Trustees of Boston University v. Clough, Harbour & associates llp

CourtMassachusetts Supreme Judicial Court
DecidedApril 16, 2025
DocketSJC-13685
StatusPublished

This text of Trustees of Boston University v. Clough, Harbour & associates llp (Trustees of Boston University v. Clough, Harbour & associates llp) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trustees of Boston University v. Clough, Harbour & associates llp, (Mass. 2025).

Opinion

SUPREME JUDICIAL COURT

TRUSTEES OF BOSTON UNIVERSITY vs. CLOUGH, HARBOUR & ASSOCIATES LLP

Docket: SJC-13685
Dates: February 5, 2025 - April 16, 2025
Present: Budd, C.J., Gaziano, Kafker, Wendlandt, Georges, Dewar, & Wolohojian, JJ.
County: Suffolk
Keywords: Repose, Statute of. Contract, Indemnity, Architectural services, Performance and breach. Indemnity. Practice, Civil, Summary judgment

            Civil action commenced in the Superior Court Department on July 2, 2020.

            The case was heard by Michael J. Pineault, J., on a motion for summary judgment.

            The Supreme Judicial Court granted an application for direct appellate review.

            Michael T. Sullivan (William F. Burke also present) for the plaintiff.

            Eric A. Howard (Thomas D. Duquette, Jr., & Shaun D. Loughlin also present) for the defendant.

            David J. Hatem, Jon C. Cowen, Kelly Martin Malone, & Dillon Aisenberg, for American Council of Engineering Companies of Massachusetts, amicus curiae, submitted a brief.

            WENDLANDT, J.  The defendant, Clough, Harbour & Associates LLP (CHA or architect), agreed to design a new athletic field for the plaintiff, Trustees of Boston University (university).  These sophisticated parties specifically negotiated the terms of an express indemnification provision pursuant to which CHA promised to indemnify the university for "any and all" expenses incurred by the university as a result of the architect's "negligen[t]" design. 

            Unfortunately, a defect in CHA's design caused the university to incur expenses to fix the field in order to render it usable for its intended purpose.  Pursuant to the indemnification provision, the university submitted the bill for its expenses to CHA; CHA declined to pay.  More than six years after the field first opened, the university brought the present action against CHA for breach of the indemnification provision.

            This case presents the question whether G. L. c. 260, § 2B (tort statute of repose), which bars "[a]ction[s] of tort" for damages arising out of a design defect in an improvement to real property six years after the opening of the improvement to use, bars the university's contract claim.  Concluding that it does not, we reverse the decision of the Superior Court judge allowing summary judgment in favor of CHA.[1]

            1.  Background.  a.  Facts.  The material facts are largely undisputed; we view the facts in the light most favorable to the nonmoving party, here, the university.  See Gibney v. Hossack, 493 Mass. 767, 768 (2024); Dorchester Mut. Ins. Co. v. Miville, 491 Mass. 489, 492 (2023) ("The standard of review of a grant of summary judgment is whether, viewing the evidence in the light most favorable to the nonmoving party, all material facts have been established and the moving party is entitled to judgment as a matter of law" [citation omitted]).

            On June 25, 2012, the university and CHA entered into a contract pursuant to which, in exchange for approximately $970,000, CHA agreed to design a synthetic turf athletic field for the university; the field was to be located above a parking structure also to be designed by CHA.  The contract included an indemnification provision specifically negotiated by the parties.[2]  Pertinent to our analysis, it provided:  "To the fullest extent permitted by law, [CHA] shall indemnify . . . [the university] . . . from and against any and all . . . expenses, including, but not limited to, reasonable attorney's fees, to the extent caused . . . by the negligence of [CHA]."

            The new athletic field hosted its first sporting event on August 31, 2013.  From the onset, however, the university experienced numerous problems with the field because of defects in its design.  Briefly, CHA's design failed to account for seasonal expansion in the joists of the parking structure; this resulted in depressions in the field that rendered it unsafe for hosting athletic events.

