Klein v. Catalano

437 N.E.2d 514, 386 Mass. 701, 1982 Mass. LEXIS 1561
CourtMassachusetts Supreme Judicial Court
DecidedJuly 7, 1982
StatusPublished
Cited by232 cases

This text of 437 N.E.2d 514 (Klein v. Catalano) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Klein v. Catalano, 437 N.E.2d 514, 386 Mass. 701, 1982 Mass. LEXIS 1561 (Mass. 1982).

Opinion

Abrams, J.

This case raises the issue of the application and constitutionality of G. L. c. 260, § 2B, 2 a statute that places a time limit on the liability of architects and contractors. General Laws c. 260, § 2B, is not a statute of limitations but a statute of repose. A statute of limitations normally governs the time within which legal proceedings must be commenced after the cause of action accrues. See, e.g., Franklin v. Albert, 381 Mass. 611, 618-619 (1980). A statute of repose, however, limits the time within which an action may be brought and is not related to the accrual of any cause of action. The injury need not have occurred, much less have been discovered. See, e.g., Rosenberg v. North Bergen, 61 N.J. 190, 199-200 (1972). As a statute of repose, G. L. c. 260, § 2B, precludes recovery against those within the protection of the statute for any injury which occurs more than six years after the performance or furnishing of the design, planning, construction, or general administration of an improvement to real property. Simply put, after six years, the statute completely eliminates a cause of action against certain persons in the construction industry. 3

*703 Since G. L. c. 260, § 2B, abolishes a cause of action in tort, the following issues arise: (1) whether G. L. c. 260, § 2B, may be applied to work completed prior to its effective date, and if so, whether the application of G. L. c. 260, § 2B, in those circumstances violates the due process guarantees of the United States or Massachusetts Constitutions; (2) whether, on its face, G. L. c. 260, § 2B, violates the equal protection and due process guarantees of the Federal or State Constitutions and the right to a remedy by recourse to the laws guaranteed by the Massachusetts Constitution; and (3) whether G. L. c. 260, § 2B, may bar a claim alleging breach of express or implied warranties.

We hold that the Legislature intended that G. L. c. 260, § 2B, apply to claims involving work completed before the statute took effect. We also believe that the application of G. L. c. 260, § 2B, in these circumstances is consistent with the due process guarantees of the Massachusetts and United States Constitutions. In addition, we think that, on its face, G. L. c. 260, § 2B, does not violate the due process and equal protection guarantees of the State and Federal Constitutions and the right to a remedy by recourse to the laws guaranteed by the Massachusetts Constitution. Finally, we conclude that G. L. c. 260, § 2B, bars the plaintiff’s warranty claims, because in this case, the elements of these claims are identical to this claim of negligence.

We summarize the facts. In February, 1963, the defendant Eduardo F. Catalano agreed to design a student center on the Massachusetts Institute of Technology (M.I.T.) campus. Catalano completed and delivered all design drawings and other documents in July, 1963. By October, 1965, M.I.T. *704 accepted and occupied the building. After September, 1967, Catalano did not perform any additional services in connection with the student center. In July, 1968, the Legislature enacted G. L. c. 260, § 2B, as appearing in St. 1968, c. 612, to be effective October, 1968.

The plaintiff, Gary Klein, claims that he was injured on April 23,1976, while leaving the Harvard Cooperative Society “Tech Coop” located in the student center. The injuries allegedly occurred when the outer door struck him and caused the plate glass panels of the door to shatter. The glass allegedly cut and damaged the nerves in his hand.

In February, 1979, the plaintiff commenced this action against Catalano individually and Eduardo F. Catalano Architects and Engineers, Inc. (Architects and Engineers), claiming negligence on the part of both Catalano and Architects and Engineers, and breach of express and implied warranties by Architects and Engineers. Prior to trial, the defendants filed motions for summary judgment claiming that G. L. c. 260, § 2B, barred the plaintiff’s claims. 4 See Mass. R. Civ. P. 56 (b), 365 Mass. 824 (1974). In support of their motions, the defendants filed three exhibits: the plaintiff’s complaint, Catalano’s agreement with M.I.T., and Catalano’s affidavit stating that Architects and Engineers never performed any services in connection with the “Tech Coop.” After a hearing, a judge of the Superior Court allowed the defendants’ motions based on G. L. c. 260, § 2B. Pursuant to Mass. R. Civ. P. 54 (b), 365 Mass. 820 (1974), another judge ordered the entry of final judgment for the defendants. The plaintiff appeals.

