20, 1972, the authority and Findlen executed a contract for the project. The contract was approved by the Department of Community Affairs. Findlen has been paid the contract price, with the exception of a small amount held back pending the completion of certain seeding operations.

Both Sardella and Findlen were eligible and responsible bidders at all material times. 4

*239 We conclude that there was no error. In reaching that conclusion we agree with the result, and in general we agree with the reasoning, of the Appeals Court. However, we expand somewhat on the analysis of the Appeals Court in support of our determination that § 441 (3) is applicable. This extended discussion is recommended because of the ambiguities of the language in two subsections of the statute, as well as the obvious importance to the public and the parties in other cases of the application of the proper statutory provisions in a situation of this type with its potential for recurrence.

Preliminarily, we observe that Sardella could not prevail, at least in the circumstances of this case, if it were determined that § 441 (2) were controlling. That section is obviously designed to cause review of the lowest responsible general bid in the public interest, and with a view toward economy. This is to be accomplished, if at all, by substitution of subbidders, but the language of the section is not mandatory and hardly seems supportive of a claim like Sardella’s in this case (e.g., the substitution is to be by “agreement” and the parties are to “jointly consider”). Further, in the stipulation of facts proffered by the parties in this case, there is no information from which this court could infer that a substitution of subbidders, whether concerned with plumbing or other trades, would restore Sardella as lowest responsible general bidder. By contrast, application of § 441 (3) protects Sardella’s position after disappearance of the subbidder Mazza, and permits only an adjustment of the contract price.

The trial judge framed the crucial issue in this case in this way: “[W]here a sub-bidder of the lowest responsible and eligible general bidder refuses to execute his subcontract, should the procedures of G. L. c. 149, § 441 (2) 5 or *240 §441 (3) 6 be followed?” (emphasis supplied; footnotes added). He concluded that § 441 (3) was the controlling section on the facts of the case, primarily because § 441 (2) could not, in his view, have been applicable for several reasons. The judge acknowledged that there were problems with the application of § 441 (3), but he nevertheless considered the result more equitable than if § 441 (2) were held to apply.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Caesars Massachusetts Management Co. v. Crosby
778 F.3d 327 (First Circuit, 2015)
Abdow v. Attorney General
468 Mass. 478 (Massachusetts Supreme Judicial Court, 2014)
Mello Construction, Inc. v. Division of Capital Asset Management
999 N.E.2d 1091 (Massachusetts Appeals Court, 2013)
Orion Technical Resources, LLC v. Los Alamos National Security, LLC
2012 NMCA 97 (New Mexico Court of Appeals, 2012)
Annese Electrical Services, Inc. v. City of Newton
730 N.E.2d 290 (Massachusetts Supreme Judicial Court, 2000)
Natick Auto Sales, Inc. v. Department of Procurement & General Services
715 N.E.2d 84 (Massachusetts Appeals Court, 1999)
White's Farm Dairy, Inc. v. City of New Bedford
10 Mass. L. Rptr. 348 (Massachusetts Superior Court, 1999)
Lawrence Brunoli, Inc. v. Town of Branford
722 A.2d 271 (Supreme Court of Connecticut, 1999)
E.D.S. Federal Corp. v. System Development Corp.
8 Mass. L. Rptr. 691 (Massachusetts Superior Court, 1998)
In Re Carl Corp. v. State, Department of Education
946 P.2d 1 (Hawaii Supreme Court, 1997)
Cataldo Ambulance Service, Inc. v. City of Chelsea
680 N.E.2d 937 (Massachusetts Appeals Court, 1997)
E. Amanti & Sons, Inc. v. Town of Barnstable
679 N.E.2d 1028 (Massachusetts Appeals Court, 1997)
Construction Industries of Massachusetts, Inc. v. City of Peabody
6 Mass. L. Rptr. 615 (Massachusetts Superior Court, 1997)
Environmental Waste Technology, Inc. v. Commonwealth
5 Mass. L. Rptr. 135 (Massachusetts Superior Court, 1995)
Planning & Design Solutions v. City of Santa Fe
885 P.2d 628 (New Mexico Supreme Court, 1994)
Petricca Construction Co. v. Commonwealth
640 N.E.2d 780 (Massachusetts Appeals Court, 1994)
School Building Committee v. Commercial Union Insurance
638 N.E.2d 499 (Massachusetts Appeals Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
356 N.E.2d 249, 371 Mass. 235, 1976 Mass. LEXIS 1157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paul-sardella-construction-co-v-braintree-housing-authority-mass-1976.