E. Amanti & Sons, Inc. v. Town of Barnstable

679 N.E.2d 1028, 42 Mass. App. Ct. 773, 1997 Mass. App. LEXIS 123
CourtMassachusetts Appeals Court
DecidedJune 2, 1997
DocketNo. 96-P-128
StatusPublished
Cited by12 cases

This text of 679 N.E.2d 1028 (E. Amanti & Sons, Inc. v. Town of Barnstable) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. Amanti & Sons, Inc. v. Town of Barnstable, 679 N.E.2d 1028, 42 Mass. App. Ct. 773, 1997 Mass. App. LEXIS 123 (Mass. Ct. App. 1997).

Opinion

Kass, J.

As if to demonstrate that no good deed goes unpunished, the town of Barnstable encouraged women and minority subcontractor participation in a public construction job on which it invited bids and then rejected a low subcontractor’s bid on the ground that the inclusion of women’s participation as provided was an “addition [in the bid response] not called for.” A judge of the Superior Court concluded that the subcontractor’s bid violated G. L. c. 149, § 44F, that the town acted lawfully in rejecting it, and that the subcontractor was not entitled to damages. The subcontractor appealed from a judgment for the town.

These are the pertinent facts. In early 1993, Barnstable [774]*774invited written bids for the construction of a middle school. See G. L. c. 149, §§ 44A and 44B. The project involved seventeen filed subtrades. E. Amanti & Sons, Inc. (Amanti), the plaintiff, was the low bidder in the heating, air conditioning, and ventilation (HVAC) subtrade and the successful general contractor bidder, in its bid, carried Amanti’s HVAC sub-bid.

Before the opening of bids, the town addressed to subcontractors a series of “addenda” to the bid invitation on the subject of participation by enterprises that women or members of a minority group controlled. Addendum No. 2,1 issued March 12, 1993, “encouraged” filed subcontractors to subcontract portions of their work to “SOMBA2 approved W/MBE3 subcontractors.” For that purpose, the town declared the availability of supplementary sub-bid forms and added, “The total amount subcontracted, except for any amounts properly listed in Paragraph E of the form for sub-bids, may not exceed 20% of the sub-bid price.”

In the relative arcana of compulsory sub-bidding in Massachusetts, a paragraph E sub-sub-bid refers to subtrades that are identified in the specifications as ones for which the bidder shall list a sub-subcontractor unless the subcontractor customarily performs that class of work. See G. L. c. 149, § 44F(3), 4th par. For the HVAC work, the anticipated sub-sub-bids were four: sheet metal, automatic temperature controls, mechanical insulation, and testing/adjusting/ balancing.

Addendum No. 3, issued two days later, on March 12, 1993, made women and minority participation mandatory, but that requirement had a short life as on March 15, 1993, an Addendum No. 4 issued, deleting the mandatory W/MBE. Addendum No. 4 added the following:

“As stated in Item 4 of Addendum No. 2, ‘Filed subcontractors are encouraged to subcontract portions [775]*775of their work to SOME A approved W/MBE subcontractors. Supplementary sub-bid forms are available to all filed sub-bidders to list W/MBE subcontractors with whom they will sub-contract and the dollar amount or percentage of those proposed subcontracts.’ The forms referred to are those documents Usted in and provided with Addendum No. 3, under Item 3.”

Albeit the precatory word, “encouraged,” a prospective subcontractor could be forgiven for thinking that the flurry of directives meant that the town desired W/MBE participation and would smile upon a bid that included it. A responding subcontractor could also reasonably understand that the cross reference in Addendum No. 4 to Addendum No. 2 incorporated the sentence that placed a limit of 20% on W/MBE participation through sub-subcontractors, exclusive of the designated paragraph E categories. Amanti thought so and with its low bid furnished a letter of intent — on a form furnished by the town — with McCarthy Mechanical, Inc., a SOMWBA certified women’s business, that McCarthy would furnish supplementary labor and materials for the piping system for a price of $240,000. That amount constituted 16% of Amanti’s bid for the HVAC work.

Barnstable and the general contractor cheerfully embraced Amanti’s bid but two other sub-bidders, including the next to lowest sub-bidder, protested the award of the HVAC subcontract to Amanti to the Department of Labor and Industries (DOLI).4 The ground of protest was that Amanti’s tender of participation by McCarthy was an “addition [to the bid response] not called for.” If language has any meaning, that could not literally be so. Barnstable, having “encouraged” W/MBE participation could hardly say that a positive response in that regard was “uncalled” for.

