JJ Associates, Inc. v. Fall River Housing Authority

471 N.E.2d 400, 19 Mass. App. Ct. 45, 1984 Mass. App. LEXIS 1860
CourtMassachusetts Appeals Court
DecidedDecember 3, 1984
StatusPublished
Cited by4 cases

This text of 471 N.E.2d 400 (JJ Associates, Inc. v. Fall River Housing Authority) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JJ Associates, Inc. v. Fall River Housing Authority, 471 N.E.2d 400, 19 Mass. App. Ct. 45, 1984 Mass. App. LEXIS 1860 (Mass. Ct. App. 1984).

Opinion

Cutter, J.

This controversy relates to a project for renovations at the Fall River Housing Authority’s (Authority) Sunset Hill Project. Bids for the project were sought under the provisions of G. L. c. 149, §§ 44A-44H. The “Instructions to Bidders” contained, among others, the following provisions: “14. AWARD OF CONTRACT. The Contract will be awarded . . . to the lowest responsible and eligible bidder. Such award shall be made within thirty working days after HUD approval. . . . 22. GOVERNMENTAL APPROVAL. Awards and contracts may be subject to the approval of the Federal Government.” See as to the inclusion of these provisions, G. L. c. 149, § 44(A)(3). The advertisement for bids pointed out that “[t]he award of this contract will take place following the execution by . . . HUD of the annual contribution contract.”2

[47]*47Plumbing subbids for the renovation work were opened on October 26, 1983. The bid of Montle Plumbing and Heating Co., Inc. (Mantle) was the low bid at $1,194,700. The bid3 of JJ Associates, Inc. (JJ) at $1,250,000, was the second lowest. When the general bids were opened on November 2, 1983, the bid ($10,795,000) of R.J. Marshall, Inc. (Marshall) was the lowest. Marshall had included in its own general bid JJ’s subbid as the plumbing component of the general bid.

Marshall, on November 4, 1983, notified JJ that Marshall intended to enter into a plumbing subcontract with JJ as soon as the Authority should award it a contract. On November 8, 1983, the Authority, by Martin Zenni, its acting executive director, wrote to Marshall calling its attention to what is now G. L. c. 149, § 44F(4)(6), as appearing in St. 1980, c. 579, § 55.4 Zenni’s letter then proceeded, “the [b]udget for this [48]*48project is very . . . tight. It is therefore respectfully requested that you [Marshall] consider using the low sub-bidder for ‘plumbing’ in order to save $55,300.” A copy of this letter was sent to the United States Department of Housing and Urban Development (HUD).

On November 14, 1983, the Authority purported to award to Marshall the general contract for the project by its Resolution No. 135 for a total amount of $10,795,000. The Authority’s chairman was authorized, “subject to the approval of” HUD, to execute the then proposed general contract. On the same day, the Authority and Marshall each executed a contract for the project work for this amount in which JJ was shown as the plumbing subcontractor at its bid price. By art. 5 of this contract the advertisement for bids and bidding documents were incorporated in the general contract by reference.5 There took place about this time correspondence summarized in the margin.6

The Authority’s board, on November 21, 1983, after a telephone poll, voted that Marshall “be instructed to substitute the [49]*49sub-bid of Montle ... for the subbid of” JJ, on the basis that “Mantle ... is the lowest responsible sub-bidder and that an appropriate reduction of $55,300 be made in the overall [project] bid price.” On that day, also, the Authority’s chairman issued a news release to the same effect. Zenni, for the Authority, on November 21, 1983, wrote to Marshall that the latter was “instructed to substitute the subbid of Montle . . . for” JJ’s subbid, and “to make a reduction of $55,300 in . . . [its] overall general bid price, for a new total of $10,739,700.” At a meeting of the Authority’s members on November 25, 1983, a resolution was adopted which (1) “accepted” Marshall’s bid as revised by the substitution of Montle’s plumbing subbid, thus reducing the over-all contract price to $10,739,700, and (2) directed the submission of the general contract as revised to Marshall for execution by it. That contract was apparently executed by the Authority and Marshall on November 25, 1983, subject to HUD approval, which (dated December 6, 1983) was received on December 8 or 9, 1983. A plumbing subcontract between Montle and Marshall was executed on November 28, 1983.7

