Environmental Waste Technology, Inc. v. Commonwealth

5 Mass. L. Rptr. 135
CourtMassachusetts Superior Court
DecidedNovember 30, 1995
DocketNo. 956203F
StatusPublished

This text of 5 Mass. L. Rptr. 135 (Environmental Waste Technology, Inc. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Waste Technology, Inc. v. Commonwealth, 5 Mass. L. Rptr. 135 (Mass. Ct. App. 1995).

Opinion

Lauriat, J.

Plaintiff Environmental Waste Technology, Inc. (“EWT’) seeks a preliminary injunction enjoining the defendant Massachusetts Highway Department (“MHD”) from entering into a contract with defendant GZA Geoenvironmental Technologies, Inc. (“GZA”) related to the Central Artery/Tunnel Project (“CA/T Project”). As the basis for its request for injunctive relief, EWT contends that awarding the contract in question to GZA would violate various statutory prohibitions against conflicts of interest in bidding for public works contracts. For the following reasons, the plaintiffs motion for preliminary injunction is ALLOWED.

BACKGROUND

In June 1995, the Commonwealth of Massachusetts, through the MHD, solicited bids for Project No. C25A2, entitled “Oil and Hazardous Materials Incident Response” (“C25A2”). The bids were solicited pursuant [136]*136to G.L.c. 30, §39M. C25A2 is one of a number of projects which comprise Boston’s federally funded CA/T Project. Seven bids were received for the C25A2 contract. EWT’s bid was $90,230 higher than GZA’s low bid. The estimated cost of the project was $5,000,000, although the actual bids were substantially below that figure.

The C25A2 contract requires the successful bidder to provide environmental emergency response services for unexpected discoveries of oil or hazardous materials, underground storage tanks or other environmental hazards not yet identified in the CA/T Project right-of-way. The C25A2 contractor must provide these services under the direction of the MHD’s management consultant for the CA/T Project, Bechtel/Parsons Brinkerhoff (“B/BP”). Camp, Dresser and McKee, Inc. (“CDM”) will provide direct oversight of the C25A2 services in the field.

Prior to the awarding of the C25A2 contract, a “Right-of-Way Assessment and Remediation Services” field investigation was conducted throughout the CA/T alignment by CDM under CA/T Project No. M025A (“M025A”). The C25A2 contract is derived from the activities undertaken under the general scope of the M025A contract. The purpose of the M025A field investigation was to identify contaminated soils within the CA/T Project right-of-way which require special handling and disposal as determined by the Massachusetts Department of Environmental Protection. Soils so identified are classified as “clearance soil” and removal of these soils is the responsibility of CA/T Project mainline contractors. The C25A2 contract does not cover the remediation of hazards identified through the M025A activities.

GZA, a consultant on at least seven CA/T Projects, performed several duties on the M025A project. Under the M025A contract, GZA, as a consultant to CDM, performed site reconnaissance, the monitoring of soil borings and groundwater wells, and the collection of soil and groundwater samples. GZA also prepared reports containing boring logs, details of monitoring well installation, and chain-of-custody records for samples delivered for analysis by others. The exact nature of the material and data collected and retained solely by GZA is unclear as the availability of the documentary information remains a point of contention between the parties.

Perceiving a conflict of interest on GZA’s'part in acting as a consultant on the M025A contract and then bidding on the C25A2 contract, EWT notified the MHD on several occasions of this potential bidding irregularify. The MHD, after conducting its own evaluation, concluded there was no conflict and expressed its willingness to award the contract to GZA. In response, EWT filed a bid protest with the Office of the Attorney General Fair Labor and Business Practices Division pursuant to G.L.c. 149, §44H. After a hearing, the Attorney General’s Office denied EWT’s bid protest on November 2, 1995.

On October 6 and 13, 1995, at approximately the same time as it was engaged in correspondence with the MHD with regard to the potential violation of public works bidding procedures, EWT made requests, pursuant to the Public Records Act (“PRA”), for certain documents related to or generated under the M025A contract. G.L.c. 66, §10. The requested materials included the boring logs and progress reports related to GZA’s work under the M025A contract. At the time of hearing, MHD had not complied with all of the PRA requests by EWT.