            The university incurred more than $25,000 in expenses to render the field usable as an athletic field.  Pursuant to the indemnification provision, the university demanded that CHA indemnify it for the expenses.  CHA declined.  More than six years after the university first started using the field, the university sued CHA for breach of the indemnification provision.[3]

            b.  Prior proceedings.  CHA moved for summary judgment on the basis that the tort statute of repose, which eliminates a cause of action in tort six years after the opening of an improvement to real estate, see note 4, infra, barred the university's indemnification claim.  Relying on the Appeals Court's unpublished decision in University of Mass. Bldg. Auth. v. Adams Plumbing & Heating, Inc., 102 Mass. App. Ct. 1107 (2023), a Superior Court judge allowed the motion.  The university timely appealed. 

            2.  Discussion.  a.  Standard of review.  We review the allowance of a motion for summary judgment, as well as questions of statutory construction, de novo.  See Gibney, 493 Mass. at 770; Conservation Comm'n of Norton v. Pesa, 488 Mass. 325, 331 (2021). 

            b.  Tort statute of repose.  CHA argues that the tort statute of repose[4] operates to bar the university's indemnification claim, which indisputably was filed more than six years after the opening of the athletic field, because, although the claim ostensibly is based in the parties' contract, the contractual provision requires CHA to indemnify the university for CHA's negligence, and a negligence action is itself an action in tort. 

            By the statute's plain terms, the tort statute of repose "does not apply to contract actions," and "expressly provides a limitation only for actions of tort."  Klein v. Catalano, 386 Mass. 701, 718 (1982).  See Patel v. 7-Eleven, Inc., 489 Mass. 356, 362 (2022), S.C., 494 Mass. 562 (2024) (clear and unambiguous statutory language is conclusive of legislative intent).  That the university has styled its claim as one for breach of "contract" is not dispositive, however; instead, we look beyond such labels to examine the "gist of the action" to determine whether the tort statute of repose bars the claim.  See Anthony's Pier Four, Inc. v. Crandall Dry Dock Eng'rs, Inc., 396 Mass. 818, 823 (1986), quoting Hendrickson v. Sears, 365 Mass. 83, 85 (1974) (party may not "escape the consequences of [the tort] statute of repose . . . merely by labelling the claim as contractual").  See also Gomes v. Pan Am. Assocs., 406 Mass. 647, 648 (1990) (examining gist of action to enforce express indemnification and determining it was contractual and not barred by tort statute of repose).

            "A key difference between an action in tort and an action in contract is that in the latter, 'the standard of performance is set by the defendants' promises, rather than imposed by law.'"  Bridgwood v. A.J. Wood Constr., Inc., 480 Mass. 349, 355 (2018), quoting Anthony's Pier Four, Inc., 396 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hendrickson v. Sears
310 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1974)
McDonough v. Marr Scaffolding Co.
591 N.E.2d 1079 (Massachusetts Supreme Judicial Court, 1992)
Anthony's Pier Four, Inc. v. Crandall Dry Dock Engineers, Inc.
489 N.E.2d 172 (Massachusetts Supreme Judicial Court, 1986)
Klein v. Catalano
437 N.E.2d 514 (Massachusetts Supreme Judicial Court, 1982)
Bridgwood v. A.J. Wood Construction, Inc.
105 N.E.3d 224 (Massachusetts Supreme Judicial Court, 2018)
Gomes v. Pan American Associates
549 N.E.2d 1134 (Massachusetts Supreme Judicial Court, 1990)
John T. Callahan & Sons, Inc. v. Worcester Insurance
453 Mass. 447 (Massachusetts Supreme Judicial Court, 2009)
Donovan v. Philip Morris USA, Inc.
455 Mass. 215 (Massachusetts Supreme Judicial Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Trustees of Boston University v. Clough, Harbour & associates llp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trustees-of-boston-university-v-clough-harbour-associates-llp-mass-2025.