1. Application of G. L. c. 260, § 2B, to torts arising out of work in connection with improvements to real property completed prior to the statute’s effective date.

a. Statutory argument. The plaintiff claims that the judge erred in granting the defendants’ motions for summary judgment, because the Legislature did not intend that *705 G. L. c. 260, § 2B, apply to work in connection with improvements to real property completed prior to the statute’s effective date. We disagree.

Elementary rules of statutory construction require us to look to the statutory language itself as the principal source of insight into the legislative purpose. Hoffman v. Howmedica, Inc., 373 Mass. 32, 37 (1977). We construe the words of the statute according to their “usual and natural meaning.” Commonwealth v. Gove, 366 Mass. 351, 354 (1974). Commonwealth v. Thomas, 359 Mass. 386, 387 (1971).

General Laws c. 260, § 2B, as amended by St. 1973, c. 777, § 2, provides that “[ajctions of tort for damages arising out of any deficiency or neglect in the design, planning, construction or general administration of an improvement to real property shall be commenced only within three years next after the cause of action accrues; provided, however, that in no event shall such actions be commenced more than six years after the performance or furnishing of such design, planning, construction or general administration.” The statute does not depend on the date of the improvement to real property but depends on the time the design, planning, construction, or general administration of the improvement to real property was furnished. We hold that G. L. c. 260, § 2B, applies to this action, although the defendants completed their work before the statute took effect.

b. Constitutional argument.. The plaintiff claims that the judge erred in granting the defendants’ motions for summary judgment, because application of the statute to work completed prior to the statute’s effective date violates the due process guarantees of the United States and Massachusetts Constitutions. In making this argument, the plaintiff assumes that the application of G. L. c. 260, § 2B, in those circumstances is retroactive. We do not agree with the plaintiff’s assumption that the application of the statute is retroactive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greene v. Philip Morris USA Inc.
Massachusetts Supreme Judicial Court, 2023
DUANE ALVES v. ROBERT COHAN & Others.
Massachusetts Appeals Court, 2023
ADAM C. SMITH v. ANDREW DIVOLL (and a companion case ).
101 Mass. App. Ct. 144 (Massachusetts Appeals Court, 2022)
JOAN MORAN & another v. CAROLYN BENSON & others.
100 Mass. App. Ct. 744 (Massachusetts Appeals Court, 2022)
Penn-America Insurance Co. v. Bay State Gas Co.
Massachusetts Appeals Court, 2019
Summers v. Cabela's Wholesale, Inc.
Superior Court of Delaware, 2019
Sisson v. Lhowe
954 N.E.2d 1115 (Massachusetts Supreme Judicial Court, 2011)
Stetter v. R.J. Corman Derailment Services, L.L.C.
2010 Ohio 1029 (Ohio Supreme Court, 2010)
Brown v. United States
514 F. Supp. 2d 146 (D. Massachusetts, 2007)
Federal Insurance v. Boston Water & Sewer Commission
514 F. Supp. 2d 130 (D. Massachusetts, 2007)
Greczyn v. Colgate-Palmolive
869 A.2d 866 (Supreme Court of New Jersey, 2005)
Sonin v. Massachusetts Turnpike Authority
809 N.E.2d 1075 (Massachusetts Appeals Court, 2004)
LAKEVIEW v. Apartment Sales Corp.
6 P.3d 74 (Court of Appeals of Washington, 2000)
Mi-Lor Corp. v. Gottsegen (In Re Mi-Lor Corp.)
233 B.R. 608 (D. Massachusetts, 1999)
R.J. Longo Construction Co. v. Transit America, Inc.
921 F. Supp. 1295 (D. New Jersey, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
437 N.E.2d 514, 386 Mass. 701, 1982 Mass. LEXIS 1561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/klein-v-catalano-mass-1982.