Upon receipt of the Attorney General’s decision and after failing to obtain the documents it requested, EWT filed this action for injunctive relief and a declaratory judgment against MHD and GZA for alleged violations of G.L.c. 268A, §l(q), G.L.c. 30, §39M, 23 C.F.R. §1.33, and G.L.c. 29, §8B & 29F, as well as an alleged failure to comply with the PRA. A hearing on EWTs motion for a preliminary injunction was held on November 16, 1995.

DISCUSSION

‘The issuance of a preliminary injunction generally rests within the sound discretion of the Judge, after a combined evaluation of the moving party’s likelihood of success on the merits, its claim of injury, and finally a balancing of the competing harms to each party.” General Accident Ins. Co. of America v. Bank of New England-West, N.A., 403 Mass. 473, 475 (1988), citing Packaging Industries Group, Inc. v. Cheney, 380 Mass. 609, 615 (1980). “When the dispute is not between private parties, however, the court should also consider the risk of harm to the public interest.” Biotti v. Board of Selectmen of Manchester, 25 Mass.App.Ct. 637, 640 (1988).1

A preliminary injunction is a drastic remedy that the court should not grant unless the movant, by a clear showing, carries its burden of persuasion. Wright & Miller, 11 Federal Practice & Procedure, §2948 (1973). If the moving party can demonstrate that an injunction is necessary to prevent irreparable harm to it and that granting an injunction poses no substantial risk of harm to the opposing party, a substantial possibility of success on the merits warrants issuing the injunction. Packaging Industries, 380 Mass. at 617 n.12.

I

“(I]n the absence of bad faith, a bidder wrongfully deprived of a contract may recover only his bid preparation costs.” Peabody Construction Co. v. Boston, 28 Mass.App.Ct. 100, 105 (1989), citing Paul Sardella Constr. Co. v. Braintree Hous. Auth., 371 Mass. 235, 243 (1976). Therefore, if the C25A2 contract is awarded to GZA, without rebidding or other reconsideration of the award, EWT’s opportunity “for consideration as a bidder would be forever lost, and its remedy at law for the damages incurred in preparing its bid falls far short of being the equivalent of the potential to win the contract.” Modern Continental Construction Co. v. Lowell, 391 Mass. 829, 837 (1984). Thus, for the purposes of this motion, the court ac[137]*137cepts EWT’s contention that it would suffer irreparable harm if the injunction it seeks is not granted.

II.

EWT further contends that it has a reasonable likelihood of prevailing on the merits of this case because GZA has violated, inter alia, the conflict of interest provisions of G.L.c. 268A, §l(q) and MHD, in turn, will violate G.L.c. 30, §39M by awarding the contract to an ineligible bidder.

As a threshold matter, the parties have offered conflicting interpretations as to whether the conflict of interest strictures of G.L.c. 268A, §l(q) apply to GZA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Engineering Corp. v. City of Fitchburg
329 N.E.2d 128 (Massachusetts Supreme Judicial Court, 1975)
Starr v. Board of Health of Clinton
252 N.E.2d 893 (Massachusetts Supreme Judicial Court, 1969)
Modern Continental Construction Co. v. Lowell
465 N.E.2d 1173 (Massachusetts Supreme Judicial Court, 1984)
Packaging Industries Group, Inc. v. Cheney
405 N.E.2d 106 (Massachusetts Supreme Judicial Court, 1980)
Biotti v. Board of Selectmen of Manchester
521 N.E.2d 762 (Massachusetts Appeals Court, 1988)
Board of Selectmen of Avon v. Linder
227 N.E.2d 359 (Massachusetts Supreme Judicial Court, 1967)
Peabody Construction Co. v. City of Boston
546 N.E.2d 898 (Massachusetts Appeals Court, 1989)
Paul Sardella Construction Co. v. Braintree Housing Authority
356 N.E.2d 249 (Massachusetts Supreme Judicial Court, 1976)
Gil-Bern Construction Corp. v. City of Brockton
233 N.E.2d 197 (Massachusetts Supreme Judicial Court, 1968)
Majestic Radiator Enclosure Co. v. County Commissioners of Middlesex
397 Mass. 1002 (Massachusetts Supreme Judicial Court, 1986)
General Accident Insurance Co. of America v. Bank of New England-West, N.A.
403 Mass. 473 (Massachusetts Supreme Judicial Court, 1988)
E. A. Berman Co. v. City of Marlborough
419 N.E.2d 319 (Massachusetts Appeals Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
5 Mass. L. Rptr. 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-waste-technology-inc-v-commonwealth-masssuperct-1995.