James J. Welch & Co. v. Deputy Commissioner of Capital Planning & Operations

387 Mass. 662
CourtMassachusetts Supreme Judicial Court
DecidedDecember 2, 1982
StatusPublished
Cited by37 cases

This text of 387 Mass. 662 (James J. Welch & Co. v. Deputy Commissioner of Capital Planning & Operations) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James J. Welch & Co. v. Deputy Commissioner of Capital Planning & Operations, 387 Mass. 662 (Mass. 1982).

Opinion

Nolan, J.

This is an action for declaratory relief under -G. L. c. 231A and for relief in the nature of mandamus under G. L. c. 249, § 5, brought against the deputy commissioner of the Division of Capital Planning and Operations [663]*663(DCPO), a State agency, and against the DCPO itself. The action was filéd in the county court. The plaintiffs, James J. Welch & Co., Inc. (Welch), and a joint venture organization composed of The Volpe Construction Co., Inc.; Dimeo Construction Company; Daniel O’Connell’s Sons, Inc.; and Gutierrez Construction Co., Inc. (VDOG), were successful general bidders on contracts awarded by the Bureau of Building Construction (BBC), a State agency.3 Welch’s contract, awarded in 1979, was for work on the Walter E. Fernald State School; VDOG was awarded a contract in 1980 for work on the State Transportation Building. At issue is whether former G. L. c. 149, § 441 (l),4 required the DCPO to allow the plaintiffs additional “expenses and profits” based on adjustments to the general contract prices caused by the BBC’s substitution of filed subbidders for [664]*664allowances which it had required the plaintiffs to carry in their general bids.5 We hold that it did not.

The statutorily prescribed general bid form in use at the relevant times was divided into two parts to distinguish the amount allocated to the general bidder and that allocated to the subbidders it would use.6 The general bidder was required to list in Item 2 the details of all the subbids it intended to use, as well as any allowances in lieu of subbids which the awarding agency had required. The general bidder was required to include in Item 1 the total cost of the “work of the general contractor, being all work other than that covered by Item 2.” G. L. c. 149, § 44F, as amended through St. 1961, c. 604, § 5. In addition to the actual cost of labor and materials for such work, the general bidder would include in Item 1 his bond costs and his markup for expenses and profit. The “contract price” would be the sum of the Item 1 price and the Item 2 price.

Former G. L. c. 149, § 441 (1), provided that, in the event the awarding agency caused a subbidder to be substituted for an allowance which it had previously required the general bidder to carry in Item 2 of its general bid, “the contract price shall be adjusted by the difference between the subcontract sum and the amount stated in the addendum. The general bidder shall include under Item 1 of the general bid form all expenses and profits on account of such adjustments.”7

[665]*665At the time the plaintiffs’ bids were to be submitted, the BBC had not established a list of qualified subbidders for some of the subtrades. Accordingly, the BBC sent out addenda specifying the allowances to be made in Item 2 of the general bids for these categories. The plaintiffs incorporated these allowances in their successful bids. In each instance, the final subbid price which was substituted for these allowances was a figure in excess of the allowance. The BBC subsequently adjusted the plaintiffs’ contract prices to reflect the differences. It also adjusted the Item 1 prices to account for increases in the bond premiums the plaintiffs were obligated to pay. When the BBC refused to allow increases in the Item 1 prices for “expenses and profits”8 resulting from the adjustments,9 the plaintiffs brought this action before a single justice of this court who reserved and reported the case to the full bench.10

There is no disagreement about the purposes of the competitive bidding statute, former G. L. c. 149, §§ 44A-44L. [666]*666As we have noted before: “We discern two fundamental, complementary legislative objectives underlying the competitive bidding statute. First, the statute enables the public contracting authority to obtain the lowest price for its work that competition among responsible contractors can secure. . . . Second, the statute establishes an honest and open procedure for competition for public contracts and, in so doing, places all general contractors and subbid-ders on an equal footing in the competition to gain the contract.” Interstate Eng’g Corp. v. Fitchburg, 367 Mass. 751, 757-758 (1975). We must, of course, construe the statute to effectuate the objectives of its framers. Id. at 757. We are not free, however, simply to excise disputed language from its statutory context and interpret it according to those perceived objectives. “It is elementary that the meaning of a statute must, in the first instance, be sought in the language in which the act is framed, and if that is plain, . . . the sole function of the courts is to enforce it according to its terms.” Caminetti v. United States, 242 U.S. 470, 485 (1917). While we think that the last sentence of § 441 (1), standing alone, is less than plain as to when expenses and profits are to be included in Item 1, any indefiniteness is clarified by reference to the statutory context.

