Van Sicklin v. Nantucket Surveyors, LLC

111 N.E.3d 1113
CourtMassachusetts Appeals Court
DecidedOctober 23, 2018
Docket17-P-1514
StatusPublished

This text of 111 N.E.3d 1113 (Van Sicklin v. Nantucket Surveyors, LLC) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Van Sicklin v. Nantucket Surveyors, LLC, 111 N.E.3d 1113 (Mass. Ct. App. 2018).

Opinion

The plaintiffs, James L. Van Sicklin and Amy B. Van Sicklin, sought damages for breach of contract and negligence against the defendant, Nantucket Surveyors, LLC (NSL), stemming from a failed septic system. A Superior Court judge allowed NSL's motion for summary judgment as to all of the plaintiffs' claims, and subsequently denied the plaintiffs' motion for reconsideration. The plaintiffs now appeal therefrom. For the reasons that follow, we affirm.

Background. We first recite the relevant facts from the summary judgment record, and provide a framework of applicable law. In December, 2009, NSL conducted an inspection and soil investigation at the premises located at 32 Polpis Road, Nantucket, MA (property), which Gary Gregoire and Beth Simonsis (sellers) owned at the time. Gregoire hired NSL to determine soil conditions and to determine if the property's septic system complied with State Sanitary Code Title V (Title V) as required by the Massachusetts board of health. NSL determined that the septic system at the property was not in compliance with Title V and submitted a proposal to Gregoire to design a replacement septic system, conduct an "as-built inspection (open hole and installation)," and file a septic permit application with the Nantucket board of health. Gregoire accepted NSL's proposal and also hired RJ Perry Excavation, LLC (RJ Perry) to perform the excavation and installation of the new septic system.

The plaintiffs and sellers executed an escrow agreement on December 18, 2009, requiring a portion of the purchase price of the property to be held in escrow to pay for the installation, inspection, and certification of the new septic system.

NSL prepared a design plan for the replacement septic system, which explains NSL's obligations as it related to the as-built inspection (open hole and installation) that was referenced in the proposal. The design plan required NSL, in part, to: (1) "inspect the overexcavation prior to fill material and infiltrators being installed"; (2) "inspect and locate the installed system"; and (3) "[a]fter the initial inspection ... call the Nantucket [b]oard of [h]ealth for a final inspection." The design plan also states that "[o]nly after the final inspection is approved by the [b]oard of [h]ealth shall the system components be backfilled" and that "unsuitable soils shall be removed" and replaced with sand. The contract at issue consists of the proposal and the design plan.

The septic system was subsequently installed, and on March 30, 2010, the Nantucket board of health issued a certificate of compliance, indicating the septic system's compliance with Title V. In December, 2014, the septic system failed. The parties agree that "placement of construction and other debris in the leaching fields of the septic system by RJ Perry in violation of applicable regulations and NSL's plan" caused the system to fail.

The plaintiffs filed suit in the Superior Court against NSL and RJ Perry, alleging that NSL was liable for breach of contract and negligence as a result of its failure to inspect RJ Perry's work and ensure that RJ Perry used sand in the leaching fields in accordance with NSL's design.3 NSL moved for summary judgement and the judge concluded that the contract at issue did not, as a matter of law, require NSL to inspect the fill installed by the contractor and that to establish a duty to inspect under a negligence theory, the plaintiffs needed to present expert evidence, which they did not do. The plaintiffs then filed a motion for reconsideration, which the judge denied. This appeal followed.

Discussion. Summary judgment is appropriate if there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. See Federal Nat'l Mtge. Ass'n v. Hendricks, 463 Mass. 635, 637 (2012). See also Mass. R. Civ. P. 56 (c), as amended, 436 Mass. 1404 (2002). We review grants of summary judgment de novo. See Verdrager v. Mintz, Levin, Cohn, Ferris, Glovsky & Popeo, P.C., 474 Mass. 382, 395 (2016). "[W]e view the evidence and draw all reasonable inferences in the light most favorable to the nonmoving party." Premier Capital, LLC v. KMZ, Inc., 464 Mass. 467, 475 (2013).