On November 22, 1983, JJ notified the Authority that it objected to the substitution of Montle as the subcontractor for plumbing, and on November 30, 1983, JJ filed a protest with the Department of Labor and Industries. This was heard (see G. L. c. 149, § 44H) by a senior departmental counsel, who sustained JJ’s protest essentially for the reason that, in his opinion, the Authority’s statutory right to compel Marshall [50]*50to accept substitution of Montle (as the plumbing subcontractor) ended when the Authority and Marshall signed the unrevised general contract of November 14, 1983, which listed JJ as the plumbing subcontractor at its original bid. Despite the Department’s ruling on JJ’s protest, the Authority proceeded with its revised general contract, and Marshall went forward with its plumbing subcontract with Montle.

JJ filed this complaint on January 5, 1984, seeking various forms of injunctive and declaratory relief, especially a declaration that the Authority and Marshall had entered into a binding general contract on November 14,1983, and that the Authority could not direct Marshall to substitute Montle as a plumbing subcontractor after that date. The pleadings were completed promptly. Montle was allowed to intervene as a party. Essentially the facts already stated above were established by admissions in the pleadings or by affidavit.

A Superior Court judge on February 17, 1984, denied JJ’s motion for summary judgment and declared (a) that Marshall never entered into a binding agreement with JJ to perform the plumbing work on the project, and (b) that the Authority in obtaining substitution of Montle (for JJ) acted in a manner consistent with its responsibility. The judgment dissolved all outstanding injunctions against proceeding with the project, and ordered that Marshall proceed with it at the revised price. JJ appealed.8

1. General Laws c. 149, § 44F(4)(b) and § 44E(2), see note 4, supra, contemplate that an awarding authority may compel the substitution of qualified subbidders for subbidders initially selected by the general contractor. See Roblin Hope Indus., Inc. v. J.A. Sullivan Corp., 6 Mass. App. Ct. 481, 483-489 (1978). There is no contention by Marshall or any other party in this case that Montle is not a plumbing contractor qualified to perform the plumbing subcontract. From pars. 14 and 22 of the Instructions to Bidders, mentioned in the first paragraph [51]*51of this opinion, JJ, the Authority, and Marshall were placed on notice that the award of the general contract was subject to HUD’s approval. From the Roblin Hope decision, JJ was bound to recognize that the Authority could force Marshall to accept a lower plumbing subbid, unless Marshall had some reasonable objection to the responsibility and standing of the substituted subbidder. Consequently, the execution of the general contract of November 14, 1983, by the Authority and Marshall was necessarily subject to the possibilities (a) that HUD might not approve that contract at all, and (b) that the Authority might require Marshall to substitute subbids more favorable to it. We do not accept the conclusion of the Department of Labor and Industries that the contract signed on November 14 became effective immediately and irrevocably before the substitution of Monde was effected. See Johnson Controls, Inc. v. School Comm. of Boston, 17 Mass. App. Ct. 1039, 1040 (1984).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. Amanti & Sons, Inc. v. Town of Barnstable
679 N.E.2d 1028 (Massachusetts Appeals Court, 1997)
Kelley Marine Transport Corp. v. Boston Sand & Gravel
2 Mass. L. Rptr. 545 (Massachusetts Superior Court, 1994)
Empire Masonry Corp. v. Town of Franklin
555 N.E.2d 603 (Massachusetts Appeals Court, 1990)
Chicopee Concrete Service, Inc. v. Hart Engineering Co.
479 N.E.2d 748 (Massachusetts Appeals Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
471 N.E.2d 400, 19 Mass. App. Ct. 45, 1984 Mass. App. LEXIS 1860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jj-associates-inc-v-fall-river-housing-authority-massappct-1984.