General Laws c. 149, § 441 (1), mandated that the “general bidder shall include under Item 1 of the general bid form all expenses and profits on account of . . . adjustments.” In the preceding sentence of the statute, the term “general contractor” was used to describe the person who either was to contract with the “lowest responsible and eligible subbidder” whom he found unobjectionable or was to negotiate with the awarding agency concerning the sum to be paid to a replacement subcontractor. Though the terms were not defined in the statute, the term “general contractor” was consistently used to describe only that “general bidder” whose general bid was selected. G. L. c. 149, § 44A, as amended through St. 1977, c. 968 (“If the general bidder selected as the general contractor . . .”); G. L. c. 149, § 44B (3), as amended through St. 1961, c. 604, § 2 [667]*667(same); G. L. c. 149, § 44F (“[T]he general contractor shall be selected on the basis of . . . general bids”). Obviously, a general bidder could not be selected as the general contractor before he submitted his general bid.11 Thus, by requiring the “general bidder” to include expenses and profits in his general bid, the Legislature indicated that this inclusion was to take place when the general bid was submitted. Otherwise, it would have used the term “general contractor” as it did in the preceding sentence.12

When we look to other specific provisions for adjustments to either the contract or item prices, a pattern emerges which we think further indicates that adjustments to Item 1 for “expenses and profits” based on subsequent adjustments to the contract price were not intended. Section 441 (2) and (3) provided that, in the event it became necessary to substitute a new subbidder for one listed in the general bid,13 the [668]*668contract price would be adjusted by the difference between the new subbid price and the price of the one previously listed. There were no provisions for including in Item 1 the expenses and profits based on these adjustments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DiGiulio v. Director of the Department of Unemployment Assistance
113 N.E.3d 850 (Massachusetts Appeals Court, 2018)
Commonwealth v. Dalton
5 N.E.3d 1206 (Massachusetts Supreme Judicial Court, 2014)
Commonwealth v. Ventura
987 N.E.2d 1266 (Massachusetts Supreme Judicial Court, 2013)
Adams v. Adams
945 N.E.2d 844 (Massachusetts Supreme Judicial Court, 2011)
Brasi Development Corp. v. Attorney General
925 N.E.2d 826 (Massachusetts Supreme Judicial Court, 2010)
Commonwealth v. Boe
924 N.E.2d 239 (Massachusetts Supreme Judicial Court, 2010)
Commonwealth v. Gillis
861 N.E.2d 422 (Massachusetts Supreme Judicial Court, 2007)
Commonwealth v. Kneram
826 N.E.2d 733 (Massachusetts Appeals Court, 2005)
Commonwealth v. Mandell
811 N.E.2d 1045 (Massachusetts Appeals Court, 2004)
Swift v. AutoZone, Inc.
441 Mass. 443 (Massachusetts Supreme Judicial Court, 2004)
Commonwealth v. Gavin G.
772 N.E.2d 1067 (Massachusetts Supreme Judicial Court, 2002)
Annese Electrical Services, Inc. v. City of Newton
730 N.E.2d 290 (Massachusetts Supreme Judicial Court, 2000)
Atlas Elevator Service, Inc. v. Thyssen Elevator (New England), Inc.
11 Mass. L. Rptr. 472 (Massachusetts Superior Court, 2000)
John T. Callahan & Sons, Inc. v. City of Malden
713 N.E.2d 955 (Massachusetts Supreme Judicial Court, 1999)
Liability Investigative Fund Effort, Inc. v. Massachusetts Medical Professional Insurance
636 N.E.2d 1317 (Massachusetts Supreme Judicial Court, 1994)
Norfolk Electric, Inc. v. Fall River Housing Authority
629 N.E.2d 967 (Massachusetts Supreme Judicial Court, 1994)
Civitarese v. Town of Middleborough
591 N.E.2d 1091 (Massachusetts Supreme Judicial Court, 1992)
Fedele v. School Committee of Westwood
587 N.E.2d 757 (Massachusetts Supreme Judicial Court, 1992)
Bynes v. School Committee of Boston
581 N.E.2d 1019 (Massachusetts Supreme Judicial Court, 1991)
Massachusetts Community College Council MTA/NEA v. Labor Relations Commission
522 N.E.2d 416 (Massachusetts Supreme Judicial Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
387 Mass. 662, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-j-welch-co-v-deputy-commissioner-of-capital-planning-mass-1982.