1. Breach of contract claim. The plaintiffs first contest the judge's determination on summary judgment that NSL did not have a contractual duty to inspect the fill material. They claim that the judge could only reach this conclusion through speculation as the record did not support this interpretation of the as-built inspection requirement. We disagree.

The plain language of the proposal requires NSL to conduct an as-built inspection (open hole and installation). There is nothing in the proposal that requires NSL to inspect the fill materials used to cover the hole. See Citation Ins. Co. v. Gomez, 426 Mass. 379, 381 (1998) (where words of contract are unambiguous, they are construed in their ordinary and usual sense). The plaintiffs respond that the proposal must be read in conjunction with the design plan, which carries with it an inherent duty to inspect the septic system to ensure that it was "as-built" in accordance with the "as-built plans." Although we agree that the design plan was part of the contract, the design plan specifies that NSL was responsible for conducting two inspections. The first occurred, as the design plan required, after RJ Perry excavated the open hole and before the septic system was installed. The second inspection, as the design plan further required, occurred after RJ Perry installed the septic system into the hole.4 The design plan further provided that "[o]nly after the final inspection is approved by the [b]oard of [h]ealth shall the system components be backfilled." Thus, by its plain terms, the design plan contemplated two inspections by NSL, after which the board of health would conduct a "final inspection," after which RJ Perry was to backfill the completed project. Neither the proposal nor the design plan obligated NSL to conduct a third inspection after the board of health conducted its final inspection and issued its approval. Where, as here, the language of the contract is clear, we cannot add an unstated obligation thereto. See Robbins v. Krock, 73 Mass. App. Ct. 134, 138-139 (2008), quoting Rogaris v. Albert, 431 Mass. 833, 835 (2000) ("the court gives full effect to all the terms expressed by the parties.... It is not the role of the court to alter the parties' agreement").

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stewart v. Worcester Gas Light Co.
170 N.E.2d 330 (Massachusetts Supreme Judicial Court, 1960)
Commonwealth v. Domanski
123 N.E.2d 368 (Massachusetts Supreme Judicial Court, 1954)
Klein v. Catalano
437 N.E.2d 514 (Massachusetts Supreme Judicial Court, 1982)
Lembo v. Waters
294 N.E.2d 566 (Massachusetts Appeals Court, 1973)
Verdrager v. Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.
50 N.E.3d 778 (Massachusetts Supreme Judicial Court, 2016)
Lexington Insurance v. All Regions Chemical Labs, Inc.
647 N.E.2d 399 (Massachusetts Supreme Judicial Court, 1995)
Citation Insurance v. Gomez
426 Mass. 379 (Massachusetts Supreme Judicial Court, 1998)
Rogaris v. Albert
730 N.E.2d 869 (Massachusetts Supreme Judicial Court, 2000)
LeBlanc v. Logan Hilton Joint Venture
463 Mass. 316 (Massachusetts Supreme Judicial Court, 2012)
Federal National Mortgage Ass'n v. Hendricks
977 N.E.2d 552 (Massachusetts Supreme Judicial Court, 2012)
Premier Capital, LLC v. KMZ, Inc.
984 N.E.2d 286 (Massachusetts Supreme Judicial Court, 2013)
Atlas Tack Corp. v. Donabed
712 N.E.2d 617 (Massachusetts Appeals Court, 1999)
Estorban v. Massachusetts Bay Transportation Authority
68 Mass. App. Ct. 911 (Massachusetts Appeals Court, 2007)
Robbins v. Krock
896 N.E.2d 633 (Massachusetts Appeals Court, 2008)
Kostrzewa v. Suffolk Construction Co.
897 N.E.2d 1272 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
111 N.E.3d 1113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/van-sicklin-v-nantucket-surveyors-llc-massappct-2018.