Sophisticates in the mysteries and nuances of the public bidding process are not, however, so easily misled by the ap[776]*776parently sensible. DOLI ruled that the hitch in Amanti’s inclusion of W/MBE participation was that the town’s inclusion of such a request violated G. L. c. 149, § 44F, that Amanti’s affirmative response necessarily also violated that statute, and, for that reason, was “an addition not called for.” Section 44F does not in express terms forbid a subcontractor from fulfilling its obligation to furnish specified labor and materials through the medium of sub-subcontractors, but such a prohibition has been drawn by DOLI from language in § 44F(1) that requires a “subcontractor to install all materials to be furnished by him” under the relevant specifications. There is support for reading a limitation on sub-subcontracting into § 44F in that the inclusion of an express provision for sub-subcontracting the designated “paragraph E” subtrades (described above) implies the exclusion of other sub-sub-bidding. Harborview Residents’ Comm., Inc. v. Quincy Hous. Authy., 368 Mass. 425, 432 (1975). Livoli v. Zoning Bd. of Appeals of Southborough, post 921, 923 (1997). We have found no cases on the point, and the conclusion that a subcontractor on a public job cannot perform its obligations through subcontracted labor is not self evident from the statu-toiy text. All the parties, however, have agreed that both the town’s request for W/MBE participation and Amanti’s proffer of it via McCarthy Mechanical, Inc., were a violation of § 44F. We continue our consideration of the case on that basis.

As Amanti’s bid violated § 44F, Barnstable was bound to reject it unless the deviation was minor or solely matter of form. Gil-Bern Constr. Corp. v. Brockton, 353 Mass. 503, 505-506 (1968). Modern Continental Constr. Co. v. Lowell, 391 Mass. 829, 840 (1984). J. D’Amico, Inc. v. Worcester, 19 Mass. App. Ct. 112, 115 & n.5 (1984). In analyzing the significance of the deviation we concentrate on the purposes of the public bidding system and on the view of the town of the importance of the W/MBE request in its bidding process.

A first objective of the competitive bidding process prescribed by G. L. c. 149, §§ 44A-44J, is to obtain the lowest price from a responsible contractor. Interstate Engr. Corp. v. Fitchburg, 367 Mass. 751, 757 (1975). The focus of controversy, the proffer of the W/MBE participation, did not interfere with the goal of the public authority getting the best price for the HVAC work; Amanti’s bid was the lowest. [777]*777Second, the bidding process is to be an open one in which all who participate do so under the same published rules. Here, the encouragement to provide W/MBE participation, by the reference to Addendum No. 2 up to 20% of the sub-bid price, was contained uniformly in the bid documents received by all competitors. The introduction by Amanti of the W/MBE proffer was not a side deal on a bid component that no other bidder knew about.5 Contrast Interstate Engr. Corp. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abdow v. Attorney General
468 Mass. 478 (Massachusetts Supreme Judicial Court, 2014)
Mello Construction, Inc. v. Division of Capital Asset Management
999 N.E.2d 1091 (Massachusetts Appeals Court, 2013)
INTERNATIONAL SALT CO., LLC v. City of Boston
547 F. Supp. 2d 62 (D. Massachusetts, 2008)
Correctional Medical Services, Inc. v. Department of Correction
22 Mass. L. Rptr. 572 (Massachusetts Superior Court, 2007)
Diebold Election Systems, Inc. v. Galvin
22 Mass. L. Rptr. 301 (Massachusetts Superior Court, 2007)
Northeast Reclamation Corp. v. Town of Wareham
766 N.E.2d 560 (Massachusetts Appeals Court, 2002)
Sci-Tech Construction Co. v. Town of Milford
14 Mass. L. Rptr. 410 (Massachusetts Superior Court, 2002)
Commonwealth v. DeCicco
744 N.E.2d 95 (Massachusetts Appeals Court, 2001)
Citizens for Citizens, Inc. v. Lambert
12 Mass. L. Rptr. 35 (Massachusetts Superior Court, 2000)
Atlas Elevator Service, Inc. v. Thyssen Elevator (New England), Inc.
11 Mass. L. Rptr. 472 (Massachusetts Superior Court, 2000)
White's Farm Dairy, Inc. v. City of New Bedford
10 Mass. L. Rptr. 348 (Massachusetts Superior Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
679 N.E.2d 1028, 42 Mass. App. Ct. 773, 1997 Mass. App. LEXIS 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-amanti-sons-inc-v-town-of-barnstable-massappct-1997.